CDS - Construction Flashcards

1
Q

prior to beginning exterior painting

A

ensure all exterior openings are sealed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

who is responsible for construction scheduling

A

contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

smoke pencil

A
  1. a type of test equipment used to check for air infiltration on an already constructed exterior wall system
  2. tool used to identify drafts and air leaks
  3. pull the trigger on the smoke stick and see how the smoke moves to determine air movement
  4. can control the amount of smoke by using the trigger
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

HEPA filter

A
  1. high efficiency particulate air
  2. composed of mat or randomly arranged fibers
  3. particles are trapped in fibers by interception, impaction, or diffusion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

list of incomplete work and work to be corrected

A

is prepared to cover all trades

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

city required inspections and tests

A
  1. cost to be included in the construction contract; owner to pay
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

architect can decease amount of construction related waste by

A
  1. designing a materials flow plan for the contractor and user
  2. specifying recycled materials and products
  3. specifying masonry construction over wood construction
  4. assisting the owner and contractor in a waste management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

substitutions during construction phase

A
  1. may be accepted if they replace unavailable products
  2. may be accepted if they replace unsuitable products
  3. may be rejected as defective work if they lack proper approval or authorization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

method of bidding required on most government funded projects

A

public

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

if bids exceed owner’s budget, owner’s options are

A
  1. give written approval for an increase in the budget
  2. authorize rebidding or renegotiation of the project
  3. cooperate in revising the scope or quality of work
  4. require architect to modify the documents without additional compensation once the scope is reduced
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

on-site field observations, architect to observe

A
  1. the progress and quality of the work
  2. the amount of work completed (totally performed) for progress payment
  3. whether the work is being performed according to contract documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

during construction, architect is responsible for

A
  1. evaluating change orders
  2. endeavoring to guard against defects in the work
  3. determining if the work is in general conformity with the contract documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

bidding and construction, architect assists in

A
  1. preparation of bidding documents
  2. filing documents with governmental agencies for approval
  3. obtain bids or negotiating proposals
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

services by architect NOT included in basic scope (B141)

A
  1. programming
  2. extensive site representation
  3. revisions due to owner changes or change in codes/regulations
  4. intent is to clearly communicate to the client what is not considered basic serves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

progress payments

A
  1. periodic payments based on contractor’s application for payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

progress payments based on

A
  1. % completion
  2. materials purchased
  3. materials in approved storage
17
Q

% completion based on

A

a schedule of values that the contractor submits to the architect

18
Q

retainage

A

10% of construction payment sum is withheld until final completion

19
Q

to receive payment, contractor must:

A
  1. submit application for payment to architect listing the completed work and stored materials according to the schedule of values
  2. architect reviews the application, verifies it, and recommends payment to the owner
  3. if there is work in dispute, architect may choose not to certify payment of all or a portion of the amount until the problem is resolved
20
Q

changes made to the work

A
  1. made after execution of the contract
  2. made by written change order
  3. construction change directive
  4. minor change in the work
21
Q

change order

A
  1. based on a written agreement among the owner, contractor, and architect concerning the extent of the change and how it affects cost and schedule
22
Q

construction change directive

A
  1. only requires agreement between the owner and architect and may or may not be agreed to by the contractor
23
Q

minor changes

A

can be made by the architect alone