CDS - Construction Cost Flashcards

1
Q

performance bond

A
  1. guarantees by a bonding company that jobs will be completed per the specifications of the contract
  2. if contractor is unable to complete the job, the bonding company may put the job out to bid with select contractors or complete the work themselves
  3. requirements are set in place by the Miller Act for all public work contracts $100k+; can also be required for private work by GC requiring it of their subs
  4. contractor must pay back the performance surety bond if claims are filed on it
  5. 1% (large projects) - 3% (smaller projects); should be included in bid so that the owner pays for it
  6. insurance for the owner
  7. count against the bond line until the job is successfully completed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

payment bond

A
  1. a guarantee that the GC will pay all subs, suppliers, and laborers
  2. it ensures the job will be completed properly
  3. very rare for a payment bond to be required without a performance bond; typically packaged with performance bond and one rate is applied
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

items to submit for application for a performance bond

A
  1. business financials
  2. balance sheet
  3. income statement
  4. cash flow statement
  5. complete notes/disclosures
  6. work schedules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

faithful performance

A

you will complete the job properly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

if claim is raised against performance surety bond

A
  1. contractor may have to pay the full amount (plus legal fees)
  2. indemnification clause - contractor pledges corporate and personal assets in the event of bond claims; rarely waived except for Fortune 500 companies
  3. bonding company listens to both contractor and owner/party making the claim and determines who is in the wrong
  4. if bonding company agrees with contractor, they will fight for GC
  5. if bonding company agrees with party making the claim, they will pay out the bond and seek reimbursement from GC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

bid bond

A
  1. guarantees a performance bond will be provided if you are awarded the contract
  2. the first thing the GC needs to bid on public projects as they guarantee the bids the GC submits are accurate
  3. count against the bond line until the GC notifies the bonding agent they were not awarded the job
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

bid spread

A
  1. difference between your bid and the other bidding contracts
  2. if it is too large, the bonding company may refuse to write the performance bond which can lead to a claim on the bid bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

contract bond line

A
  1. can be thought of as a surety credit line that the GC is pre-approved to use
  2. a single bond limit for individual jobs (max. single contract) and an aggregate bond limit which is the total of all active bonds (max. amount of total work)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

architect’s estimates of construction costs based on final documents should consider

A

the bidding climate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

stipulated sum / fixed fee (architect’s fee)

A
  1. fixed sum of money + reimbursable expenses as an additional fee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

cost plus fee (architect’s fee)

A
  1. architect is compensated for the actual expense to do the job, plus a reasonable fee for profit (hourly basis)
  2. is a multiple of direct personnel expense (multiplier considers overhead and profit)
  3. is a multiple of direct salary expense (large multiplier to provide for employee benefits)
  4. hourly billing rates - client only sees one number for each of the types of people working on the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

percentage of construction cost (architect’s fee)

A
  1. architect’s fee calc’d as a % of the cost of construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

unit cost method (architect’s fee)

A
  1. fees are based on a definable unit such as square footage, for such work as tenant planning in a leased building or on a per-hour basis in a large residential project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

compensation methods

A
  1. stipulated sum / fixed fee
  2. cost plus fee
  3. percentage of construction cost
  4. unit cost method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

cost plus fee (contractor’s fee)

A
  1. compensate contractor for actual expenses plus a fixed fee for overhead and profit
  2. more flexibility than fixed fees
  3. allow construction to proceed before design is complete
  4. disadvantage is cost is not known
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

how to mitigate construction costs not known

A
  1. guaranteed maximums
  2. target prices with incentives
  3. partial cost guarantees - involves getting fixed prices from certain subcontractors or material suppliers
17
Q

stipulated sum / fixed price (contractor’s fee)

A
  1. fixed price owner agrees to pay contractor for work shown in contract documents
  2. simple way to arrange things
  3. owners like it because cost is known when the bids are made
  4. competitive bidding always uses a stipulated sum method
18
Q

unit price (contractor’s fee)

A
  1. used where it is not possible to firmly establish quantities at the time of bid
  2. where changes or additions are anticipated, the contractor can be requested to include unit prices in the bid
19
Q

costs

A
  1. materials, labor, equipment
  2. life cycle
  3. need balance btw client’s needs, life cycle cost, initial costs
20
Q

construction costs

A
  1. cost to build the project
  2. does not include a/e fees, financing costs, etc.
  3. architect’s estimate is a best judgement as a design professional
  4. no fixed limit of construction cost will be established as a condition of the agreement unless agreed by all parties