Ch 6: Integration + Scope mngment Flashcards
What does project integration an scope management include?
- team contract
- requirements/scope statement
- WBS
What is the project planning process?
what is a baseline?
provides plans to facilitate communication and provide a baseline for measurement of process. it should guide project execution.
baseline is a startin point. an observation that is documented so it can b compared in the future .
What do team contracts do?
promote teamwork and clarify team communications.
breaks out what participation, how will communicate, how to solve problems, as what guidelines should be met
What is included in a project management plan?
- intro to the project
- project org
- management and technical process
- wrk to be performed
- schedule info
- budget info
- references to other project planning docs
What is scope?
what are deliverables ?
What is scope management?
- the requirements or features of a project and it’s end product or service.
- deliverables are items produced as part of a product such as the end product or service.
- scope management defines and controls what work is and isn’t included.
- good scope definition improves accuracy of time, cost, and resource estimates.
What does a requirements traceability matrix do?
table that lists requirements, various attributes of each requirement, and the state of the requirement to ensure that all of them are addressed
When is the WBS made?
what is a WBS?
after scope planning.
it’s a grouping of all work tasks involved in a project. provides the basis for planning and managing project schedules, costs, and changes.
Wha are user cases?
replace formal requirements. they are short descriptions of functionality told from the perspective of the user.
e. g.
- ability to store SAN info in third party database
- integrate with 3rd party reporting tool
Top 3 factors causing project problems?
- lack of user input
- incomplete requirements an specifications
- changing requirements and specifications