Chapter 9 - Calculation and budgeting Flashcards

1
Q

Project cost

A

Costs for the resources in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Product cost

A

Related to materials needed to produce the product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Lifecycle cost

A
  • All costs arising during all phases of a product’s lifecycle
  • Often discussed in larger projects or investments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Top Down

A

A rough estimate of costs by comparison with similar projects already executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Self-costing estimate

A
  • Based on the idea that the project should bear all its own costs
  • Both direct (can be attributed to a certain activity/cost unit) and indirect (overhead, common to several cost units) costs should be included
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bottom Up

A

Detailed calculation based on a careful analysis of each activity in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Internal pricing

A
  • Might be hard to distribute indirect costs

- You should evaluate work efforts and other resources in the fairest way possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contribution estimate

A
  • Based on project being burdened only with the cost that arise if the project is preformed, so-called specific costs
  • Useful in prioritising between different courses of action
  • Alternative with largest contribution margin should be chosen
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Specific revenue

A

The revenue that arises through execution of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Specific cost

A

The cost that arises through execution of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you calculate the Contribution margin?

A

Specific revenue - Specific cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Describe Income - expenditure

A
  • Income arises at the time of sale
  • Expenditure arises at the time of purchase
  • For external reporting and tax calculations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe Revenue - cost

A
  • Distributed incomes and expenditures
  • Value created of consumed during a certain period
  • Financial result = Revenue - Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe Payment - disbursement

A
  • Occur at the time of cast receipt

- When an invoice or other bill is paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pre-estimates

A
  • Connect the project estimates to the schedule
  • Items in budget should be possible to connect to activities and resources
  • Estimating cost for each activity in the schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Variable costs are

A

Affected by volume

17
Q

Fixed costs are

A

Independent

18
Q

Cost estimates in agile projects

A
  • Cost for each sprint is fixed
  • Because sprint length is set and staffing of team should not be changed
  • Project cost is determined by number of Scrum teams working on the project and number of sprints to achieve the goal

Calculation of cost for scrum team on p. 220

19
Q

Accrual-basis accounting

A
  • Advance estimate should be based on it, presented in table or graphically, in chart, to be used during execution
  • Schedule and estimated activity costs are important information sources in order to enable it
20
Q

Resource histogram

A

Provides overview of the distribution of project costs over time

21
Q

A projects S-curve or Cost baseline

A

Visual presentation of the advanced estimate, as shown on p. 221

22
Q

Methods most suitable when uncertainty is high

A
  • Rolling wave planning
  • Agile work methods
  • This gives control over costs and risks, however requires PO to keep cool and be ready to give a loose mandate to the project
23
Q

Uncertainty analysis

A

Estimating uncertainty
Base the values on similar projects, or estimates from groups with members having different ideas of the final costs
- The closer to the upper intervals you are, the larger the risk of exceeding budget is
See p. 223 for formula and example

24
Q

What needs to be done if the budget and advance estimate isn’t in balance

A
  • Review calculations and try to find cheaper resources
  • Re-plan project and find another way to achieve the goal
  • PM must ask PO for larger budget or decreased project scope
25
Q

What is Crashing?

A
  • Method for when the critical path is too long

- Identifying which activities on the critical path cost the least to shorten

26
Q

The Pay-back method

A

Estimate the time that passes before an investment, a project, has earned back the capital invested

27
Q

Pay-back time

A
  • The time it takes before a project has earned back the capital invested
  • The most profitable project is the one with the shortest Pay-back time
28
Q

The net present value method

A
  • Method for estimating investments, taking into account payments and expenditures that occur at different time points
  • Thought behind: recalculate the value of all expected payments and expenditures of the investment at a certain time: the present net value or capital value
29
Q

Cost of capital

A
  • Recalculation factor/discounting factor in net present value method
  • Often set to the interest rate an alternative placement of capital would have yielded
30
Q

ROI

A
  • Return on Investment

- Increased fourfold if you send an invoice every quarter, instead of once at the end of the year

31
Q

The internal rate of return method

A

Method based on determining the interest rate at which the net present value of the investment (project) is zero

32
Q

Interest rate

A
  • Called internal interest rate of the investment

- Reveals the annual ROI or yield that the investment options give on the invested capital

33
Q

Expected monetary value, EMV

A

Based on risk probabilities and risk values

Example of calculation on p.228