Ch 6 Project Schedule Management Flashcards

1
Q

Schedule Baseline

A

One of the three baselines in the project management plan that the project manager and team will use to measure the progress of the project schedule

It will include the baseline start and end dates of the project

An output of the Develop Schedule process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Management Plan

A

The management plan that documents how the project defines the activities, sequences the activities, estimates the resources, develops the schedule and controls the schedule to ensure the project stays on schedule.

An output of the Plan Schedule Management process (Schedule/Planning)

An input to the:

  • Develop Project Management Plan process (Integration/Planning)
  • Define Activities process (Schedule/Planning)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Parametric Estimating

A

A method of estimation that uses a math algorithm based on historical data and variables to calculate cost or duration

A tool used to help execute the Estimate Activity Durations process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity Attributes

A

Detailed information about each activity (e.g., resources necessary, location, cost, assumptions, constraints, leads and lags, and relationships to other activities)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Plan Schedule Management

A

The process of establishing the policies, procedures, and documentation for planning, developing, executing, and controlling the schedule

Knowledge Area: Schedule

Process Group: Planning

Inputs:

  • Project Charter

Tools:

  • None

Outputs:

  • Schedule Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Schedule Management

A

Knowledge area regarding the processes required to manage the timely completion of the project; creating the schedule baseline, project schedule, and ensuring the project stays on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Control Schedule

A

The process of monitoring the status of the project to:

  • Ensure that it finishes on the schedule baseline
  • Update the project schedule
  • Manage changes to the schedule baseline

Knowledge Area: Schedule

Process Group: Monitoring & Controlling

Inputs:

  • Work Performance Data

Tools:

  • None

Outputs:

  • Work Performance Information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Dependency Determination

A

There are four types of activity dependencies:

  • Mandatory (hard logic/dependency): must be done; could halt the project (e.g., government regulations); can be imposed by customer or sponsor
  • Discretionary (soft logic): best practice, customary
  • External: outside the project team’s control (e.g., construction permits, deliveries)
  • Internal: within the project team’s control

A tool used to help execute the Sequence Activities process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Duration Estimates

A

Duration estimates for each individual activity

A numerical estimation (e.g., hours, days, weeks required) with ranges, if known

An output of the Estimate Activity Durations process (Schedule/Planning)

An input to the Develop Schedule process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

(Total) Float or Slack

A

The amount of time you can delay an activity (or multiple activities) without delaying the entire project

An important concept for the Critical Path Method, a tool used to help execute the Develop Schedule process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sequence Activities

A

The process of putting identified activities in the order they will be performed; identifying and documenting the relationships between project activities

Knowledge Area: Schedule

Process Group: Planning

Inputs:

  • Activity List

Tools:

  • Precedence Diagramming Method (PDM)
  • Dependency Determination
  • Lags & Leads

Outputs:

  • Project Schedule Network Diagrams
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Crashing

A

A method of schedule compression in which more resources are added to activities to complete them faster

This method generally increases cost

A tool used to help execute the Develop Schedule process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fast Tracking

A

A method of schedule compression in which activities are completed in parallel instead of sequentially

This method generally increases risk

A tool used to help execute the Develop Schedule process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Bottom-Up Estimating

A

A method of estimation that breaks down the work into its lowest levels and aggregates the work back up to find an overall cost or duration

The most accurate method that requires more work and time to complete

A tool used to help execute the Estimate Activity Durations process (Schedule/Planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define Activities

A

The process of taking the work packages from the WBS and breaking them down (decomposition) into activities; identifying and documenting the specific actions to be performed to produce the project deliverables

Knowledge Area: Schedule

Process Group: Planning

Inputs:

  • Project Management Plan
    • Scope Baseline
      • WBS
      • WBS Dictionary
      • Project Scope Statement
    • Schedule Management Plan

Tools:

  • Decomposition
  • Rolling Wave Planning

Outputs:

  • Activity List
  • Activity Attributes
  • Milestone List
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Compression

A

Shortening the duration of the project schedule without changing or reducing the scope

A tool used to help execute the Develop Schedule process (Schedule/Planning)

17
Q

Resource Leveling

A

A resource optimization technique used when resources are limited or over-allocated

Activities are resequenced and/or activity dates are extended to accommodate the resource constraints (e.g., changing the schedule so that parallel activities become sequential)

Doing this usually increases the critical path

A tool used to help execute the Develop Schedule process (Schedule/Planning)

18
Q

Three-Point Estimating

A

A method of estimation also known as “PERT” (program evaluation and review techniques), which uses three values to calculate the cost or duration of an activity:

  • Optimistic: best case
  • Most likely (realistic): most likely or realistic case
  • Pessimistic: worst case
  • Normal PERT Formula (Beta Distribution):
    • (Optimistic + (4*Realistic) + Pessimistic) / 6

A tool used to help execute the Estimate Activity Durations process (Schedule/Planning)

19
Q

Risk Register

A

A list of all the identified project risks, as well as their impact and response

An output of the Identify Risks process (Risk/Planning)

An input of the Estimate Activity Durations process (Schedule/Planning)

20
Q

Activity List

A

A detailed list of the work needed to complete each work package; each activity should map back to only one work package, since each work package has many activities

An output of the Define Activities process (Schedule/Planning)

An input to the:

  • Sequence Activities process (Schedule/Planning)
  • Estimate Activity Durations (Schedule/Planning)
  • Estimate Activity Resources (Resource/Planning)
21
Q

Lag

A

Delays or waiting time between activities

Always denoted with a positive number above an arrow (not a box)

A tool used to help execute the Sequence Activities process (Schedule/Planning)

22
Q

Resource Breakdown Structure

A

The hierarchical breakdown of resources by their categories and types

An output of the Estimate Activity Resources process (Resource/Planning)

An input to the Estimate Activity Durations process (Schedule/Planning)

23
Q

Develop Schedule

A

The iterative process of creating the project schedule and the schedule baseline; the project manager will continue updating the schedule throught the project life cycle

Knowledge Area: Schedule

Process Group: Planning

Inputs:

  • Duration Estimates
  • Project Schedule Network Diagrams

Tools:

  • Critical Path Method
  • Critical Chain Method
  • Resource Optimization Techniques
    • Resource Leveling
  • Data Analysis
    • Monte Carlo Simulation
  • Schedule Compression
    • Crashing
    • Fast Tracking

Outputs:

  • Schedule Baseline
  • Project Schedule
    • Bar / Gantt Charts
    • Milestone Charts
24
Q

Analogous (Top-Down) Estimating

A

A method of estimation also known as “top-down estimation” that relies on historical information from similar projects to assign the current cost or duration to activities

Very quick and least accurate

A tool used to help execute the Estimate Activity Durations process (Schedule/Planning)

25
Q

Milestone List

A

A list of all major accomplishments or events, which have no duration

Examples include obtaining a permit, finishing a major work package

An output of the Define Activities process (Schedule/Planning)

26
Q

Critical Path Method (CPM)

A

A scheduling method that uses a network diagram to identify the critical path and calculate its duration

A tool used to help execute the Develop Schedule process (Schedule/Planning)

The exam will never ask you what the critical path is; it will only ask you for the duration of the critical path

This isn’t needed for the exam, but all activities have four dates associated with them:

  • Early Start (ES)
  • Late Start (LS)
  • Early Finish (EF)
  • Late Finish (LF)

The ES is the earliest you can start the activity without delaying the project (and so on)

27
Q

Project Schedule Network Diagrams

A

Diagram illustrating all the activities in the order they are to be performed

The number on top of the boxes indicates how long the activity will take

Unclear how these diagrams differ from PDM

An output of the Sequence Activities process (Schedule/Planning)

An input to the:

  • Develop Schedule process (Schedule/Planning)
  • NOT Estimate Activity Durations process (Schedule Planning)
28
Q

Resource Requirements

A

The resources needed to complete each activity

An output of the Estimate Activity Resources process (Resource/Planning)

An input to the Estimate Activity Durations process (Schedule/Planning)

29
Q

Free Float

A

The amount of time you can delay an activity without delaying the next activity

An important concept for the Critical Path Method, a tool used to help execute the Develop Schedule process (Schedule/Planning)

30
Q

Critical Chain Method

A

A method of schedule development in which a project buffer is placed at the end of the project instead of throughout the project schedule

A tool used to help execute the Develop Schedule process (Schedule/Planning)

31
Q

Milestone Charts

A

A time-phased graphical display of only the major project deliverables (milestones) that are points in time and have no duration

These are usually used when updating senior management, customers, or sponsors

An output of the Develop Schedule process (Schedule/Planning)

32
Q

Precedence Diagramming Method (PDM)

A

A technique used to build a sequence of defined activities; used to create the Project Schedule Network Diagrams (the output of the Sequence Activities process)

One method of PDM is an activity-on-node (AON) precedence diagram, in which the boxes are activities and the arrows indicate the type of relationship (see pgs 124-125)

  • Finish-to-Start (FS) is most frequently used
  • Finish-to-Finish (FF)
  • Start-to-Start (SS)
  • Start-to-Finish (SF)

A tool used to help execute the Sequence Activities process (Schedule/Planning)

33
Q

Bar / Gantt Charts

A

A time-phased graphical display of all the activities and their start dates, end dates, and durations

These are usually used by the project manager and team because they contain details

An output of the Develop Schedule process (Schedule/Planning)

34
Q

Estimate Activity Durations

A

The process of estimating how long each activity will take with the estimated resources; durations may vary based on individual (expert vs novice)

Knowledge Area: Schedule

Process Group: Planning

Inputs:

  • Activity List
  • Resource Breakdown Structure (RBS)
  • Resource Requirements
  • Risk Register

Tools:

  • Analogous Estimating
  • Parametric Estimating
  • Three-Point Estimating
  • Bottom-Up Estimating

Outputs:

  • Duration Estimates
35
Q

Project Schedule

A

A document that will include the start and end dates for all the activities on the project

It can be very detailed and should include bar or Gantt charts and milestone charts

An output of the Develop Schedule process (Schedule/Planning)

36
Q

Critical Path

A

The longest path through a network diagram and will represent the longest amount of time to complete a project

If the activities along this path are delayed, the entire project will be delayed

These activities are considered high-risk activities, because they have no float, which is the amount of time you can delay the activities without delaying the project end date.

Multiple critical paths indicate more project risk

An important concept for the Critical Path Method, a tool used to help execute the Develop Schedule process (Schedule/Planning)

37
Q

Monte Carlo Simulation

A

A data analysis technique done by a computer that involves going through a series of what-if scenarios that could affect the project, such as:

  • What would happen if you run two activities in parallel?
  • What-if you add more resources to these activities?
  • What if activities are delayed or finished faster?

A tool used to help execute the

  • Develop Schedule process (Schedule/Planning)
  • Perform Quantitative Risk Analysis process (Risk/Planning)
38
Q

Lead

A

An overlap between activities

Non-waiting time between activities

Always denoted with a negative number above an arrow (not a box)

A tool used to help execute the Sequence Activities process (Schedule/Planning)

39
Q

Project Calendar

A

A calendar that identifies working days and shifts that are available for scheduled activities

An output of the Develop Schedule process (Schedule/Planning)