CDS - Contract Documents Flashcards
1
Q
contract documents consist of
A
- owner-architect/contractor agreement
- general conditions of the contract
- supplementary conditions of the contract
- drawings
- specifications
- addenda
- other documents listed in the agreement
- modifications issued after execution of the contract
2
Q
a modification is
A
- change order
- construction change directive
- written order issued by the architect for a minor change in the work
- written amendment to the contract signed by both parties
3
Q
approaches to project delivery
A
- description of the sequence of events necessary to provide an owner with a complete building
- selection of people who will design and construct the project
- establishment of contractual relationships
- organizing contractors to perform the work
4
Q
responsibility for design and construction
A
- traditional method (o-a relationship + o-c relationship)
- architect as owner’s agent with no financial stake
- fixed sum agreement with contractor
- single entity responsible for design and construction
5
Q
single entity responsible for design and construction
A
advantages:
1. allows review by construction experts
2. often includes a guaranteed cost
disadvantages:
1. eliminates the advantages of competitive bidding
2. potential conflicts because goals of the designers vary from the goals of the contractor
6
Q
agency
A
- legal concept of agency involves principal (owner), agent (architect), and third party (contractor)
- the agent works on behalf of the principal and has the authority to perform certain duties
- agent can legally bind the principal to the third party
- contractor is considered a vendor
7
Q
contract types
A
- classified by the primary relationship the owner has with the contractor
- this relationship is called the prime contract
8
Q
most common types of prime contracts
A
- single prime contract
- multiple prime contract
- many prime contracts
9
Q
single prime contract
A
- most common type of prime contracts
- GC is responsible to the owner and must coordinate the other subs
- advantage: owner has a single source of responsibility
10
Q
multiple prime contract
A
- major portions of the work are contracted separately with the owner
- disadvantage: more difficult for the architect to coordinate
11
Q
many prime contracts
A
- applied in fast track construction
2. typ. needs the use of a construction manager (if architect is unable to coordinate the effort)
12
Q
design-award-build
A
- first and most traditional project delivery method
- fairly simple: well defined roles, linear work flow
- minimal coordination problems
- contract relationships are straightforward
- owner receives fixed price before proceeding with construction
- disadvantage: one phase at a time
13
Q
fast track
A
- compressed construction schedule
- overlap between design and construction phases
- requires many prime contracts and more coordination
- can substantially reduce time and cost of a project
- may require a CM: owner’s agent, provides scheduling, early material purchasing, design review related to constructability, contract preparation
- CM may guarantee cost and time of delivery of the project
14
Q
design build
A
- single entity to provide design and construction
- design build firm subcontracts as required
- typ. used by owners who have building experience with multiple facilities and who have clearly defined needs that can be stated in performance requirements
15
Q
design build advantages
A
- single source of responsibility
- administration is direct
- fixed price early in the process
- total schedule is typ. reduced