Chapter 5 Flashcards

1
Q

A distinct, scheduled portion of work performed during the course of a project

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Information that provides schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.

A

Activity attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A tabulation of activities to be included on a project schedule

A

Activity list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities

A

Activity-on-arrow (AOA) approach or Activity-diagramming-method (ADM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The estimates that use the actual cost of a previous, similar project as the basis for estimating the cost of the current project

A

Analogous estimates or Top-down estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost estimates created by estimating individual activities and summing them to get the project total

A

Bottom-up estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Additional time to complete an activity, added to an estimate to account for various factors

A

Buffer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An occurrence when two or more activities follow a single node on a network diagram

A

Burst

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A time-phased budget that project managers use to measure and monitor cost performance

A

Cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A method of scheduling that takes limited resources into account when creating a project schedule and includes buffers to protect the project completion date

A

Critical chain scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The series of activities that determine the earliest time which the project can be completed; it is the longest path through the network diagram and has the least amount of slack or float

A

Critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A network diagramming technique used to predict total project duration and show the amount of schedule flexibility on the network paths within the schedule model

A

Critical path method (CPM) or Critical path analysis (CPA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The sequencing of project activities

A

Dependency or relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The dependencies that are defined by the project team

A

Discretionary dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The actual amount of time spent working on an activity plus elapsed time

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The number of workdays or work hours required to complete an activity

A

Effort

18
Q

The dependencies that involve relationships between project and non-project activities

A

External dependencies

19
Q

A schedule compression technique where you do activities in parallel that you would normally do in sequence

A

Fast-tracking

20
Q

Additional time added before activities on the critical path that are preceded by non-critical path activities

A

Feeding buffers

21
Q

A standard format for displaying project schedule information by displaying project activities and their corresponding start and finish dates in a calendar format

A

Ghantt charts

22
Q

When an activity requires a gap in time before it can start.

A

Lag

23
Q

When an activity can overlap a preceding one

A

Lead

24
Q

The dependencies that are inherent in the nature of the work being performed on a project

A

Mandatory dependencies

25
Q

A situation when two or more nodes precede a single node on a network diagram

A

Merge

26
Q

A significant point or event in a project

A

Milestone

27
Q

Quantitative risk analysis technique that provides a probability distribution for outcome values for the whole project

A

Monte Carlo simulation

28
Q

When a resource works on more than one activity at a time

A

Multitasking

29
Q

If something can go wrong, it will.

A

Murphy’s Law

30
Q

A schematic display of the logical relationships among, or sequencing of, project activities

A

Network diagram

31
Q

The starting and ending point of an activity-on-arrow diagram

A

Node

32
Q

A technique that uses project characteristics (parameters) in a mathematical model to estimate project costs

A

Parametric modelling

33
Q

Work expands to fill the time allowed

A

Parkinson’s Law

34
Q

A network diagramming technique in which boxes represent activities

A

Precedence diagramming method (PDM)

35
Q

A network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates

A

Program Evaluation and Review Technique (PERT)

36
Q

The additional time added before a project’s due date to account for unexpected factors

A

Project buffer

37
Q

The amount of time an activity may be delayed without delaying a succeeding activity or the project finish date

A

Slack or Float

38
Q

Work that is done in support of operational, functional, or project performance. These are not part of the schedule (activities are shown on the schedule). These include many management functions such as things done to manage the team, run a production line, or build relationships.

A

Task

39
Q

A management philosophy that states that any complex system at any point in time often has only one aspect or constraint that is limiting its ability to achieve more of its goal

A

Theory of Constraints (TOC)

40
Q

An estimate that includes an optimistic, most likely, and pessimistic estimate.

A

Three point estimate