Class 4 Flashcards
Define: Process design
Decisions about how production of goods or services is to occur
Define: Line Balancing
The process of assigning taks to workstations in such a way as to ensure that the different workstations have approximately equal time requirements
What is automation? Name and describe 3 types
Automation - use of machinery with sensing and control devices that enable it to operate automatically
1) Fixed - very rigid, high cost
2) Programmable - high cost, general purpose eqpt controlled by a computer program
3) Flexible - computer-assisted design/manufacture (CAD,CAM), computer-integrated manufacturing (CIM), Flexible manufacturing systems (FMS)
Advantages and Disadvantages of Automation
Advantages - ensures low variability in production process
-eliminates dirty, tedious or dangerous jobs
Disadvantages - often costly, inflexible, difficult to integrate with rest of operation
- usually requires high volume to justify
- often replaces labour with high-skilled service jobs to install and maintain automated eqpt
Why do we need to do line balancing?
To plan and sequence an overall operational process that will minimize idle time, ensure high labour utilization
List 4 main types of manufacturing process with examples
1) Job Shop ex appliance repair, emergency room
2) Batch ex commercial bakery, classroom lecture
3) Repetitive ex automotive assembly, car wash
4) Continuous ex refinery, water purification
List 3 basic types of facility layout. Describe.
1) Product - uses standardized processing operations to achieve smooth, rapid, high volume flow ex production or assembly line
2) Process - uses non-standardized processing for items that require a variety of different production processes, have discontinuous workflow, frequent adjustments to machinery, etc ex machine shops, services
3) Cellular - machines grouped in a cell to process part families
what is the equation for cycle time?
CT=OT/D ex 480 min per day/ 48 units per day = 10 min per unit = CT of 10min
What is the equation for Theoretical # of workstation on a line?
Nmin=∑t/CT ex 50/10=5
What is the equation for Idle Time?
Idle Time (%)= Idle Time/ (N X CT)
What is the equation for Efficiency?
Efficiency (%)= 1 - Idle Time %
Calculation - line balancing