Cheonggyecheon River Restoration Project Flashcards
What is the population of Seoul?
Over 10 million
When was the Cheonggyecheon project stated?
In 2003
How much did the project cost?
£281 Million
How much of the river was restored?
5.8km
Why was the project needed? 3 reasons
To create opportunities
To improve connectivity
For businesses
What were dismantled for the project?
The elevated freeway and concrete deck covering the stream
Where was water pumped from for a consistent flow?
Nearly Hanang river
What did the 1st zone consist of?
Seating throughout to encourage public to use the space
What did the 2nd zone consist of?
Recreational areas
What are 3 social factors of the project?
Improved parking
Promoted businesses
Public services
What are 3 economic factors of the project?
Property prices rise 2x than elsewhere
Number of businesses increased
A tourist attraction
Where was this project?
South Korea
What are 3 environmental factors of the project?
Re-established habitats
Species reappeared
Improvements in quality
What are 3 political factors of the project?
President included project in his bid in 2001
Committies took responsibility for opinions
Experts were concerned that the removal of highway would increase congestion