CH11 Flashcards

1
Q

The project charter provides the project manager with the authority to apply ________ to project activities.

A

organizational resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The ________ meeting is typically held at the end of planning and the start of executing.

A

kick-off

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The project management plan integrates and consolidates all ________ and baselines.

A

subsidiary management plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The ________ includes raw observations and measurements identified during project execution.

A

work performance data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Knowledge management techniques include ________, storytelling, and workshops.

A

networking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Changes are recorded in the ________ log to track all requested and approved modifications.

A

change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The key benefit of the Monitor and Control Project Work process is to provide ________ into the current and future project status.

A

visibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The ________ is used as a formal record of lessons learned during the project.

A

lessons learned repository

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

________ is the process of finalizing all activities for the project, phase, or contract.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The ________ provides details of how change requests will be formally authorized and incorporated.

A

change management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The ________ outlines the roles and responsibilities of the change control board (CCB).

A

configuration management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Outputs from Direct and Manage Project Work include ________, work performance data, and issue logs.

A

deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A ________ is any unique and verifiable product or capability required to complete a project.

A

deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The ________ describes the series of phases a project passes through from initiation to closure.

A

project life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Corrective actions are intentional activities that ________ the performance of project work.

A

realign

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which document formally authorizes the existence of a project?
a) Business Case
b) Project Charter
c) Issue Log
d) Change Log

A

b) Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which of the following is NOT an input to the project charter process?
a) Business case
b) Agreements
c) Lessons learned register
d) Organizational process assets

A

c) Lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The primary purpose of the project kick-off meeting is to:
a) Communicate project objectives
b) Distribute deliverables
c) Approve the project charter
d) Close the project

A

a) Communicate project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a key output of the Close Project or Phase process?
a) Issue log
b) Final report
c) Approved change requests
d) Work performance reports

A

b) Final report

20
Q

The Monitor and Control Project Work process allows stakeholders to:
a) Approve the business case
b) Track project performance
c) Schedule kick-off meetings
d) Reallocate resources

A

b) Track project performance

21
Q

Which of the following is NOT a tool or technique for knowledge management?
a) Storytelling
b) Online forums
c) Lessons learned register
d) Work shadowing

A

c) Lessons learned register

22
Q

What type of analysis is used to determine the best corrective action?
a) Variance analysis
b) Root cause analysis
c) Cost-benefit analysis
d) Trend analysis

A

c) Cost-benefit analysis

23
Q

Changes to project deliverables are recorded in the:
a) Scope baseline
b) Configuration management plan
c) Change log
d) Issue log

A

c) Change log

24
Q

What is the primary output of the Direct and Manage Project Work process?
a) Status reports
b) Deliverables
c) Work performance data
d) Change requests

A

b) Deliverables

25
Which meeting typically occurs at the beginning of each phase in a multi-phase project? a) Kick-off meeting b) Lessons learned session c) Change control board meeting d) Status meeting
a) Kick-off meeting
26
Work performance data is analyzed during which process? a) Manage Project Knowledge b) Perform Integrated Change Control c) Monitor and Control Project Work d) Close Project or Phase
c) Monitor and Control Project Work
27
The ________ is created early in the project and updated throughout its life cycle. a) Change log b) Lessons learned register c) Final report d) Stakeholder register
b) Lessons learned register
28
A key feature of the configuration management plan is: a) Setting project baselines b) Tracking stakeholder satisfaction c) Maintaining the consistency of project artifacts d) Monitoring procurement activities
c) Maintaining the consistency of project artifacts
29
Corrective actions ensure that the project: a) Aligns with the project charter b) Aligns with the project management plan c) Aligns with stakeholder expectations d) Avoids all defects
b) Aligns with the project management plan
30
Who typically approves changes to the project management plan? a) Project manager b) Sponsor c) Change control board (CCB) d) Stakeholder committee
c) Change control board (CCB)
31
The project charter is updated regularly throughout the project.
False. The project charter is typically created once at the start of the project and is not regularly updated.
32
A comprehensive project management plan includes baselines and subsidiary management plans.
True.
33
Knowledge management tools focus exclusively on capturing explicit knowledge.
False. Knowledge management tools focus on capturing both explicit and tacit knowledge.
34
Deliverables are an output of the Direct and Manage Project Work process.
True
35
Corrective actions modify project baselines directly.
False. Corrective actions align project performance with the project management plan but do not directly modify baselines.
36
The lessons learned repository is updated only at the end of a project.
False. The lessons learned repository is updated throughout the project as lessons are identified.
37
The kick-off meeting helps align team members with project objectives.
True.
38
The business case is primarily used to assess the project's performance.
False. The business case is used to justify the project and define its objectives, not to assess its performance.
39
The Close Project or Phase process includes archiving project information.
True.
40
Work performance data includes raw observations and measurements.
True.
41
Changes must be documented in the change log before implementation.
True.
42
A performance measurement baseline integrates scope, cost, and schedule plans.
True.
43
Approved change requests are implemented through the Monitor and Control Project Work process.
False. Approved change requests are implemented through the Direct and Manage Project Work process.
44
A configuration management plan helps define how changes are managed.
True.
45
The final report summarizes project performance, including cost and quality objectives.
True