Chapter 8 - Managing Project Stakeholders & Communications Flashcards

1
Q

Describe what is meant by informal organization.

A

The informal organization is how people actually relate to one another in an organization, as opposed to how they SHOULD relate to one another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why should the project manager be concerned with understanding the informal organization?

A

The informal organization dictates a flow of information and influence separate from the formal organization, and needs to be considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a stakeholder?

A

A stakeholder is anyone who has a stake in the project’s outcome, good or bad.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of developing a project communications plan?

A

A project stakeholder plan allows us to determine what information needs to get where, by what channels, and when.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are project metrics?

A

A project metric is a quantitative measurement of some portion of the project, something that is able to be tangibly observed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe the qualities of a good metric.

A

A metric should be:

  • Understandable
  • Quantifiable
  • Cost-Effective
  • Proven (Accurate)
  • High Impact (Should matter)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why should a project have a good measurement system in place?

A

A measurement system allows the stakeholders in a project to understand how the project is going, and adjust accordingly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Describe the concept of earned value (EV).

A

Earned value is the amount that we should have paid for an activity or component, rather than what we actually have to pay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is PV?

A

PV stands for Planned Value, that is, the planned or budgeted cost for an activity or component.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is BAC?

A

BAC stands for budget at completion, which is the cumulative planned value for a project; it’s what we expect to have spent, in the end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a project review, and what purpose does it serve?

A

A project review is a formal, or informal meeting with stakeholders. It may focus on some deliverables, milestones, phases, etc. It’s purpose it twofold, to show that work is being done, but also to confirm that things are up to snuff.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a status report?

A

A status report describes the current state of the project, usually compared to the baseline plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a progress report?

A

A progress report is a report to tell specifically what has been accomplished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a forecast report?

A

A forecast report does exactly what it sounds like it would do, predict future progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is CPI?

A

CPI, or cost performance index, is a measure of how effectively the money being spent is being used. It’s calculated as so:
CPI = EV / AC
A CPI of less than one is inefficient, over one is efficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is SPI?

A

SPI, or Schedule Performance Index, is a measure of how effectively time is being used. It is calculated by:
SPI = EV/PV
A SPI of greater than one indicates being ahead of schedule. Less than one is behind.

17
Q

What is EAC?

A

EAC, or estimate at completion, is a revised estimate of the total cost of a project based on progress so far. It is calculated as so:
EAC = Cumulative AC + (BAC - Cumulative EV)/Cumulative CPI

18
Q

What is VAC?

A

VAC, or Variance at Completion, is a comparison of the original budget to the estimate at completion, to determine how far off the original budget was.