CH11 Flashcards
The project charter provides the project manager with the authority to apply ________ to project activities.
organizational resources
The ________ meeting is typically held at the end of planning and the start of executing.
kick-off
The project management plan integrates and consolidates all ________ and baselines.
subsidiary management plans
The ________ includes raw observations and measurements identified during project execution.
work performance data
Knowledge management techniques include ________, storytelling, and workshops.
networking
Changes are recorded in the ________ log to track all requested and approved modifications.
change
The key benefit of the Monitor and Control Project Work process is to provide ________ into the current and future project status.
visibility
The ________ is used as a formal record of lessons learned during the project.
lessons learned repository
________ is the process of finalizing all activities for the project, phase, or contract.
Close Project or Phase
The ________ provides details of how change requests will be formally authorized and incorporated.
change management plan
The ________ outlines the roles and responsibilities of the change control board (CCB).
configuration management plan
Outputs from Direct and Manage Project Work include ________, work performance data, and issue logs.
deliverables
A ________ is any unique and verifiable product or capability required to complete a project.
deliverable
The ________ describes the series of phases a project passes through from initiation to closure.
project life cycle
Corrective actions are intentional activities that ________ the performance of project work.
realign
Which document formally authorizes the existence of a project?
a) Business Case
b) Project Charter
c) Issue Log
d) Change Log
b) Project Charter
Which of the following is NOT an input to the project charter process?
a) Business case
b) Agreements
c) Lessons learned register
d) Organizational process assets
c) Lessons learned register
The primary purpose of the project kick-off meeting is to:
a) Communicate project objectives
b) Distribute deliverables
c) Approve the project charter
d) Close the project
a) Communicate project objectives