Ch. 10: Questions Flashcards
Of the following, which one is an example of noise? A. Fax machine B. Ad-hoc conversations C. Contractual agreements D. Distance
D
You are the project manager for the JHG Project. Management has requested that you create a document detailing what information will be expected from stakeholders and to whom that information will be disseminated. Management is asking for which one of the following? A. The roles and responsibilities matrix B. The scope management plan C. The communications management plan D. The communications worksheet
C
Which of the following will help you, the project manager, complete the needed communications management plan by identifying the stakeholders’ communication needs?
A. Identification of all communication channels
B. Formal documentation of all communication channels
C. Formal documentation of all stakeholders
D. Lessons learned from previous similar projects
D
You are the project manager for the JGI Project. You have 32 stakeholders on this project. How many communication channels do you have?
A. Depends on the number of project team members
B. 496
C. 32
D. 1
B
You are the project manager for the KLN Project. You had 19 stakeholders on this project and have added three team members to the project. How many more communication channels do you have now compared to before? A. 171 B. 231 C. 60 D. 1
C
A memo has been sent to you, the project manager, the project team members, and the project customers from the project sponsor. In this instance, who is the encoder? A. Project sponsor B. Project manager C. Project team members D. Project customers
A
Which one of the following is an example of a project communication constraint?
A. Ad-hoc conversations
B. Demands for formal reports
C. Stakeholder management
D. Team members in different geographical locales
D
Project managers can present project information in many different ways. Which one of the following is not a method a project manager can use to present project performance? A. Histograms B. S-curves C. Bar charts D. RACI charts
D
Of the following, which term describes the pitch and tone of an individual's voice? A. Paralingual B. Feedback C. Effective listening D. Active listening
A
You are the project manager of the KMH Project. This project is slated to last eight years. You have just calculated EVM and have a cost variance (CV) of −$3,500, which is outside of the acceptable thresholds for your project. What type of report is needed for management? A. Progress report B. Forecast report C. Exception report D. Trends report
C
You are presenting your project performance to your key stakeholders. Several of the stakeholders are
receiving phone calls during your presentation, and this is distracting from your message. This is an example of what?
A. Noise
B. Negative feedback
C. Outside communications
D. Message distracter
A
You are the project manager for the OOK Project. You will be hosting project meetings every week. Of the following, which one is not a valid rule for project meetings?
A. Schedule recurring meetings as soon as possible
B. Allow project meetings to last as long as needed
C. Distribute meeting agendas prior to the meeting start
D. Allow the project team to have input to the agenda
B
What percentage of a message is sent through nonverbal communications, such as facial expressions, hand gestures, and body language? A. Greater than 50 percent B. 30 to 40 percent C. 20 to 30 percent D. 10 to 20 percent
A
When does lessons-learned identification take place? A. At the end of the project B. At the end of each project phase C. Throughout the project life cycle D. Whenever a lesson has been learned
C
Why should a project team complete lessons-learned documentation?
A. To ensure project closure
B. To show management what they’ve accomplished on the project
C. To show the project stakeholders what they’ve accomplished on the project
D. To help future project teams complete their projects more accurately
D