Chapter 6: Project Schedule Management Flashcards

1
Q

The Project Time Management processes and their associated tools and techniques are documented in the:

A. Time management plan
B. Schedule management plan
C. Scope management plan
D. Cost management plan

A

B. Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Company ASR has been working on a project to erect a new office building on their manufacturing site. The project is due for completion in two months, when employees from another site which has been sold are due to move into the new building. However, the project is behind schedule and current forecasts indicate that the building will not be available for another three months. The project manager has been asked to produce plans that will speed up the project and deliver it on time. One term for this is:

A. Project crashing
B. Schedule acceleration
C. Project pace setting
D. Schedule efficiency

A

A. Project crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Variance thresholds for monitoring performance that may be specified to indicate an agreed upon amount of variation to be allowed before some action needs to be taken are called:

A. Control limits
B. Control thresholds
C. Control parameters
D. Control processes

A

B. Control thresholds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The deliverables at the lowest level of the WBS are known as work packages. Decomposition of work packages divides them into:

A. Actions
B. Tasks
C. Activities
D. Deliverables

A

C. Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The iterative planning technique in which the work to be accomplished in the near term is planned in detail while the work in the future is planned at a higher level is known as:

A. Decomposition
B. Rolling wave planning
C. Waterfall planning
D. Forward planning

A

B. Rolling wave planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The multiple components associated with each activity are known as:

A. Activity attributes
B. Activity characteristics
C. Activity description
D. Activity register

A

A. Activity attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Company GVN is completing a project and has reached a milestone with the completion of the basement foundation in their house construction. Which of the following is a characteristic that distinguishes a milestone from a scheduled activity:

A. A milestone is a key project schedule activity
B. A milestone occurs at the end of each project phase
C. A scheduled activity occurs at a specific point in the project
D. A milestone has zero duration

A

D. A milestone has zero duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The precedence diagramming method is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. Most project management software packages use which method to represent a precedence diagram:

A. Arrow diagramming model
B. Activity on node
C. Critical path method
D. Program evaluation and review technique

A

B. Activity on node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is which type of relationship:

A. Finish to start
B. Finish to finish
C. Start to start
D. Start to finish

A

A. Finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A construction project has activities that cannot be completed until the electrical wiring work has been inspected by the municipality. This is known as which type of dependency:

A. Mandatory dependency
B. Discretionary dependency
C. External dependency
D. Internal dependency

A

C. External dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity is called:

A. A lead
B. A lag
C. A precedent
D. A timeline

A

B. A lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A project schedule network diagram is a graphical representation of the logical relationships among the project schedule activities. These relationships are also known as:

A. Prerequisites
B. Prerequirements
C. Dependencies
D. Leads and lags

A

C. Dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Steffi is organizing a group of volunteers to organize a holiday dinner for a seniors group. She has to decide on the number of volunteers she will need. The PMBOK process that she should use for this is:

A. Estimate activity durations
B. Estimate activity costs
C. Project budgeting
D. Develop project scope

A

A. Estimate activity durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A resource calendar is used for:

A. Estimating project costs
B. Estimating resource utilisation
C. Project planning
D. Monitoring and controlling resources

A

B. Estimating resource utilisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The method of estimating project duration or cosy by aggregating the estimates of the lower level components of the WBS is:

A. Top-down estimating
B. Bottom-up estimating
C. Analogous estimating
D. Parametric estimating

A

B. Bottom-up estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Ash is developing estimates for his project to create a green roof for a new condo building. To do this he has looked at similar projects on other condo buildings and the costs that existed there are is assuming that his costs be in the same range. Which type of estimating is this:

A. Parametric estimating
B. Bottom-up estimating
C. Analogous estimating
D. Three-point estimating

A

C. Analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the critical path through the following network:

              C10 A1 B2 D5     E3            F1
         G2 H3 I2 (With lines going through - C10 to GHI are in parallel)

A. ABDEF
B. ABGHIF
C. ABDGHIF
D. ABCF

A

D. ABCF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply is:

A. Simulation
B. Resource smoothing
C. Resource leveling
D. Critical chain method

A

C. Resource leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A logic bar chart is also known as:

A. A project schedule network diagram
B. A milestone chart
C. A GANTT chart
D. A critical path

A

A. A project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work are known as:

A. Schedule acceleration
B. Schedule speedup
C. Schedule complexity
D. Schedule compression

A

D. Schedule compression

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The processes used in Project Schedule Management process

A
  1. Plan Schedule Management
  2. Define Activities
  3. Sequence Activities
  4. Estimate Activity Durations
  5. Develop Schedule
  6. Control Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Rolling wave planning

A

Project elements are completed when capacity is created to work on them by the completion of previous project elements. This approach may be used in agile, adaptive, and incremental projects, and is contrasted with approaches that create a schedule for most activity at the start of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Possible project schedule influences

A
  • Resources
  • Scheduling technology
  • Control
  • Complexity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Alternative scheduling methods

A
  • Agile
  • Predictive
  • Agile/predictive hybrid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Plan Schedule Management process

A

Process for developing a plan for the creation of the project schedule and its management through: understanding how various project activities impact each other and how to best fit them together in the schedule and management of the schedule as the project proceeds, including management of changes in the Perform Integrated Change Control process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Plan Schedule Management inputs

A
  • Project charter
  • Project management plan elements (scope baseline)
  • Developmental approach (ex. Predictive, agile, etc.)
  • EEFs
  • Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Plan Schedule Management tools and techniques

A
  • Expert judgement
  • Data analysis techniques
  • Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Plan Schedule Management outputs

A

Schedule management plan, which includes how the project schedule will be developed and managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Possible Schedule Management Plan elements

A
  • Method that will be used for schedule model development
  • Level of detail, such as units of measurement
  • How it will be linked to other elements of the project management plan
  • How the schedule model will be maintained and kept up-to-date
  • How control threshold will be used
  • How schedule performance will be measured and reported
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Define Activities process

A

Process for breaking down the work packages into the individual activities that achieve them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Define Activities outputs

A
  • Schedule management plan
  • Scope baseline (WBS, work packages)
  • EEFs
  • Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Define Activities tools and techniques

A
  • Expert judgement
  • Decomposition
  • Rolling wave planning (for agile approach)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Define Activities outputs

A
  • Activity list
  • Activity attributes
  • Milestone list
  • Change requests
  • Project management plan updates
34
Q

Activity list

A

Output of Define Activities process; a list of all the activities that are required to complete the project, ideally including descriptions for each activity and titles indicating each activity’s place in the project schedule

35
Q

Activity attributes

A

Output of the Define Activities process; an extended description of each activity, providing information needed for the completion of that activity

36
Q

Milestone list

A

Output of the Define Activities process; based on the activity list, listing important points in the project

37
Q

Sequence Activities process

A

Process for organizing that activities required to complete the project into the order in which they should be completed

38
Q

Sequence Activities inputs

A
  • Project management plan elements
  • Schedule management plan
  • Activity list
  • Activity attributes
  • Milestone list
  • Project scope statement
  • EEFs
  • Organizational process assets
39
Q

Sequence Activities tools and techniques

A
  • Precedence diagramming method
  • Software packages using the Activity on Node (AON) diagramming method
  • Leads and lags
  • Project management information system (PMIS)
40
Q

Predecessor activities (predecessors)

A

Activities that are undertaken before others

41
Q

Successor activities (successors)

A

Activities that follow others

42
Q

Precedence diagramming

A

Technique in the Sequence Activities process, used to visually represent relationships between predecessors and successors and support the creation of a schedule; nodes represent activities and arrows indicate the relationships between the nodes (Activity on Node (AON) diagramming)

43
Q

Four types of dependencies represented in a precedence diagram

A
  1. Finish to start
  2. Finish to finish
  3. Start to start
  4. Start to finish
44
Q

Dependency categories according to strength of relationship

A
  • Mandatory (AKA hard logic)
  • Discretionary
  • External
  • Internal
45
Q

Lead

A

In the Sequence Activities process, time that an activity can start before another activity is completed

46
Q

Lag

A

In the Sequence Activities process, time that must pass before an activity can start, relative to another activity

47
Q

Sequence Activities outputs

A
  • Project schedule network diagram

- Updated project documents

48
Q

Project schedule network diagram

A

Displays relationship between project activities

49
Q

Estimate Activity Durations process

A

Process that provides information on the time that it will take to complete each project activity and the amount of the available resources needed to complete it

50
Q

Estimate Activity Duration inputs

A
  • Project management plan elements (schedule management plan and scope baseline)
  • Project documents (activities relationships, activities list, project team assignments)
  • EEFs
  • Organizational process assets
51
Q

Estimate Activity Durations tools and techniques

A
  • Expert judgement
  • Estimating techniques (analogous, parametric, three-point and bottom-up)
  • Data analysis (alternatives analysis and reserve analysis)
  • Decision making techniques (voting)
52
Q

Analogous estimating

A

Estimating technique that uses data from activities or projects that are similar to those that are being estimated

53
Q

Parametric estimating

A

Estimating technique that applies an algorithm to historical data to calculate the cost for the existing project

54
Q

Three point estimating system

A

Estimating technique that creates three estimates (most likely, optimistic, and pessimistic) and then calculates the average of these to arrive at the estimate figure

55
Q

Bottom-up estimating

A

Builds up costs by calculating the amount that lower level components of the WBS will cost and then adding them together to create estimated costs

56
Q

Estimate Activity Durations outputs

A
  • Duration estimates
  • Basis or estimates
  • Updated project documents
57
Q

Develop Schedule process

A

Process for creating the schedule model or the project, which can be used to execute the schedule and monitor and control it

58
Q

Develop Schedule inputs

A
  • Project management plan elements (schedule management plan and scope baseline)
  • Project documents (activity list, assumptions, activity durations and lessons learned)
  • Project vendors
  • EEFs
  • Organizational process assets
59
Q

Develop Schedule tools and techniques

A
  • Schedule network analysis
  • Critical path method
  • Resource optimization
  • Data analysis techniques (what if scenario analysis and simulation)
  • Schedule compressing techniques (crashing and fast tracking)
  • Project management information system (PMIS)
  • Agile releaser planning (for agile projects)
60
Q

Schedule network analysis

A

Main tool usually used in the Develop Schedule process, which studies the possible ordering of project activities to arrive at the optimum schedule for the project

61
Q

Critical Path method

A

Used in the Develop Schedule process to find the quickest schedule that can be achieved for the project and the various possibilities that may exist for the different schedules that may be created

62
Q

Resource optimization

A

Technique used in the Develop Schedule process which adjusts the time periods for activities based on the availability of project resources by adjusting the scheduling of activities to match or be less than the maximum resources that are available through resource leveling and resource smoothing

63
Q

What-If scenario analysis

A

Used in the Develop Schedule process to determine the consequences of possible schedules on project success

64
Q

Schedule compression techniques

A

Techniques used in the Develop Schedule process, to allow the schedule to be completed more quickly using crashing (additional resources) and fast tracking (completion activities together)

65
Q

Agile release planning

A

Used in the Develop Schedule process for agile projects to determine the objectives of each project iteration

66
Q

Develop Schedule outputs

A
  • Approved project schedule model (schedule baseline)
  • Milestone chart
  • Bar chart
  • Other data (activity resource requirements and alternative schedules)
  • Project calendars
  • Change requests
  • Project management plan updates
  • Other project document updates
67
Q

Control Schedule process

A

Process to monitor the project schedule for where activities for where activities are on schedule and where changes need to be made

68
Q

Control schedule inputs

A
  • Project management plan elements (schedule management plan and schedule, scope and performance management baseline)
  • Other project documents (lessons learned register, project schedule and resource calendars)
  • Work performance data
  • Organizational process assets
69
Q

Control Schedule tools and techniques

A
  • Data analysis techniques (trend, variance and what-if scenario analysis)
  • Performance measurement techniques (earned value analysis)
  • Iteration burndown chart (for agile projects)
  • Performance reviews
  • Critical path method
  • PMIS
  • Resource optimization
  • Leads and lags
  • Schedule compression techniques
70
Q

Control Schedule outputs

A
  • Information on project work performance
  • Schedule forecast updates
  • Change requests
  • Project management plan updates
  • Other project document updates
71
Q

Example EEFs that are inputs to Plan Schedule Management process

A
  • Availability of project resources
  • Organizational culture
  • Software to develop and manage the plan
72
Q

Example organizational process assets that are inputs to Plan Schedule Management process

A
  • Information from previous projects

- Organization’s scheduling tools

73
Q

Example EEFs that are inputs to Define Activities process

A

Publicly available information for determine the activities required to complete the work

74
Q

Example organizational process assets that are inputs to Define Activities process

A

Information from previous projects

75
Q

Example EEFs that are inputs to Sequence Activities process

A

Regulations or standards that may impact the project

76
Q

Example organizational process assets that are inputs to Sequence Activities process

A

Information from previous projects

77
Q

Example EEFs that are inputs to Estimate Activity Duration process

A
  • Standard Activity Durations

- Information from similar projects

78
Q

Example organizational process assets that are inputs to Estimate Activity Durations process

A
  • Historical activity durations

- Lessons learned

79
Q

Example EEFs that are inputs to Develop Schedule process

A

Government standards for scheduling

80
Q

Example organizational process assets that are inputs to Develop Schedule process

A

Organization’s methodology for creating schedules

81
Q

Example organizational process assets that are inputs to Control Schedule process

A
  • Organization’s policies and procedures
  • Organization’s schedule and control tools
  • Organization’s monitoring and reporting methods