APC Academy - Contract Administration Flashcards
What is an Extension of Time?
Claim made by the contractor due to a relevant event which has caused a delay resulting in the contractor being unable to complete works as per the contractural date.
What are relevant events?
Under JCT the following are relevant events:
• instructions/variations
• deferment of possession of the site
• suspension
• works by others (which would include works by
statutory undertakers)
• unusually adverse weather; and
• events causing delay that neither party could
prevent or foresee (which would include civil
commotion, terrorism and strikes, if these are
‘Employer’s risks’ under clause 80.1)
How did the contractor submit their claim?
Contractor must submit written delay notice in accordance with clause 2.7. Delay notice must set out the circumstances and the relevant event that caused the delay. Contractor must state the effects of delay upon completion date.
What was your role in assessing the claim?
I assessed the claim in accordance with JCT suite of contracts which allows the CA to determine the claim within 12 weeks. (although M/W doesn’t set that out). T
I advised client and contractor that the claim was fair and reasonable and that on completion of works the claim would be assessed.
What is loss and expense?
Loss suffered as a result of variations.
What is a concurrent delay?
delay involving two or more events.
What is a variation?
As per clause 3.6 a variation is defined as “an omission, change or other change to the works or manner in which they are to be carried out”.
How are variations valued?
using any relevant priced specifications, schedule or contractors schedule of rates.
How did you agree on valuations?
priced obtained from contractor was discussed and agreed with client prior to agreeing with contractor and CVI issued.
When are interim payments due?
Typically one month after commencement and at monthly intervals.
What is included within a valuation?
The value of works completed to date and the value of materials and goods onsite.
*no provision for value of materials offsite.
How was the delay at your Netherbank Project measured?
By comparing actual progress achieved onsite with planned progess shown on the programme of works.
What is a latent defect?
A defect that cant be determined through reasonable inspection and may not become apparent for weeks or months after completion.
What is a patent defect?
A defect found my reasonable inspection. Contractor has to rectify during the defects rectification period.
Under JCT M/W16 what is the length of time for defects period?
3 months.
6 months in SBC