Case Study Questions Flashcards
How did you make sure you fully understood your Clients requirements?
Through communication and listening skills. I was present at the 4 design team meetings and provided the client with query sheets and request for information.
How was the budget cost of £150,000.00 ascertained?
Based on the clients brief a scope of works was drawn up and budget costs were ascertained using BCIS, Spons pricing book and recent tender return costs.
Why did you consider single stage selective tendering to be the most suitable
procurement strategy for this project/ client?
Quality, time and cost were extremely important to the client. SSST ensured that we obtained the most competitive cost to the most appropriate contractor. The design and scope of works was defined.
What other options were considered and why were these rejected?
Negotiated tender would have been a quicker process however it may not have achieved the most competitive cost or the best contractor for the job.
How were the four contractors identified as suitable for tendering?
The four contractors were selected on the basis of their ability to carry out the works. The client asked that we tender to two of the contractors. Pre Qualification questionnaires were issued to the 4 tenders to determine their financial standing, ability to undertake the works, ascertain references and proof of similar works.
What if anything was carried out prior to issuing the tender to these four
contractors?
We could have carried out pre qualification interviews however it was felt that a project of this scale and the contractors selected that the PQQ was suitable in identifying who was most appropriate to tender to.
Was there a scoring ration or matrix for the tender returns?
No however I am aware that these are used in many framework tenders and local authority jobs tendered through Public Contracts Scotland.
You mention the most competitive price, were the tenders assessed against any
other criteria?
Tenders were assessed on the following: Price Understanding of the Requirements Technical Ability Availability Proposed Methodology Qualification Notes on Form of Tender (manual handling)
Why was SBCC Minor works deemed to be the most suitable form of contract for
these works?
The work was simple in character, well defined in tender and specification documents and had no requirement for contractors design.
Talk me through the conflict of interest check that was carried out.
A conflict check was carried out on the companies database against client, address, building name and building address. No conflict existed.
What did you do to prepare for the measurement survey you undertook of the 3rd
floor?
The measured survey was carried out using gross internal area in order to ascertain the size of the suite. I ensured that the digital measuring equipment was calibrated and also carried a tape measure and camera.
What did the tender documents consist of?
Tender documents consisted of the following: Prelims Description of Works NBS PCI Drawings Any other relevant information
Talk me through your tender analysis exercise?
Once tenders received and opening exercise completed tender were assessed on the following:
Arithmetical errors Items not priced Rates Proposed Methodology Compliance with tender procedure Understanding of Requirements Qualification Notes
Talk me through the headings within your tender report?
Project, Scope of Works, Basis of Report, Review of tenders commenting from the lowest bid to the highest bid, statutory consents and recommendations.
What were your key duties as Principle Designer?
My key duties were to liaise with the client and obtain any existing H&S files, manuals and information
To identify, eliminate and control Health and Safety elements of the pre-design phase
To liaise with the Principal Contractor and ensure H&S in design changes are managed.
To obtain construction phase plan.