Chapter 14 Matters of Time Flashcards
Working Day schedule is appropriate when
The site conditions are subject to delays (weather, differing site conditions)
Federal agencies use?
Calendar day schedule
State agencies use
Working day schedule
Private O uses what
Either calendar or fixes completion day
What does O require for his assurance that C will complete the job?
Requires C to submit a schedule before conference
Critical Activity
One that must start ASAP as it’s proceeding activity has been completed and must be completed in the allotted time or the project will be delayed.
Define the Critical Path Method
Longest sequence of activities in a project to complete on the due date
Who Owns the Float?
K should address it otherwise it could be either O or C.
Construction Schedule
Contract requires C to submit schedule that shows how projects is going to be executed
Calendar days
Considers all calendar days including weekends and holidays
Working Day Schedule
Considers only working days excludes weekends and holidays
Limitation of Operations
O may place a restriction on C by placing limitation of operations provision that specifically prohibits work on certain days
Three types of Delays
- The C and his agents
- The O and his agents
- Force Majeure or Acts of God
Delay of C or his agents
If delay is of such magnitude, O can terminate project if it’s too much. Usually O will try to work with C
Delay of O or his agents
- An extension is usually granted to duration
- C’s right to terminate stems only from O’s delay in making payments