Chapter 10: Organisation theme Flashcards

1
Q

What is the purpose of the PRINCE2 organisation theme?

A

To define and establish the project’s structure of accountability and responsibilities (the ‘who?’).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is it important to establish a project management team structure early in a PRINCE2 project?

A

To ensure effective direction, management, control, and communication throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the three principal categories of stakeholders in PRINCE2?

A

Business, User, and Supplier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the role of the business stakeholder in PRINCE2?

A

To ensure that the project meets a business need, justifies the investment, and provides value for money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the role of the user stakeholder in PRINCE2?

A

To specify the desired outputs and ensure the project delivers them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the role of the supplier stakeholder in PRINCE2?

A

To provide resources with the necessary skills to create the project’s outputs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does PRINCE2 mandate in terms of project roles?

A

Certain roles must be fulfilled on every project, though they can be combined depending on the project’s needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does Agile differ from PRINCE2 in terms of roles?

A

Agile emphasizes self-organising teams with a focus on leadership (e.g., Scrum Master), while PRINCE2 has defined roles with clear responsibilities and accountability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the PRINCE2 team manager role and how does it integrate with agile delivery teams?

A

The team manager has defined responsibilities and works closely with agile delivery teams, balancing project management needs and empowering the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the key focus in agile delivery teams?

A

The team should be self-organising, with an emphasis on autonomy and cross-functional skills.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the advantage of having multi-skilled people in agile teams?

A

It allows for flexibility and quicker adaptation to changes, as team members can assist in various tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the RACI model used for?

A

To define roles and responsibilities: Responsible, Accountable, Consulted, and Informed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is a single-team project structure used in PRINCE2 Agile?

A

In small projects, where the roles of project manager and team manager can be combined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does a multiple-team project structure work in PRINCE2 Agile?

A

It involves one project manager and several team managers, with customer and supplier roles integrated across teams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly