Ch 4: Project Time Management Flashcards

0
Q

What is project time management?

What is included? (5)

A

the processes required to ensure timely completion of a project

includes:

  • activity definition
  • activity sequencing
  • activity duration estimating
  • Schedule development
  • Schedule control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are the primary reasons for conflicts on projects?

A

Schedule issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is activity definition?

A

goal is to ensure that project team members have a complete understanding of all the work they just do as part of project scope so they can start scheduling .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is activity sequencing?

A

reviewing activities and determining dependencies between activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

3 types of dependencies for an activity?

A

Mandatory: inherent on nature of work (a certain activity must be completed before this can start)

Discretionary: defined by project team

External: involve relationships between project and non project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is activity duration estimation?

What is a three point estimate?

A

after defining and determine sequence,

now must estimate duration.

Duration = actual amount of time worked on an activity (effort) plus elapsed time.

it’s an estimation that includes optimistic, likely, and pessimistic times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule development and schedule control are what?

A

Dev: determines the project start and end dates ****
-goal is to create realistic project schedule that provides a basis for monitoring project process

Control:
-uses important tools/techniques like Gantt charts, network diagrams, and critical path analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a network diagram?

A

it’s a schematic display of the logical relationships along, or sequencing of, project activities.

CPM, PERT, PDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is slack / float time?

A

the amount of time an activity can be delayed without delaying a succeeding activity or the project finish date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are milestones?

How should milestones be set?

A

significant events on a project that normally have 0 duration.

should be tied to an event. better than an arbitrary date bc it makes the event the bad guy, and not the pm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Way to shorten the Critical path?

A
  • changing the CP activities’ scope
  • Crashing (makes cost and schedule trade-offs to obtain greatest amt of sched compression at least cost)
  • Fast tracking (doing tasks in parallel or overlapping them)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a buffer? what is the best approach to using them?

A

it’s additional time to complete a project. best to add small bits to each task bc managemet won’t like seeing a huge addition at the end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is project cost management?

A

cost is a resource sacrificed or forgone to achieve a specific objective.

PCM process is required to ensure project is completed within an approved budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is:

  • life cycle costing?
  • cash flow analysis?
  • sunk cost?
A

LCC: estimates the cost of a project plus maintenance costs on the product it produces

CFA: determines the estimated annual cost and benefits for a project

Sunk cost: costs already experienced with either decision. isn’t a criteria in project selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the four Project cost management processes? (4)

A
  • resource planning (determining what resource and quantity should be used)
  • cost estimating (developing cost and resource estimates)
  • cost budgeting (allocating overall cost estimates to individual work items to measure performance)
  • cost control (controlling changes to the project budget)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What usually represents the highest project cost?

A

PEOPLE!!

16
Q

3 ways to do cost estimates?

Whih is used most?

A
  • Analogous (use actual cost of similar project to use as basis)
  • Bottom Up (estimate individual work items and sum them to get total estimate)
  • parametric (use project characteristics in a mathematical model to estimate costs)

Bottom up used most!!!!