Chapter 6 Flashcards

1
Q

What is the purpose of a Gantt chart?

A

A Gantt chart is used for planning out the schedule of a project by showing the time each task involved in a phase will need, and staggering them in sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some advantages network diagrams have over traditional Gantt charts?

A

A network diagram, unlike the Gantt chart, show information on the interdependencies of tasks in a phase, as well as required start and end dates, as well as highlighting the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is meant by slack, or float?

A

Slack, or float, is the amount of time an activity can be delayed before it impacts the projected end-time of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between crashing and fast tracking a project’s schedule?

A

Crashing is when resources are added to a critical path activity in order to shorten its duration. Fast-tracking is when two parallel activities are started at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between AON and PERT?

A

AON, or Activity on the Node, is a network diagramming method that uses sequence dependencies to determine the overall schedule of a project. PERT, or Program Evaluation and Review Technique performs a similar task, but it determines an estimate of the amount of time a task will take based on the following equation:
Activity Estimate = (Optimistic Time + (4 * Most Likely Time) + Pessimistic Time) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define the following:

  • Finish-to-Start
  • Start-to-Start
  • Finish-to-Finish
  • Start-to-Finish
A
  • Finish-to-Start: Finish to start means one activity can’t start until the other is finished.
  • Start-to-Start: Start-to-Start means that two activities can either start at the same time, or one can’t start until the other has.
  • Finish-to-Finish: Finish-to-Finish means that two processes can run side-by-side, but one cannot finish without the other.
  • Start-to-Finish: Least common, a task cannot end until another starts.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between lead and lag?

A

Lead time allows for activities to overlap, such as installing computers can be overlapped by configuring them; if installing computers takes twice as long as configuring, then configuring can start when installing is half-done, and they’ll finish at the same time.
Lag is the other way around, time after a task has completed where work can’t be done, like allowing the paint to dry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why do many people inflate their estimates? Does this help anything?

A

People inflate their estimates because they feel safer with a bit of leeway, or padding. This usually doesn’t help, as people then procrastinate to fill that padding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is critical chain project management?

A

Critical chain project management is a method of removing people’s natural tendency to inflate schedules by adding buffers to time estimates, and putting expected time estimates in place that are about 50% likely to be met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is resource contention?

A

Resource contention occurs where a team member is assigned to more than one project, and therefor is torn in their ability to devote the necessary amount of time between them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of buffers?

A

The purpose of buffers is to allow for projects to finish on-time, without the general padding that occurs to schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the critical chain, and how is it different from the critical path?

A

The critical chain takes into account resource contention, unlike the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why should a project manager ensure that project resources are leveled?

A

When resources aren’t leveled, then they’re in-contention, assigned to multiple tasks at once.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When does the project manager have authority to begin executing the project plan?

A

A project manager can begin executing the project plan once the project plan and charter are approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a task? How is it different from a process?

A

A task, also known as an activity, is an action that must be taken to complete a deliverable within a phase. A task uses resources, takes time, and has a place in the overall sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a baseline plan, and what purpose does it serve?

A

The baseline plan is the estimated costs and schedules carried over from the initial project plan and schedule, which are then used to compare current progress to determine if the project is ahead or behind, etc.

17
Q

Why do most organizations have a kick-off meeting?

A

The kick-off meeting provides a sense of closure to planning, communicates what needs to be said, and gets things started on the right foot.

18
Q

What are the steps involved in determining the cost of an activity?

A

To determine the cost of an activity, you must:

  • Determine what resources are needed
  • Determine the quantity of the resources
  • Determine the cost of using each resource
  • Calculate the total cost
  • Ensure the resources are leveled.