Chapter 9 Flashcards
What is project scheduling?
an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources
What is a scope?
The work content and products of a project or component of a project. Scope is fully described by naming all activities performed, the resources consumed, and the end products that result, including quality standards.
What is work breakdown structure?
A task-oriented “family tree” of activities that organizes,
defines, and graphically displays the total work to be accomplished in order to achieve the final objectives of a project. Each descending level represents an increasingly detailed definition of the project objective.
What is work package?
A deliverable at the lowest level of the Work Breakdown Structure; it is an element of work performed during the course of a project. A work package normally has an expected duration plus an expected cost. Other generic terms for project work include task or activity.
What is project network diagram?
Any schematic display of the logical relationships of
project activities.
What is a path?
A sequence of activities defined by the project network logic.
What is an event?
A point when an activity is either started or completed. Often used in conjunction with AOA networks, events consume no resources and have no time to completion associated with them.
What is a node?
One of the defining points of a network; a junction point joined to some or all of the others by dependency lines (paths).
What are predecessors?
Those activities that must be completed prior to initiation of a later activity in the network.
What are successors?
Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks.
What is an early start (ES) date?
The earliest possible date on which the uncompleted portions of an activity (or the project) can start, based on the network logic and any schedule constraints.
Early start dates can change as the project progresses and changes are made to the project plan.
What is a late start (LS) date?
The latest possible date that an activity may begin without delaying a specified milestone (usually the project finish date).
What is a forward pass?
Network calculations that determine the earliest start/earliest finish time (date) for each activity. The earliest start and finish dates are determined by working forward
through each activity in the network.
What is a backward pass?
Calculation of late finish times (dates) for all uncompleted network activities.
The latest finish dates are determined by working backward through each activity.
What is a merge activity?
An activity with two or more immediate predecessors (tasks flowing into it). Merge activities can be located by doing a forward pass through the network. The PMBoK refers to merge activities as “path convergence.”