CDS - Construction Cost Flashcards
1
Q
performance bond
A
- guarantees by a bonding company that jobs will be completed per the specifications of the contract
- if contractor is unable to complete the job, the bonding company may put the job out to bid with select contractors or complete the work themselves
- requirements are set in place by the Miller Act for all public work contracts $100k+; can also be required for private work by GC requiring it of their subs
- contractor must pay back the performance surety bond if claims are filed on it
- 1% (large projects) - 3% (smaller projects); should be included in bid so that the owner pays for it
- insurance for the owner
- count against the bond line until the job is successfully completed
2
Q
payment bond
A
- a guarantee that the GC will pay all subs, suppliers, and laborers
- it ensures the job will be completed properly
- very rare for a payment bond to be required without a performance bond; typically packaged with performance bond and one rate is applied
3
Q
items to submit for application for a performance bond
A
- business financials
- balance sheet
- income statement
- cash flow statement
- complete notes/disclosures
- work schedules
4
Q
faithful performance
A
you will complete the job properly
5
Q
if claim is raised against performance surety bond
A
- contractor may have to pay the full amount (plus legal fees)
- indemnification clause - contractor pledges corporate and personal assets in the event of bond claims; rarely waived except for Fortune 500 companies
- bonding company listens to both contractor and owner/party making the claim and determines who is in the wrong
- if bonding company agrees with contractor, they will fight for GC
- if bonding company agrees with party making the claim, they will pay out the bond and seek reimbursement from GC
6
Q
bid bond
A
- guarantees a performance bond will be provided if you are awarded the contract
- the first thing the GC needs to bid on public projects as they guarantee the bids the GC submits are accurate
- count against the bond line until the GC notifies the bonding agent they were not awarded the job
7
Q
bid spread
A
- difference between your bid and the other bidding contracts
- if it is too large, the bonding company may refuse to write the performance bond which can lead to a claim on the bid bond
8
Q
contract bond line
A
- can be thought of as a surety credit line that the GC is pre-approved to use
- a single bond limit for individual jobs (max. single contract) and an aggregate bond limit which is the total of all active bonds (max. amount of total work)
9
Q
architect’s estimates of construction costs based on final documents should consider
A
the bidding climate
10
Q
stipulated sum / fixed fee (architect’s fee)
A
- fixed sum of money + reimbursable expenses as an additional fee
11
Q
cost plus fee (architect’s fee)
A
- architect is compensated for the actual expense to do the job, plus a reasonable fee for profit (hourly basis)
- is a multiple of direct personnel expense (multiplier considers overhead and profit)
- is a multiple of direct salary expense (large multiplier to provide for employee benefits)
- hourly billing rates - client only sees one number for each of the types of people working on the project
12
Q
percentage of construction cost (architect’s fee)
A
- architect’s fee calc’d as a % of the cost of construction
13
Q
unit cost method (architect’s fee)
A
- fees are based on a definable unit such as square footage, for such work as tenant planning in a leased building or on a per-hour basis in a large residential project
14
Q
compensation methods
A
- stipulated sum / fixed fee
- cost plus fee
- percentage of construction cost
- unit cost method
15
Q
cost plus fee (contractor’s fee)
A
- compensate contractor for actual expenses plus a fixed fee for overhead and profit
- more flexibility than fixed fees
- allow construction to proceed before design is complete
- disadvantage is cost is not known