Chapter 6: Project Schedule Management Flashcards
The Project Time Management processes and their associated tools and techniques are documented in the:
A. Time management plan
B. Schedule management plan
C. Scope management plan
D. Cost management plan
B. Schedule management plan
Company ASR has been working on a project to erect a new office building on their manufacturing site. The project is due for completion in two months, when employees from another site which has been sold are due to move into the new building. However, the project is behind schedule and current forecasts indicate that the building will not be available for another three months. The project manager has been asked to produce plans that will speed up the project and deliver it on time. One term for this is:
A. Project crashing
B. Schedule acceleration
C. Project pace setting
D. Schedule efficiency
A. Project crashing
Variance thresholds for monitoring performance that may be specified to indicate an agreed upon amount of variation to be allowed before some action needs to be taken are called:
A. Control limits
B. Control thresholds
C. Control parameters
D. Control processes
B. Control thresholds
The deliverables at the lowest level of the WBS are known as work packages. Decomposition of work packages divides them into:
A. Actions
B. Tasks
C. Activities
D. Deliverables
C. Activities
The iterative planning technique in which the work to be accomplished in the near term is planned in detail while the work in the future is planned at a higher level is known as:
A. Decomposition
B. Rolling wave planning
C. Waterfall planning
D. Forward planning
B. Rolling wave planning
The multiple components associated with each activity are known as:
A. Activity attributes
B. Activity characteristics
C. Activity description
D. Activity register
A. Activity attributes
Company GVN is completing a project and has reached a milestone with the completion of the basement foundation in their house construction. Which of the following is a characteristic that distinguishes a milestone from a scheduled activity:
A. A milestone is a key project schedule activity
B. A milestone occurs at the end of each project phase
C. A scheduled activity occurs at a specific point in the project
D. A milestone has zero duration
D. A milestone has zero duration
The precedence diagramming method is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. Most project management software packages use which method to represent a precedence diagram:
A. Arrow diagramming model
B. Activity on node
C. Critical path method
D. Program evaluation and review technique
B. Activity on node
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is which type of relationship:
A. Finish to start
B. Finish to finish
C. Start to start
D. Start to finish
A. Finish to start
A construction project has activities that cannot be completed until the electrical wiring work has been inspected by the municipality. This is known as which type of dependency:
A. Mandatory dependency
B. Discretionary dependency
C. External dependency
D. Internal dependency
C. External dependency
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity is called:
A. A lead
B. A lag
C. A precedent
D. A timeline
B. A lag
A project schedule network diagram is a graphical representation of the logical relationships among the project schedule activities. These relationships are also known as:
A. Prerequisites
B. Prerequirements
C. Dependencies
D. Leads and lags
C. Dependencies
Steffi is organizing a group of volunteers to organize a holiday dinner for a seniors group. She has to decide on the number of volunteers she will need. The PMBOK process that she should use for this is:
A. Estimate activity durations
B. Estimate activity costs
C. Project budgeting
D. Develop project scope
A. Estimate activity durations
A resource calendar is used for:
A. Estimating project costs
B. Estimating resource utilisation
C. Project planning
D. Monitoring and controlling resources
B. Estimating resource utilisation
The method of estimating project duration or cosy by aggregating the estimates of the lower level components of the WBS is:
A. Top-down estimating
B. Bottom-up estimating
C. Analogous estimating
D. Parametric estimating
B. Bottom-up estimating
Ash is developing estimates for his project to create a green roof for a new condo building. To do this he has looked at similar projects on other condo buildings and the costs that existed there are is assuming that his costs be in the same range. Which type of estimating is this:
A. Parametric estimating
B. Bottom-up estimating
C. Analogous estimating
D. Three-point estimating
C. Analogous estimating
What is the critical path through the following network:
C10 A1 B2 D5 E3 F1 G2 H3 I2 (With lines going through - C10 to GHI are in parallel)
A. ABDEF
B. ABGHIF
C. ABDGHIF
D. ABCF
D. ABCF
The technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply is:
A. Simulation
B. Resource smoothing
C. Resource leveling
D. Critical chain method
C. Resource leveling
A logic bar chart is also known as:
A. A project schedule network diagram
B. A milestone chart
C. A GANTT chart
D. A critical path
A. A project schedule network diagram
Ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work are known as:
A. Schedule acceleration
B. Schedule speedup
C. Schedule complexity
D. Schedule compression
D. Schedule compression
The processes used in Project Schedule Management process
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activity Durations
- Develop Schedule
- Control Schedule
Rolling wave planning
Project elements are completed when capacity is created to work on them by the completion of previous project elements. This approach may be used in agile, adaptive, and incremental projects, and is contrasted with approaches that create a schedule for most activity at the start of a project
Possible project schedule influences
- Resources
- Scheduling technology
- Control
- Complexity
Alternative scheduling methods
- Agile
- Predictive
- Agile/predictive hybrid
Plan Schedule Management process
Process for developing a plan for the creation of the project schedule and its management through: understanding how various project activities impact each other and how to best fit them together in the schedule and management of the schedule as the project proceeds, including management of changes in the Perform Integrated Change Control process
Plan Schedule Management inputs
- Project charter
- Project management plan elements (scope baseline)
- Developmental approach (ex. Predictive, agile, etc.)
- EEFs
- Organizational process assets
Plan Schedule Management tools and techniques
- Expert judgement
- Data analysis techniques
- Meetings
Plan Schedule Management outputs
Schedule management plan, which includes how the project schedule will be developed and managed
Possible Schedule Management Plan elements
- Method that will be used for schedule model development
- Level of detail, such as units of measurement
- How it will be linked to other elements of the project management plan
- How the schedule model will be maintained and kept up-to-date
- How control threshold will be used
- How schedule performance will be measured and reported
Define Activities process
Process for breaking down the work packages into the individual activities that achieve them
Define Activities outputs
- Schedule management plan
- Scope baseline (WBS, work packages)
- EEFs
- Organizational process assets
Define Activities tools and techniques
- Expert judgement
- Decomposition
- Rolling wave planning (for agile approach)