Ch. 12: Questions Flashcards

1
Q
Which of the following may be used as a risk mitigation tool?
A. Vendor proposal
B. Contract
C. Quotation
D. Project requirements
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You are the project manager for the 89A Project. You have created a contract for your customer. The
contract must have what two things?
A. Offer and consideration
B. Signatures and the stamp of a notary public
C. Value and worth of the procured item
D. Start date and acceptance of start date

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The project scope statement can help a project manager create procurement details. Which one of the following best describes this process?
A. The project scope statement defines the contracted work.
B. The project scope statement defines the requirements for the contract work.
C. The project scope statement defines the contracted work, which must support the requirements of the
project customer.
D. Both parties must have and retain their own copy of the product description.

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Yolanda has outsourced a portion of a project to a vendor. The vendor has discovered some issues that will influence the cost and schedule of its portion of the project. How must the agreement be updated?
A. As a new contract signed by Yolanda and the vendor.
B. As directed by the contract change control system.
C. As a memo and SOW signed by Yolanda and the vendor.
D. Project management contracts have clauses that allow vendors to adjust their work according to
unknowns.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
The United States backs all contracts through which of the following?
A. Federal law
B. State law
C. Court system
D. Lawyers
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Terry is the project manager of the MVB Project. She needs to purchase a piece of equipment for her project. The accounting department has informed Terry that she needs a unilateral form of contract. Accounting is
referring to which of the following?
A. SOW
B. Legally binding contract
C. Purchase order
D. Invoice from the vendor
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
The purpose of a contract is to distribute between the buyer and seller a reasonable amount of what?
A. Responsibility
B. Risk
C. Reward
D. Accountability
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Privity is what?
A. Relationship between the project manager and a known vendor
B. Relationship between the project manager and an unknown vendor
C. Contractual, confidential information between customer and vendor
D. Professional information regarding the sale between customer and vendor

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Sammy is the project manager of the DSA Project. He is considering proposals and contracts presented by vendors for a portion of the project work. Of the following, which contract is least risky to the DSA Project
from Sammy's perspective?
A. Cost plus fixed fee
B. Cost plus percentage of cost
C. Cost plus incentive fee
D. Fixed-price
A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
In the following contract types, which one requires the seller to assume the risk of cost overruns?
A. Cost plus fixed fee
B. Cost plus incentive fee
C. Lump-sum
D. Time and materials
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Benji is the project manager of the PLP Project. He has hired an independent contractor for a portion of the project work. The contractor is billing the project $120 per hour plus materials. This is an example of what?
A. Cost plus fixed fee
B. Time and materials
C. Unit-price
D. Lump-sum
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Mary is the project manager of the JHG Project. She has created a contract statement of work (SOW) for a vendor. All of the following contribute to the creation of the contract statement of work, except for which one?
A. Project scope statement
B. Work breakdown structure (WBS)
C. Risk register
D. WBS dictionary
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You are the project manager for a software development project for an accounting system that will operate over the Internet. Based on your research, you have discovered that it will cost you $25,000 to write your own code. Once the code is written, you estimate you’ll spend $3,000 per month updating the software with client information, government regulations, and maintenance.
A vendor has proposed to write the code for your company and charge a fee based on the number of clients using the program every month. The vendor will charge you $5 per month per user of the Web-based accounting system. You will have roughly 1,200 clients using the system per month. However, you’ll need an in-house accountant to manage the time and billing of the system, so this will cost you an extra $1,200 per month.
How many months will you have to use the system before it is better to write your own code than to hire the vendor?
A. 3 months
B. 4 months
C. 6 months
D. 15 months

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Henry has sent the ABN Contracting Company a letter of intent. This means what?
A. Henry intends to sue the ABN Contracting Company.
B. Henry intends to buy from the ABN Contracting Company.
C. Henry intends to bid on a job from the ABN Contracting Company.
D. Henry intends to fire the ABN Contracting Company.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Martha is the project manager of the MNB Project. She wants a vendor to offer her one price to do all of the detailed work. Martha is looking for which type of document?
A. Request for proposal
B. Request for information
C. Proposal
D. Invitation for bid
A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which one of the following is true about procurement documents?
A. They offer no room for bidders to suggest changes.
B. They ensure receipt of complete proposals.
C. They inform the performing organization why the bid is being created.
D. The project manager creates and selects the bid.

A

B

17
Q
In what process group does the select seller process happen?
A. Initiating
B. Planning
C. Executing
D. Closing
A

C

18
Q
You have an emergency on your project. You have hired a vendor who is to start work immediately. What contract is needed now?
A. T&M
B. Fixed-price
C. Letter contract
D. Incentive contract
A

C

19
Q

You are the project manager for a seller and are managing another company’s project. Things have gone well on the project, and the work is nearly complete. There is still a significant amount of funds in the project budget. The buyer’s representative approaches you and asks that you complete some optional requirements to use up the remaining budget. You should do what?
A. Negotiate a change in the contract to take on the additional work.
B. Complete a contract change for the additional work.
C. Gain the approval of the project stakeholder for the requested work.
D. Deny the change because it was not in the original contract.

A

C

20
Q
A tornado has wrecked your construction project. The tornado is known as what?
A. Force majeure
B. Risk transference
C. Direct costs
D. Unknown unknown
A

A