CM - Cost Estimates (Detailed) Flashcards

1
Q

For recapping purposes, what happens to the variation of actual costs from the cost estimate as the project definition increases?

A

Gets closer to the actual project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is the direct cost evaluated in a detailed cost etimate?

A

Using a bill of quantities and unit rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the equation of the total indirect cost?

A

Total direct cost * Overheads %

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the equation of the detailed construction cost of a proejct?

A

(Total direct + indirect cost) * Location adjustment * Inflation factor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the typical percentage of the indirect cost to the direct cost?

A

2.5 - 10 %

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the typical percentage of the mark-up?

A

2 - 3 % of the construction cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the total detailed cost of a project?

A

Construction cost + contingency cost + mark-up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the most time-consuming aspect of a detailed cost estimate?

A

Using a bill of quantities and unit rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the equation of an activity cost?

A

Price of unit quantity of work ( e.g. pounds per meter cubed ) * Quantity of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does total direct cost equal?

A

Cost of activity 1 + 2 ….

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the step-by-step process for coming up with a detailed cost estimate?

A

1 - WBS
2 - Record quantities and units associated with each activity
3 - Associate cost with each item
4 - Calculate activity cost
5 - Sum activity costs together

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does a bill of quantities describe?

A

Material and labour work itemised.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the prime cost?

A

Cost of raw materials for unit quantity of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the material rate equal?

A

Prime cost + Ancillary material costs (nails, screws, waste, etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the total rate the sum of?

A

Labour rate + plant rate + material rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly