Chapter 7 - Time and resource planning Flashcards
What should a project overview include?
What should be done and in what order –> schedule
Why should those performing the work be included in planning?
- Reduces misjudging required time and resources
- The PM can’t know everything; delegate to the team members who’ve been selected for their competence
What is a project management plan?
A governing document that gathers all information necessary to execute the project.
What are possible headings in a project plan?
- Executive summary
- Background, purpose and goals
- Scope and delimitations
- Requirements specification
- Delivery and implementation
- Situational analysis and stakeholders
- Organization and staffing
- Communication
- Milestones
- Activities
- Schedule
- Budget and benefits assessment
- Risk analysis
- Routines for change management
What is the projects baseline?
The original project plan, which is the reference for any changes. It’s the point against which the project progress is measured.
Which are the four development principles?
Predictable
Iterative
Incremental
Adaptive
Describe the predictable development principle.
Predictable - Few deliveries and likely small need for changes. Traditional approach, early planning. Decreases uncertainty and complexity
Describe the Iterative development principle.
Iterative - Unclear requirements, small need to divide the delivery in parts. Test your way forward with multiple loops, gradually improve.
Describe the Incremental development principle.
Incremental - Known requirements, multiple deliveries preferred. Many small sub-deliveries of functional results that can be used right away.
Describe the Adaptive development principle.
Adaptive - Combination of iterative and incremental, to refine the work and deliver i stages. Early feedback means you learn during process.
Which of the four development principles are agile?
Adaptive, Incremental, Iterative
What are the steps in the planning chain?
- Determine the purpose and goal.
- Define the scope of the project in a wbs.
- Compare with requirements.
- Create a logical network
- Break down the work packages into activities.
- Assess the resource usage, work hours and duration of each activity.
- Create a schedule by entering the activities into a calendar
- Analyse the project’s resource needs in a resource histogram.
- Create a budget
- Optimize the plan.
What is an activity plan?
An activity plan is a logical network showing the order in which the project activities will be performed.
Activity-on-node: Activities are shown as boxes, and dependencies as arrows. (Most common)
Activity-on-arrow: Activities are arrows between nodes, which are the dependencies.
What is the milestone method?
A simplified planning method suitable for smaller projects, where milestones are known. Start with the milestone plan, for each milestone assess which activities must be performed to reach the milestone. Activities are then planned between the milestones
Give examples of resources.
Project members, equipment, materials, time, money
What is a resource management plan?
The resources needed for each activity is specified and compiled into a resource management plan. Basis for budgeting and resource provision.
What is the critical path?
The critical path is the sequence of activities that determines the earliest possible finishing time for a project, and the total duration.
What is total float/slack?
Activities that are not on the critical path have float or slack - if they get delayed it doesn’t delay the entire project. Activities on the cp don’t have float. Float changes as the project moves along.
How do you identify the critical path?
The path that takes the longest is the critical path. In large projects, start with stating the earliest possible start and endpoints for each activity.
What is LS, LF, ES, EF?
LS - late start
LF - late finish
How long you can wait to start an activity without affecting the total duration of the project.
ES - early start
EF - early finish
When the earliest possible starting time is for an activity