Containers shall be _____, _____, ______, and _____ In accordance with the regulations of the department of transportation.

A

Designed, fabricated, tested, and marked

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Containers that have been involved in a fire and show no distortion shall be _________ for continued service before being used or reinstalled

A

Requalified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ASME or API – ASME containers shall be retested using the _____ test procedure applicable at the time of the original fabrication

A

Hydrostatic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Containers that show excessive denting, bulging, gouging, or corrosion shall be _____________.

A

Removed from service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Field welding shall be permitted only on _____, _____, _____, _____, or ______ that are attached to the container by the container manufacturer

A

Saddle plates, lugs, pads, or brackets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Containers for general use shall not have individual water capacities greater than ___________.

A

120,000 gallons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Heating or cooling coils shall not be installed _______ storage containers

A

Inside

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

ASME containers installed underground, partially underground, or as a mounded installation shall incorporate provisions for_____

A

Cathode protection And shall be coated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cylinders filled on site at the point of use shall be requalified in a accordance with

A

DOT requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cylinders filled on site at the point of use shall be visually inspected within ______ and within every _____ thereafter

A

12 years, 5 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A cylinder that passes, the visual examination is marked with the month and year of examination, followed by the letter ____ indicating requalification

A

E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The results of the visual inspection are documented, and a record of the inspection is retained for a _________

A

Five year period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In addition to the applicable provisions for horizontal ASME containers, vertical ASME containers over _____ Shall comply with 5.2.4.3 A through 5.2.4.3 E

A

125 gallons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The maximum allowable working pressure shall be at the top head, with allowance made for increased pressure on the lower shell sections and the bottom head due to the _______

A

Static pressure of the product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Windspeeds shall be based on a mean occurrence interval of

A

100 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Shop fabricated containers shall be fabricated with ___________ or other means to lift the container

A

Lifting lugs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Cylinders shall be designed and constructed for at least a _______ service pressure

A

240 psig

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

ASME containers of more than _____ gallons through 2000 gallons water capacity that are designed to be filled volumetric shall be equipped for filling into the vapor

A

30 gallons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

ASME containers of 126 gallons through 4000 gallons water capacity in other than bulk plant and industrial occupancies shall be provided with an opening for an ______

A

Actuated liquid withdrawal excess flow valve with a connection, not smaller than 3/4 inch NPT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

ASME containers of more than 4000 gallons shall have an opening for a ________

A

Pressure gauge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

ASME containers in storage or use shall have pressure relief valve connections that have direct communication with ____ ______ of the container

A

Vapor space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

If the pressure relief valve is located in any portion, other than the________ of the ASME container, the connection shall be internally piped To the uppermost point practical in the vapor space of the container

A

Uppermost point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

ASME containers to be filled on a volumetric basis_____ so that they can be equipped with a fix maximum liquid level gauge

A

Shall be fabricated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Vertical ASME containers over _______ water capacity for use in permanent installations stationary service shall be designed with steel supports that allow the container to be mounted on and fastened to concrete foundations or supports

A

125 gallons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Steel support shall be protected against_______ with a material having a fire resistance rating of at least two hours

A

Fire exposure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The bottom of container skids shall not be less than ____ or more than______ below the outside bottom of the tank shell

A

2 inches, 12 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

The marking specified for ASME containers shall be on a ______ Attached to the container, located to remain visible after the container is installed.

A

Stainless steel metal nameplate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Gray cast iron shall:

A

Not be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Non-metallic materials, for bonnets or bodies of valves or regulators

A

Shall not be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Container apparatuses shall have a service pressure of at least

A

250 psi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Gaskets should be made of metal or other material confined in metal having a melting point over _________ or shall be protected against fire exposure

A

1500°F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

When a flange is open, the gasket shall be

A

Replaced

33
Q

ASME containers shall be equipped with one or more __________ that are designed to relieve vapor

A

Pressure relief valves

34
Q

ASME containers for LP – gas shall be a equipped with direct ________ pressure relief valves conforming with the requirements of ANSI – UL 132

A

Spring loaded

35
Q

Relief valves for above ground ASME containers shall relieve before the pressure exceeds __________ the minimum permitted start to leak pressure setting of the device

A

120%

36
Q

Vapor inlet openings shall be equipped with either of the following: a positive shut off valve that is located as close to the container as practical in combination with either a backflow check valve or an excess flow valve installed in the container or

A

An internal flow valve

37
Q

Liquid level gauging devices shall be installed on all containers filled by

A

Volume

38
Q

Cargo tanks and ASME containers utilizing multiple fixed liquid level gauges having the loading percentage to the nearest _______ stamped adjacent to each gauge

A

2/10ths percent

39
Q

Pressure gauges shall be attached directly to the container, opening or valve or fitting that is directly attached to the

A

Container opening

40
Q

If the cross-sectional area of The opening into the container is greater than a _____ an excess flow check valve shall be provided for the container connection

A

Number 54 drill size

41
Q

Single stage regulators shall have a maximum outlet pressure of _____

A

1.0 PSIG

42
Q

Cast-iron pipe fittings

A

Shall not be used

43
Q

Brazing filler material shall have a melting point that exceeds

A

1000°F

44
Q

 Tank heaters shall be approved and shall be permanently and legibly marked with

A

Rated input to the burner in BTU per hour

45
Q

Tank heaters shall be approved and shall be permanently and legibly marked with the following a maximum vaporizing capacity in

A

Gallons per hour

46
Q

Tank heaters shall be approved and shall be permanently and legibly marked with the following, name or symbol of the

A

Manufacturer

47
Q

Direct gas fired tank heaters shall be designed exclusively for

A

Outdoor above ground use

48
Q

Vaporizing burners shall be constructed with a pressure rating of

A

250 psig

49
Q

Vaporizing burners shall be constructed with a safety factor of

A

5 to 1

50
Q

Pressure regulating, and control equipment shall be so located or so protected to prevent its exposure to temperatures above

A

140°F

51
Q

Hydrostatic relief valves designed to relieve hydrostatic pressure between closed shut off valves shall have pressure settings of not less than ______ or more than ______

A

400 psi, 500 psi

52
Q

Hydrostatic relief valves for use in systems designed to operate above 350 PSIG shall have settings not less than _____% and not more than _____% of the system design pressure

A

110%

125%

53
Q

Pressure containing metal parts shall be made of______, ______, ______, or _______

A

Steel, ductile iron, malleable iron, or brass

54
Q

Aluminum cylinders and composite cylinders involved in a fire shall be permanently

A

Remove removed from service

55
Q

ASME paragraph U–68 or U–69 containers shall be permitted to be

A

Continue to use, installed, reinstalled or placed back into service

56
Q

Repairs or alterations to ASME containers shall be in accordance with which code?

A

NSI/NB 23 national board inspection code

57
Q

Where the container is buried, mounded, insulated or otherwise covered so that the nameplate is obscured the information contained on the nameplate shall be

A

Duplicated and installed on an adjacent piping or structure

58
Q

Please study 5.2.8.3 C

A

Numbers 1 through 14

59
Q

Aluminum O-rings and spiral wound metal gaskets shall be

A

Permitted

60
Q

Gaskets for use with approved or listed liquid level gauges for installation on a container of 3500 gallons water capacity or less Shelby

A

Exempt from the minimum melting point requirement

61
Q

Each pressure relief valve shall be plainly and permanently marked with the following:

A

Pressure in PSIG at which the valve is set to start to leak

Rated relieving capacity in SCFM

Manufactures name and catalog number

62
Q

Each pressure relief valve shall be plainly and permanently marked with the following following:

A

Pressure in PSIG at which the valve is set to start to leak

Rated were leaving capacity in SCFM

Manufactures name and catalog number

63
Q

Pressure relief valves shall be designed to minimize the possibility of:

A

Tampering

64
Q

Pressure containing metal parts of apparatuses shall have a minimum melting point of 1500°F except for:

A

Fusible elements

Approved or listed a variable liquid level gauges used in containers of 3500 gallons water capacity or less

65
Q

Pressure containing metal parts of apparatuses shall have a minimum melting point of 1500°F except for:

A

Fusible elements

Approved or listed a variable liquid level gauges used in containers of 3500 gallons water capacity or less

66
Q

Shut off valves shall not be installed between pressure relief devices, and the container unless they listed pressure, relief, valve manifold:

A

Meeting the requirements of 6.7.2.9 is used

67
Q

Externally, set or adjusted pressure relief valves shall be provided with an approved means of:

A

Sealing the adjustment

68
Q

ASME containers having a propane capacity, not greater than ______ shall be permitted to have an external pressure relief valve.

A

100 gallons

69
Q

Valves, regulators, gauges, and other container apparatus shall be protected against:

A

Physical damage

70
Q

Every ASME storage container of more than 2000 gallons shall be provided with a:

A

Pressure gauge

71
Q

First – stage regulators shall have an outlet pressure setting up to:

A

10.0 PSIG

72
Q

Regulators shall be designed to drain condensate from the regulator spring case when the:

A

Vent is directed vertically down

73
Q

True or false PVC piping materials and polyethylene and polyamide pipe and tubing are permitted to be used to vent regulators

A

False

74
Q

The metal – gas caring portion of the Anodless riser after the transition shall have a wall thickness equal to

A

Schedule 40 pipe

75
Q

We’re fusible elements are used, they shall have a melting point not exceeding

A

250°F

76
Q

Gas – fired heating appliances, and waters heater shall be equipped with automatic devices, designed to shut off the flow of gas to the main burner, and the pilot in the event the pilot:

A

Flame is extinguished

77
Q

Tank heaters of the electric immersion type shall be automatically de-energized when the liquid level falls below

A

The top of the heater

78
Q

Direct gas fired tank heater shall be designed such that there is no direct flame:

A

impingement upon the container

79
Q

The metal gas, caring portion of the Anodeless riser after the transition shall have a wall thickness equal to

A

Schedule 40 pipe