Chapter 13 - Project on track Flashcards

1
Q

Reviewing the plan

A
  • Important, especially if there has passed since the compilation of the plan
  • PM should have the authority to preform a final review and update the plan before execution
  • List of things to be documented, reviewed and approved before execution on p. 321
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should you replace a larger delivery with?

A
  • Several smaller deliveries

- Should be thought about already in planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Baseline/original plan

A
  • An approved schedule

- Needed in order to have something to be compared with

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Pros and cons with digital planning tools

A

+ Plan can be shared with everyone, regardless of their geographic location
+ Can connect schedule to spreadsheets and tools for follow-up
+ Can preform analysis and simulations
- Lose comprehensive view, plan is not physically in front of you. Can usually only see part on the screen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who has approved the original plan?

A

Project owner and steering committee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Revised plan

A

The plan with approved changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Outcomes

A

Project status in the form of activities performed, milestones approved or sprints preformed, and costs reported

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Forecasts

A

Relates to analyses preformed for the future project work, based on the results up to this point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Responsibility matrix

A
  • Often called RACI
  • Define who is in charge of execution
  • Who has decision-making mandates
  • Who needs what information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

RACI stands for

A

Responsible, Accountable, Consulted and Informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Milestone chart

A
  • Planned milestones are compared with when they were completed in reality
  • Indicating the intersection between the vertical line from the planned milestone and the horizontal line from the actual realised one
  • Above diagonal: ahead of plan, below diagonal: behind schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Percentage - work performed

A
  • Indicating performed and approved activities with different colors to get a good overview of the project
  • Assessing how much of activity that remains may be difficult, up to PM or person performing activity to provide subjective assessment
  • Can use criteria (such as 25, 50, 75, 100 percent) to simplify follow-up
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project boards

A
  • Suitable for all types of projects
  • Normally used in sgile projects
  • Work tasks defined in WBS are transferred to cards, which are moved between the columns as they are performed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Daily scrum

A
  • Effective method for following up a project
  • Max 15 minutes of meeting
  • Answers What did you do yesterday? What are you going ti do today? Are there any obstacles?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Burndown chart

A
  • Check off tasks performed and ongoing work on a daily basis
  • Not unusual for the sprint log to grow during a sprint
  • Important to ensure that you have a margin for the unexpected
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Burn-rate

A
  • Measure of a team’s productivity
  • Shows how many posts or “story points” are handled each sprint
  • Result is presented to PO and client
  • PO decides if the results can be approved and delivered
17
Q

When should costs be reported?

A

One of the following options is usually applied:

  • 100% of costs are reported when the activity is begun
  • -> avoids giving an impression that the project is doing better than it is, cost wise, but also shows that the projects look like going over budget
  • 100% of costs are reported when the activity is finished and approved
  • -> will look good in the reporting but can lead to unpleasant surprises
  • 50% of costs are reported when the activity is begun and 50% when the activity is finished and approved
  • -> Might be a more correct method
18
Q

What does the cost for agile projects depend on?

A
  • How many teams take part
  • How many sprints each team perform
  • It is simply a matter of multiplication
19
Q

Six steps for keeping project costs under control

A
  1. Reporting and following up on actual costs as compared with the plan
  2. Identifying deviations as compared with the plan
  3. Identifying the causes of deviations
  4. Creating and implementing relevant measures
  5. Following up to see if the measures have fixed the problem
  6. Creating further measures if necessary
20
Q

Earned Value Management, EVM

A
  • Gives chance to assess both actual results and resources used throughout the project
  • The results achieved (EV) are evaluated in financial terms, so they can be compared with PV and AC
21
Q

EV

A

Earned Value - The value of the work performed

- The budgeted cost for activities performed at a certain time

22
Q

PV

A

Planned Value - The planned cost for the work performed

- Number of work hours planned for the activities that have been performed up until the time of measurement

23
Q

AC

A

Actual Cost - The actual cost of the work performed

- Actual number of hours used in execution

24
Q

BAC

A

Budget At Completion - the planned cost for the entire project

25
Q

EAC

A

Estimate At Completion - the estimated cost fo the entire project

26
Q

The 20 percent-follow-up

A
  • Key figures are stable once 20 percent of the project has been performed
  • Gives a correct forecast for the future
27
Q

Cost variance

A
  • Indicates where the project costs stand in relation to value created
  • CV = EV - AC
    Example on p. 335
28
Q

Schedule variance

A
  • Indicates if a project is ahead of or behind schedule
  • SV = EV - PV
    Example on p. 335
29
Q

What can you do with Cost Performance Index and Schedule Performance Index?

A

Forecast the rest of the project

30
Q

CPI

A
  • Cost Performance Index

- CPI = EV / AC

31
Q

SPI

A
  • Schedule Performance Index

- SPI = EV / PV

32
Q

How is forecast cost calculated?

A

PV / CPI

Example on p. 337

33
Q

How to calculate forecast delivery

A

PD / SPI

Example on p. 337

34
Q

Work remaining

A
  • EVM can be used to estimate final costs
  • Based on results up to the time of follow-up and prediction of the reminder of the project
  • See example of different methods to do it on p. 339
35
Q

What is a good method for ensuring that there is enough money?

A
  • Continually check hos much money is left in the project budget and estimate how many activities these funds will cover
  • Make a habit of going over and updating budget analysis at each project meeting
36
Q

Whos responsibility is it to ensure that the risk analysis is up-to-date?

A

The project manager

- Done by re-evaluating and, if necessary, changing risk values, removing outdated risk events and entering new ones

37
Q

Change management

A
  • It is important to update the risk analysis and project plan as the project goes on
  • One should also keep track of stakeholders, stakeholders who were positive from the beginning might change their opinion if they feel neglected or poorly treated