Ch. 11: Questions Flashcards
When is it appropriate to accept a project risk?
A. It is never appropriate to accept a project risk.
B. All risks must be mitigated or transferred.
C. It is appropriate to accept a risk if the project team has never completed this type of project work before.
D. It is appropriate if the risk is in balance with the reward.
D
Frances is the project manager of the LKJ Project. Which of the following techniques will she use to create the risk management plan? A. Risk tolerance B. Status meetings C. Planning meetings D. Variance meetings
C
You are the project manager of the GHK Project. You and the manufacturer have agreed to substitute the type of plastic used in the product to a slightly thicker grade should there be more than 7 percent error in production. The thicker plastic will cost more and require the production to slow down, but the errors should diminish. This is an example of which of the following? A. Threshold B. Tracking C. Budgeting D. JIT manufacturing
A
An organization's risk tolerance is also known as what? A. The utility function B. Herzberg's theory of motivation C. Risk acceptance D. The risk-reward ratio
A
The customers of the project have requested additions to the project scope. The project manager notifies you that additional risk planning will need to be added to the project schedule. Why?
A. The risk planning should always be the same amount of time as the activities required by the scope
change.
B. Risk planning should always occur whenever the scope is adjusted.
C. Risk planning should only occur at the project manager’s discretion.
D. The project manager is incorrect. Risk planning does not need to happen at every change in the
project.
B
Which one of the following best describes the risk register?
A. It documents all of the outcomes of the other risk management processes.
B. It’s a document that contains the initial risk identification entries.
C. It’s a system that tracks all negative risks within a project.
D. It’s part of the project’s project management information system (PMIS) for integrated change control.
A
\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ include(s) fire, theft, or injury, and offer(s) no chance for gain. A. Business risks B. Pure risks C. Risk acceptance D. Life risks
B
Complete this sentence: A project risk is a(n) \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ occurrence that can affect the project for good or bad. A. Known B. Potential C. Uncertain D. Known unknown
C
When should risk identification happen?
A. As early as possible in the initiation process
B. As early as possible in the planning process
C. Throughout the product management life cycle
D. Throughout the project life cycle
D
You are the project manager of the KLJH Project. This project will last two years and has 30 stakeholders. How often should risk identification take place? A. Once at the beginning of the project B. Throughout the execution processes C. Throughout the project D. Once per project phase
C
Which one of the following is an acceptable tool for risk identification? A. Decision tree analysis B. Decomposition of the project scope C. The Delphi Technique D. Pareto charting
C
You are the project manager for a project that will create a new and improved Web site for your company. Currently, your company has over eight million users around the globe. You would like to poll experts within your organization with a simple, anonymous form asking about any foreseeable risks in the design, structure, and intent of the Web site. With the collected information, subsequent anonymous polls are submitted to the
group of experts. This is an example of ________________________________.
A. Risk identification
B. A trigger
C. An anonymous trigger
D. The Delphi Technique
D
Which risk analysis technique provides the project manager with a risk ranking? A. Quantifiable B. Qualitative C. The utility function D. SWOT analysis
B
A table of risks, their probability, impact, and a number representing the overall risk score is called a \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_. A. Risk table B. Probability and impact matrix C. Quantitative matrix D. Qualitative matrix
B
You are presented with the following table: What is the EMV for Risk Event 3? Risk Event Probability Impact Cost/Benefit EMV 1 .20 -4,000 2 .50 5,000 3 .45 -300 4 .22 500 5 .35 − 4,500
A. $135
B. -$300
C. $45
D. -$135
D