Chapter 12: Capital Project Appraisal Flashcards
Capital project
Any project where there is initial expenditure and then, once the project comes into operation, a stream of revenues less running costs.
Main purpose of INITIAL capital project appraisal
To ascertain whether a project satisfies the criteria that have been established by the sponsoring organisation for projects that it is prepared to authorise.
Criteria are usually expressed in terms of
- FINANCIAL results and risks
- SYNERGIES with other projects
- POLITICAL constraints
- sufficient upside POTENTIAL
- use of scarce RESOURCES
Final criteria may be expressed in terms of
- NPV
- IRR
- payback period
- discounted payback period.
Specific Risk
Probabilistic risk
The element of risk that can be eliminated either by repeated investment in the same project,
or - failing this - by diversification over a number of different projects.
Specific risk analysis
Consists of
- IDENTIFYING
- QUANTIFYING
the risks,
where possible:
- MITIGATING the risks
- MANAGING any residual risks that remain.
Specific risks must be (3)
- identified
- analysed
- mitigated
Residual risks
Specific risks that cannot be mitigated.
They must be managed carefully and highlighted to the sponsors.
Specific risks can be identified using (5)
- high level PRELIMINARY ANALYSIS
- BRAINSTORMING with experts
- DESKTOP ANALYSIS
- risk register
- risk matrix
Analysis of specific risks involves characterising them by (4)
- FREQUENCY of occurrence
- FINANCIAL consequences
- CORRELATIONS between risks
- CONTROLLABILITY
6 key methods of mitigating specific risk
- SHARING the risk
- TRANSFERRING the risk
- AVOIDING the risk
- INSURING the risk
- REDUCING the risk (frequency and/or consequences)
- further researching of the risk
Each mitigation option for a particular risk will be evaluated, assessing:
FEASIBILITY and cost of implementing the option
likely EFFECT on frequency, consequence and expected value
- overall impact on the distribution of NPVs
any “SECONDARY RISKS” resulting from the option
- further mitigating actions to respond to secondary risks
Systematic risk
Element of risk that cannot be eliminated by diversification, no matter how widely we spread our investment and no matter how often a particular project is repeated.
Final investment decision will reflect…
- distribution of NPVs
- characteristics of the residual risks that cannot be mitigated.
Investment submission
Results of the detailed appraisal is written up in a document called the investment submission
Considerations in the investment decision, beyond the investment submission, might include…
- allowance for any likely bias or possible approximations in the estimates
- “hunch”
- knowledge not in the possession of those who have prepared the submission
- last-minute developments
- doubts about feasibility or quality of implementation
- overall project credibility.
Crieteria involved in “initial appraisal”
- promising financial results
- acceptable risks that these results may not be achieved
- achieving synergy or compatibility with other projects undertaken by the sponsor.
- satisfying “political constraints” both within and without the sponsoring organisation
- having sufficient upside potential
- using scarce investment funds or management resources in the best way
Possible inclusions in the scope of a project
- to WHOM (or which departments) the goals of the project apply (and who should not be affected)
- exact RESPONSIBILITIES of the people involved in the project team
- a list of connected ISSUES for which the project team is not responsible.
- SUCCESS CRITERIA of the project and how these will be measured
- TIMESCALES involved including limits beyond which the project team’s responsibilities and powers will not extend
- BUDGET of the project
Evaluation of cashflows step
an evaluation of the most likely cashflows for the
- capital expenditure,
- running costs,
- revenues
- termination costs.
The cashflows should allow for any consequential effects on the sponsor’s other activities or costs.
4 Appraisal techniques (financial results
- Net present value (NPV)
- internal rate of return (IRR)
- payback period
- discounted payback period
payback period
the length of time before the capital expended on the project is recouped from the net revenues (consisting of the gross revenues less running costs), without discounting the cashflows.
discounted payback period
as per the payback period but with discounting of the cashflows
Sensitivity analysis
investigates how the profitability of the project changes in response to a change in a single assumption in isolation.
Scenario testing
varies several assumptions simultaneously and in a mutually consistent fashion.