Chapter 10 Flashcards

1
Q

What is a lag?

A

Logical relationship between the start and finish of one activity and the start and finish of another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a finish to start relationship?

A

When activity b cannot start before the completion of activity a.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is finish to finish relationship?

A

Finish to Finish relationships require that two linked activities share a similar completion point.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is start to start relationship?

A

Often two or more activities can start simultaneously or a lag takes place between the start of one activity after an earlier activity has commenced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is start to finish relationship?

A

successor’s finish is dependent upon a predecessor’s start, least common.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is project crashing?

A

The process of accelerating a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the options for crashing a project?

A
  1. Improve the productivity of existing project resources
  2. Change the working method employed for the activity, usually by altering the technology and types of resources employed
  3. Compromise quality and/or reduce project scope
  4. Fast-track the project
  5. Use overtime
  6. Add resources to the project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly