Chapter 5- Project Scope Management Flashcards
8/80 Rule
A planning heuristic for creating the WBS. This rule states that the work package in a WBS take no more than 80 hours of labour to create and no fewer than 8 hours of labour to create
Active observation
The observer interacts with the worker to ask questions and understand each step of the work being completed. In some instances, the observer could server as an assistant in doing the work.
Affinity diagrams
When stakeholders create a larger number of ideas, you can use an affinity diagram to cluster similar ideas together for further analysis. Common categories: Business requirements, Project Reqs, Stakeholder req, Solution Reqs, Quality Reqs, Technical Reqs, Transition requirements
Alternatives generation
A scope definition process of finding alternative solutions for the project customer while considering the customer’s satisfaction, the cost of the solution, and how the customer may use the product in operations
Brainstorming
This approach encourages participants to generate as many ideas as possible about the project requirements. No idea is judged or dismisses during the brainstorming session.
Change Control System CCS
Documented in the scope management plan, this system defines how changes o the project scope are managed and controlled.
Change Management Plan
This subsidiary plan defines how changes will be allowed and managed within the project.
Code of accounts
A numbering system for each item in WBS. The PMBOK is a good example of a code of accounts, as each chapter and its subheadings follow a logical numbering scheme.
Configuration management plan
The subsidiary plan defines how changes to the features and functions of the project deliverables will be monitored and controlled within the project.
Context diagram
These diagrams show the relationship b/n elements of an environment. For example a context diagram would illustrate the networks, servers, work stations, and people that interact with the elements of the environment
Delphi technique
This approach uses rounds of anonymous survey to build consensus. Because the surveys are anonymous, participants are more likely to be honest with their requirements, opinions, and statements. The PM organises these comments and inputs and then sends them back to the participant for another round of anonymous input.
Dictatorship
A decision method where only one individual makes the decision for the group.
Focus groups
A moderator-led requirements collection method for elicit requirements from stakeholders
Functional analysis
This is the study of the functions within a system, project, or, what’s more likely in the project scope statement, the product the project will be creating. Functional analysis studies the goals of the product, how the product will be used, and the expectations the customer has of the product once it leaves the project and moves into operations. Functional analysis may also consider the cost of the product in operations, which is known as life-cycling.
Funding limit
Most projects have a determined budget in relation to the project scope. There may be a qualifies if this budgets, such as plus or minus 10% based on the type of cost estimate created.
Initial Project organisation
The project scope statement identifies the project team and the key stakeholders. In some organisation, especially on larger projects, the team organization and structure are also documented.
Interviewers
A requirements collection method used to elicit requirements from stakeholders in a one-on-one conversations.
Majority
A group decision method where more than 50% of the group must be in agreement.
Mind mapping
Diagram of ideas or notes used to help generate, classify, or record information. It will show branches extending out from central core word or words.
Nominal Group technique
A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.
Passive observation
The observer records information about the work being completed without interrupting the process, sometimes called the invisible observer.
Plurality
A group-decision method where the largest part of the group makes the decision when it’s less than 50 percent of the total ( Consider three or four fractions within the stakeholders.)
Product acceptance criteria
This project scope statement components work with the project requirements, but focuses specifically on the product and what the conditions are processes are for formal acceptance of the product.
Product breakdown
A scope definition technique that breaks down a product into a hierarchical structure, much like a WBS breaks down a project scope
Product Scope description
This is a narrative description of what the project is creating as a deliverable for the project customer
Product scope
Defines the product or service that will come about as a results of completing the project. It defines the features and functions that characterise the product.