APC Academy - Contract Administration Flashcards

1
Q

What is an Extension of Time?

A

Claim made by the contractor due to a relevant event which has caused a delay resulting in the contractor being unable to complete works as per the contractural date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are relevant events?

A

Under JCT the following are relevant events:

• instructions/variations
• deferment of possession of the site
• suspension
• works by others (which would include works by
statutory undertakers)
• unusually adverse weather; and
• events causing delay that neither party could
prevent or foresee (which would include civil
commotion, terrorism and strikes, if these are
‘Employer’s risks’ under clause 80.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did the contractor submit their claim?

A

Contractor must submit written delay notice in accordance with clause 2.7. Delay notice must set out the circumstances and the relevant event that caused the delay. Contractor must state the effects of delay upon completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was your role in assessing the claim?

A

I assessed the claim in accordance with JCT suite of contracts which allows the CA to determine the claim within 12 weeks. (although M/W doesn’t set that out). T
I advised client and contractor that the claim was fair and reasonable and that on completion of works the claim would be assessed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is loss and expense?

A

Loss suffered as a result of variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a concurrent delay?

A

delay involving two or more events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a variation?

A

As per clause 3.6 a variation is defined as “an omission, change or other change to the works or manner in which they are to be carried out”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How are variations valued?

A

using any relevant priced specifications, schedule or contractors schedule of rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you agree on valuations?

A

priced obtained from contractor was discussed and agreed with client prior to agreeing with contractor and CVI issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When are interim payments due?

A

Typically one month after commencement and at monthly intervals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is included within a valuation?

A

The value of works completed to date and the value of materials and goods onsite.
*no provision for value of materials offsite.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How was the delay at your Netherbank Project measured?

A

By comparing actual progress achieved onsite with planned progess shown on the programme of works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a latent defect?

A

A defect that cant be determined through reasonable inspection and may not become apparent for weeks or months after completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a patent defect?

A

A defect found my reasonable inspection. Contractor has to rectify during the defects rectification period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Under JCT M/W16 what is the length of time for defects period?

A

3 months.

6 months in SBC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Under JCT M/W when is final account to be determined.

A

within 3 months of practical completion date. Within 28 days of receipt of all info from contractor.

17
Q

What certificates are up to final certificate stage?

A
  • interim payment certificates at monthly intervals (cl 4.3);
  • practical completion certificate (cl 2.9, or 2.10 in MWD16);
  • interim payment certificates following practical completion, including release of half of the retention (cl 4.3);
  • certificate of making good (cl 2.11, or 2.12 in MWD16).
18
Q

What is the length of time in which the CA advises the contractor of defects?

A

Within 14 days of the end of the rectification period.

19
Q

How does SBCC M/W16 deal with final certificate?

A

Contractor must issue certificate 3 months from date of Practical Completion certified by the CA. Due date for payment will be 28 days after receipt date of info. Payment must be made to the contractor within 5 days of due date.

20
Q

How does SBCC deal with non completion?

A

Provided relevant notices have been issued the CA may deduct monies owed from the next payment certificate or recover what is owed as debt. CA is not required under M/W to issue a certificate of non completion but best practice to put in writing.

21
Q

What is the process for dealing with defects under SBCC M/W?

A

If defects found the CA must notify the contractor within 14 days of the date of expiry of the defects period. The contractor must attend and repair at no cost to the client. Once repairs are done and defects period the CA can issue a certificate of making good.

22
Q

What is a Prime Cost?

A

Prime cost is a cost allowance made for works by a nominated subcontractor. The main contractor will likely apply a & uplift for attendance fees.

23
Q

What is a Provisional Sum?

A

Provisional sum is an allowance for an element of work that has been defined in sufficient detail to allow the contractor to make an allowance for it within their cost.

24
Q

What is an undefined provisional sum?

A

An undefined provisional sum is one that is not well defined and one which the contractor can not be expected to have made an allowance for within their costs.