Chapter 7: Project Cost Management Flashcards
The Cost Performance Baseline in Earned Value Management is also part of:
A. The cost estimating baseline
B. The budget baseline
C. The performance measurement baseline
D. The cost measurement baseline
C. The performance measurement baseline
Company WWX is planning its cost management activity and examining the extent to which they will allow project costs to exceed the baseline before action is taken. These limits are known as:
A. Control boundaries
B. Control headlines
C. Control thresholds
D. Control limits
C. Control thresholds
If the EAC is 1200, the BAC is 1000 and the ETC is 800, what is the VAC?
A. -400
B. -200
C. 400
D. 200
B. -200
VAC=BAC-EAC
Company LWJ has completed 50% of its project and the project sponsor has asked how much more money will be needed for the last half of the project. The metric that you will use to provide the answer is:
A. EAC
B. CV
C. AC
D. ETC
D. ETC
If EV=30 000, PV=25000, AC=27000, what is the SV?
A. -3000
B. 5000
C. -5000
D. 3000
B. 5000
SV=EV-PV
Your project sponsor has requested a meeting about the project status. You would like to graphically show them the earned value and will use which chart:
A. S-curve
B. Trend analysis
C. Pareto diagram
D. Control chart
A. A-curve
If EV=30000, PV=25000, AC=27000, what is the CV?
A. -3000
B. -5000
C. 5000
D. 3000
D. 3000
CV=EV-AC
The degree of confidence in cost estimates which usually becomes more accurate as the project proceeds is:
A. Random order of measure
B. Routine order of measure
C. Rough order of magnitude
D. Regular order of magnitude
C. Rough order of magnitude
Time reporting, required expenditure and disbursement reviews, accounting codes and standard contract provisions are known as:
A. Financial accounting conventions
B. Financial controls procedures
C. Financial controls processes
D. Financial accounting processes
B. Financial controls procedures
Which type of estimation methods can be used in agile/adaptive environments:
A. Lightweight estimating
B. Parametric estimating
C. Bottom up estimating
D. Analogous estimating
A. Lightweight estimating
Early scope definition is critical for project cost management because:
A. It ensures that projects are aligned with organizational strategic objectives
B. It minimizes the project cost
C. The ability to influence cost is greatest at the early stages of the project
D. Sponsors need early notice to secure funding
C. The ability to influence cost is greatest at the early stages of the project
In a project being conducted by company LXC the midway point in the schedule has been reached. The SPI has been calculated and is 1.1. This means the project is:
A. Ahead of schedule
B. Over budget
C. Under budget
D. Behind schedule
A. Ahead of schedule
The WBS component that is used for project cost accounting is called:
A. The cost breakdown structure
B. The control account
C. The WBS dictionary
D. The project budget
B. The control account
Which of the following is not a project indirect cost:
A. The occasional support provided to the project by the information technology department
B. The heating costs for the production area in which the project is being conducted
C. Benefits for employees who are working part time on the project team
D. The full time project manager’s salary
D. The full time project manager’s salary
If EV=30000, PV=25000, AC=27000, what is the SPI?
A. 0.83
B. 1.2
C. 1.18
D. 0.88
B. 1.2
SPI=EV/PV
Tailoring considerations for Project Cost Management do not include which one of the following:
A. Flexibility of ethical considerations
B. Estimating and budgeting
C. Knowledge management
D. Use of agile approach
A. Flexibility of ethical considerations
If EV=30000, PV=25000, AC=27000, what is the CPI?
A. 1.15
B. 0.83
C. 0.88
D. 1.11
D. 1.11
CPI=EV/AC
Company NHS is halfway through its project and the project sponsor has asked how much the total project will cost when it is completed. The value metric that will be used for this is:
A. ETC
B. EAC
C. AC
D. CV
B. EAC
An amount of the project budget that is withheld for management control purposes and reserved for unforeseen work that is within the project scope is known as:
A. Parametric reserves
B. Management reserves
C. Contingency reserves
D. The cost of quality
B. Management reserves
Which of the following is not a point in the project when the cost of an acquired item may be measured:
A. When the order is placed
B. When the project closure activities have commenced
C. When the actual cost is incurred or recorded for project accounting purposes
D. When the acquisition decision is made or committed
B. When the project closure activities have commenced
In PMBOK, the definition of Project Cost Management
“The processes involved in planning, estimating, budgeting, financing, funding, managing and controlling costs so that the project can be completed within the approved budget”
The processes from the PMBOK Project Cist Management Knowledgement Area
- Plan Cost Management
- Estimate Costs
- Determine Budget
- Control Costs
Plan Cost Management inputs
- summary budget
- Project charter (outlines process to gain approval of financial decisions)
- Project management plan elements (schedule management plan and risk management plan)
- EEFs
- Organizational process assets
Plan Cost Management tools and techniques
- financial analysis techniques (payback period, return on investment and others)
- Meetings (with stakeholders)