Chapter 4.1 to 4.3 Flashcards
Q01: Which of these processes are not Technical Processes (choose 2)?
A. Implementation Process
B. Acquisition Process
C. Disposal Process
D. Measurement Process
E. Verification Process
B/D
Q02: Which three of the following are preliminary life cycle concepts that support mission needs? (Choose 3)
A. Acquisition Concept
B. Deployment Concept
C. Operational Concept
D. Budget Concept
E. Engineering Concept
A/B/C
Q03: What are the definitions of ConOps and OpsCon (choose 2)
A. ConOps describes the organization’s assumptions to an overall operation of the business with using the system to be developed, existing systems, and possible future systems
B. OpsCon describes the organization’s assumptions to an overall operation of the business with using the system to be developed, existing systems, and possible future systems
C. ConOps describes system characteristics from a user’s viewpoint
D. OpsCon describes system characteristics from a user’s Viewpoint
A/D
Q04: The OpsCon is just one of the life cycle concepts required to adress the stakeholder needs across the system life cycle. In addition to the operational aspects, other related life cycle concepts are required to address (choose 3);
A. Acquisition concept
B. Retirement concept
C. Production concept
D. Deployment concept
A/B/D
Q05: Which three of the following are described in a System Operational Concept (OpsCon) document? (Choose 3).
A. Constraints of the project.
B. What the tystem will do.
C. How the system will operate.
D. Why (rationale)
E. System’s characteristics from user’s viewpoint
B/D/E
Q06: Which of the following are outputs for Business or Mission Analysis process (choose 3)?
A. Business or mission analyisis report
B. Major stakehoider identification
C. Business or mission analysis strategy
D. Major stakeholder requirements
E. Business requirements
B/C/E
Q07: Which of the following are inputs for Stakeholder Needs and Requirements Definition process (choose 3)
A. Source documents
B. Stakeholder requirements
C Stakeholder needs
D. Project constraint
A/C/D
Q08: Which of the following are outputs of Stakeholder Needs and Requirements Definition process (choose 3)?
A. Measures of effectiveness needs
B. Measure of performance needs
C Validation critera
D. Stakeholder list
E. Stakeholder requirements
A/C/E
Q09: Which step should be conducted in the Stakeholder needs and requirement definition process (choose 1)?
A. Document the business case
B. Perform analysis to develop the operational concept
C Use the Markov method to identify the key stakeholders
D. Document only the needs from the highest equity stakeholders
B
Q10: Which of the following are techniques usable to elicit user requirements (choose 3)?
A. Interviews
B. Focus groups
C. KTA and AHP models
D. Delphi method
A/B/D
Q11: The requirements database is Initiated as part of (choose 1)?
A. Stakeholder needs and requirements definition process
B. System requirements definition process
C. Architectural definition process
A
Q12: Which of the following are life cycle concepts refined in the stakeholder needs and requirements definition process (choose 2)?
A. Acquisition concept
B. Production concept
C. Retirement concept
D. Research concept
A/C
Q13: Which of the following are inputs for System Requirements Definition process (choose 3)?
A. Life cycle concepts
B. System functions
C. Initial RVTM
D. Stakeholder requirements
A/C/D
Q14: Which of the following are outputs of System Requirements Definition process (choose 2)?
A. Verification criteria
B. Technical performance measures needs
C. System requirements
D. Initial RVTM
A/C
Q15: Which of the following are constraints need to be reflected to define system requirements (choose 3)?
A. Standards
B. Essential design consideration
C. Stakeholder requirements
D. Utilization environments
A/B/D