Ch. 11: Questions Flashcards

1
Q

When is it appropriate to accept a project risk?
A. It is never appropriate to accept a project risk.
B. All risks must be mitigated or transferred.
C. It is appropriate to accept a risk if the project team has never completed this type of project work before.
D. It is appropriate if the risk is in balance with the reward.

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Frances is the project manager of the LKJ Project. Which of the following techniques will she use to create the risk management plan?
A. Risk tolerance
B. Status meetings
C. Planning meetings
D. Variance meetings
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
You are the project manager of the GHK Project. You and the manufacturer have agreed to substitute the type of plastic used in the product to a slightly thicker grade should there be more than 7 percent error in production. The thicker plastic will cost more and require the production to slow down, but the errors should diminish. This is an example of which of the following?
A. Threshold
B. Tracking
C. Budgeting
D. JIT manufacturing
A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
An organization's risk tolerance is also known as what?
A. The utility function
B. Herzberg's theory of motivation
C. Risk acceptance
D. The risk-reward ratio
A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The customers of the project have requested additions to the project scope. The project manager notifies you that additional risk planning will need to be added to the project schedule. Why?
A. The risk planning should always be the same amount of time as the activities required by the scope
change.
B. Risk planning should always occur whenever the scope is adjusted.
C. Risk planning should only occur at the project manager’s discretion.
D. The project manager is incorrect. Risk planning does not need to happen at every change in the
project.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which one of the following best describes the risk register?
A. It documents all of the outcomes of the other risk management processes.
B. It’s a document that contains the initial risk identification entries.
C. It’s a system that tracks all negative risks within a project.
D. It’s part of the project’s project management information system (PMIS) for integrated change control.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ include(s) fire, theft, or injury, and offer(s) no chance for gain.
A. Business risks
B. Pure risks
C. Risk acceptance
D. Life risks
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
Complete this sentence: A project risk is a(n) \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ occurrence that can affect the project for good or bad.
A. Known
B. Potential
C. Uncertain
D. Known unknown
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When should risk identification happen?
A. As early as possible in the initiation process
B. As early as possible in the planning process
C. Throughout the product management life cycle
D. Throughout the project life cycle

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
You are the project manager of the KLJH Project. This project will last two years and has 30 stakeholders. How often should risk identification take place?
A. Once at the beginning of the project
B. Throughout the execution processes
C. Throughout the project
D. Once per project phase
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Which one of the following is an acceptable tool for risk identification?
A. Decision tree analysis
B. Decomposition of the project scope
C. The Delphi Technique
D. Pareto charting
A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You are the project manager for a project that will create a new and improved Web site for your company. Currently, your company has over eight million users around the globe. You would like to poll experts within your organization with a simple, anonymous form asking about any foreseeable risks in the design, structure, and intent of the Web site. With the collected information, subsequent anonymous polls are submitted to the
group of experts. This is an example of ________________________________.
A. Risk identification
B. A trigger
C. An anonymous trigger
D. The Delphi Technique

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Which risk analysis technique provides the project manager with a risk ranking?
A. Quantifiable
B. Qualitative
C. The utility function
D. SWOT analysis
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A table of risks, their probability, impact, and a number representing the overall risk score is called a \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_.
A. Risk table
B. Probability and impact matrix
C. Quantitative matrix
D. Qualitative matrix
A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
You are presented with the following table:
What is the EMV for Risk Event 3?
Risk Event Probability Impact Cost/Benefit EMV
1 .20 -4,000
2 .50 5,000
3 .45 -300
4 .22 500
5 .35 − 4,500

A. $135
B. -$300
C. $45
D. -$135

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

You are presented with the following table:
Risk Event Probability Impact Cost/Benefit Ex$V
1 .35 − 4,000
2 .40 50,000
3 .45 -300,000
4 .30 50,000
5 .35 − 45,000

Based on the preceding numbers, what is the amount needed for the contingency fund?
A. Unknown with this information
B. 249,000
C. 117,150
D. 15,750
A

C

17
Q
The water sanitation project manager has determined that the risks associated with handling certain chemicals are too high. He has decided to allow someone else to complete this portion of the project, and so has outsourced the handling and installation of the chemicals and filter equipment to an experienced contractor. This is an example of which of the following?
A. Avoidance
B. Acceptance
C. Mitigation
D. Transference
A

D

18
Q
A project manager and the project team are actively monitoring the pressure gauge on a piece of equipment. Sarah, the engineer, recommends a series of steps to be implemented should the pressure rise above 80 percent. The 80 percent mark represents what?
A. An upper control limit
B. The threshold
C. Mitigation
D. A workaround
A

B

19
Q

You are presented with the following table:
What would Risk Event 6 be based on the following information: Marty is 60 percent certain that he can get the facility needed for $45,000, which is $7,000 less than what was planned for.
Risk Event Probability Impact Cost/Benefit Ex$V
1 .20- 4,000
2 .50 5,000
3 .45 -300
4 .22 500
5 .35 -4,500
6

What would Risk Event 6 be based on the following information: Marty is 60 percent certain that he can get the facility needed for $45,000, which is $7,000 less than what was planned for.

A. .60, 45,000, 27,000
B. .60, 52,000, 31,200
C. .60, 7,000, 4,200
D. .60, −7,000, −4,200

A

C

20
Q
Which of the following can determine multiple scenarios, given various risks and the probability of their impact?
A. Decision tree
B. Monte Carlo technique
C. Pareto chart
D. Gantt chart
A

B