Chapter 15 Payments Flashcards
Periodic Payments
Generally on monthly basis
Unit Price Contracts
Similar to lump sum contracts.
Payment is based on the unit prices as bid and the precise measurements of in-place field quantities.
Cost Plus Contracts
Contractor is reimbursed for direct expenditures plus an allowance to cover overhead and profit which may vary depending on the nature of the expense.
Lump Sum Contracts
Contract stipulates that before performing, the C will submit a schedule of values or cost breakdown of all work items for which payments will be requested.
“Bury”
C will always try to “bury” certain costa in other job items
“No excuse bonus”
Completion date will not be changed under any circumstance other than a disaster
Project Closeout
Ensures quality of the project
Contractor must show that completed project meets the terms of the agreement between the owner and contractor.
Final payment
Verifying punch lost items have been corrected and all aspects of project are in top shape
Retainage
O typically holds back/retains percentage of money earned as an incentive for C to complete project properly. (5-20%)
Sometimes stops after 50% complete project
Paid w/in 30 days
Sub C Payments
Subs have their own K with C
Usually paid when C is paid
Pay-if-paid
Stipulates that C has no obligation to pay Sub C if O fails to pay