Chapter 3 - Termination of Contract Flashcards
What is the normal method of discharging a contract
Performance - each party fulfils/performs contractual obligations
T/F
So long as there is substantial performance of party’s contractual obligations that will be sufficient discharge
True
What happens if one party prevents performance
offer of performance by the other is sufficient discharge they can sue for damages for breach or bring ‘quantum merit’ action to claim for work completed
Planché v Colburn 1831
P had agreed to write book on costumes and Arbor for a book series and was to receive £100 on completion. Did some research and wrote some, series abandoned by C.
Held P was entitled to 50 guineas (little over 50£) as reasonable remuneration on quantum merit basis
When is a contract discharged by frustration
If after made, performance or further performance is impossible or totally futile by some extraneous cause (for which neither party is responsible and there is no prevision for) the contract will be treated as discharged by frustration
If it is impossible to perform the contract when it is made then
there is usually no contract at all
Frustration
Destruction of subject matter example Taylor v Caldwell 1863
Hall let to musician for series of concerts, but before date of first concert, hall accidentally destroyed by fire
Frustration
Personal incapacity to perform contract of personal service
Condor v the Barron Knights 1966
Drummer contracted to perform 7 nights a week, due to ill health could only perform 4
Frustration
Government intervention explanation
Where outbreak of war/new legislation rendered further performance of the contract illegal
Frustration
Non-occurrence of an event which is the sole purpose of the contract
Krell v Henry 1903
Room let for sole purpose of overlooking coronation procession of a king, illness caused the procession to be postponed
What regulates the rights and liabilities of parties discharged by frustration
Law reform Frustrated Contracts Act 1943
Consequences of frustration under Law reform frustrated contracts act 1943
Money paid before frustrating event to be repaid
sums due for payment cease to be payable
if person has to repay money, or must forego payment that should have been made before frustrating event, may be able to recover expenses incurred if they were incurred in performance of the contract and before frustrated
If either party has obtained a valuable benefit under the contract before it is discharged, the court may in its discretion order them to pay the other party all/such part of the value as it considers just having regard to all circumstances of the case
BP Exploration Libya ltd v Hunt 1982
Hunt owned oil concession in libya, BP contracted to explore and exploit oil fields in return for share of concession if successful, investigation revealed large oil field, pipes laid, Libyan government cancelled concession, frustrated contract
Held Hunt received valuable benefit 85m in terms of increased value due to discovering oil, court awarded just sum (35m) to represent this, taking account of circumsatances
Breach of contract is where
a party does not perform their contractual obligation sufficiently
When is there a lawful excuse and no breach of contract (3)
Tendered performance but this has been rejected
other party made it impossible for them to perform
Parties have by agreement permitted non-performance
Repudiatory breach
Breach is of a term that is fundamentally important/has effect of depriving injured party of substantially the whole benefit of the contract
Yes
Repudiatory breach
Where one party renounces their contractual obligations explicitly or implicitly in advance by showing they have no intention of performing them
Yes - also known as anticipatory breach
Where breach is sufficiently serious, injred party may choose to either
treat contract as discharged immediately and sue for damages, or allow contract to continue until actual breach and take action at that time
Can the injured party seek damages for any breach of contract
Yes
Poussard v Spiers 1876
P agreed to sing in opera, she was ill and couldn’t perform opening night. Producer engaged substitute who insisted on being engaged for the whole run, when P recovered, producer declined to accept services.
Held failure to sing opening night was breach of condition, entitled producer to treat contract for remaining performances as discharged
Rochester v De La Tour 1853
DLT engaged H as courier to accompany on European tour on 1 June, on 11 May DLT wrote saying no longer required services. 22 May, H commenced legal proceedings for anticipatory breach, DLT stated no actionable breach until 1 June
Held H entitled to sue as soon as anticipatory breach occured
T/F
If innocent party elects to treat contract as still in force after anticipatory breach, may continue with preparations and recover agreed price. Duty to mitigate less does not arise until accept breach, need to show losses caused by actual breach
True
t/f
if innocent party elects to treat contract as discharged, must notify other party.
True
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
They are not discharged from obligations due at the time of termination, but from future obligations and cannot be sued on them
True
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
Need not accept/pay for further performance
True
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
May refuse to pay for partial/defective performance already received
True - unless contract is severable
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
May refuse to pay for partial/defective performance already received
True - unless contract is severable
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
Can still reclaim money already paid in respect of defective performance
True
T/F
if innocent party elects to treat as discharged by refusal to accept further performance/refusal to perform own obligations then
can still claim damages from defaulter
True
What are damages designed to do
Put the claimant in the position they would have been in had the contract been performed
what is considered regarding remoteness of damage
How far down the sequence of cause and effect the consequences of breach should be tranced before they should be ignored
Damages may only be awarded in respect of losses that may fairly and reasonably be considered as either
arising naturally from breach or such as may reasonably be supposed to have been in contemplation of both parties at the time of making the contract as the probable result of the breach
Hadley v Baxendale 1854
C owned mill, when shaft broke, made contact for transport of broken shaft to greenwich to serve as pattern for making new shaft. Due to D neglect, delivery delayed mill out of action, D didn’t know mill idle, just to transport broken shaft
Held although D failure was direct cause, claim must fail as it was not natural consequence of delay in transport of broken shaft
T/F
If the defendant can show the chain of causation was broken and the claimant cause the loss, the defendant is not liable
True