Case Study Questions Flashcards

1
Q

What is value engineering?

A

Value engineering is a systematic approach used to analyze the functions of a project or product with the aim of achieving the necessary functions at the lowest possible cost while maintaining quality, performance, and safety standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is value management?

A

Value management involves a structured process of understanding and defining the value objectives of a project, identifying and evaluating alternative solutions to achieve those objectives, and selecting the most effective and efficient solutions to maximize value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you decide on your contingency?

A

I decided on the contingency by considering various factors such as the level of risk associated with the project, the complexity of the work involved, historical data from similar projects, and the client’s risk appetite. Additionally, I benchmarked other projects of similar nature to understand the appropriate level of contingency to apply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What did you consider around acceleration and what is your understanding of it?

A

Acceleration refers to the process of speeding up the project timeline or specific activities within the project to meet deadlines or mitigate delays. I considered the feasibility of accelerating critical path activities by engaging with design consultants to understand their commitments and potential constraints. This involved resequencing activities, negotiating incentives for early completion, and exploring options for fast-tracking critical path activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What materials did you consider for early procurement?

A

I considered procuring various office components such as screens, desks, ergonomic chairs, kitchen equipment, and bomb-proof windows required for the Mercury House project. These materials were essential for the refurbishment and fit-out of the office space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What else could you use instead of vesting?

A

Instead of vesting, alternative options for securing early procured materials include leasing storage space off-site, utilizing existing storage facilities within the client’s organization or subcontractors, or negotiating with suppliers for delayed delivery options to align with project timelines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is vesting and who is responsible?

A

Vesting refers to the process of transferring ownership or possession of procured materials to the client or their designated entity. The responsibility for vesting typically lies with the project manager or procurement manager, who oversees the logistics of receiving, storing, and managing the materials on-site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you carry out the forecast on your project?

A

I carried out the forecast by meticulously analyzing the project budget, identifying potential cost drivers and risks, and collaborating with various stakeholders to understand their requirements and constraints. This involved regular cost reporting and monitoring, reforecasting based on updated information, and aligning forecasts with the project timeline and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you identify the materials for early procurement?

A

I identified materials for early procurement by conducting a thorough assessment of the project requirements, consulting with the project delivery team, and understanding the lead times and availability of materials from suppliers. This involved analyzing the project schedule to determine critical items that could be procured in advance to mitigate delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the advantages of early procurement?

A

Early procurement allows for timely acquisition of critical materials, reduces lead times, minimizes project delays, provides greater flexibility in scheduling, and enables better cost management through favorable pricing negotiations with suppliers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

At which stage did you do the cost plan?

A

The cost plan was initiated at the early stages of the project, specifically at GRIP Stage 2, which is equivalent to RIBA Stage 2 in the rail sector. This allowed for comprehensive cost planning and forecasting to inform decision-making and budget allocation throughout the project lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an order of cost estimate?

A

An order of cost estimate is an early-stage cost estimation process used to provide a preliminary assessment of the likely cost of a project based on limited information. It serves as a basis for budgeting and decision-making during the initial stages of project development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a cost plan?

A

A cost plan is a detailed breakdown of the anticipated costs associated with a construction project. It includes estimates for various elements such as materials, labor, equipment, overheads, and contingencies, and serves as a baseline for managing and controlling project costs throughout its lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why was only one tender used for concept design?

A

Only one tender was used for concept design to expedite the procurement process and avoid delays in project commencement. This decision was made based on the urgency to initiate design activities and the availability of the selected consultant to meet project timelines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you ensure money for value for one tender?

A

To ensure value for money with a single tender, I would rigorously review and assess the submitted tender against project requirements, benchmark the tendered prices against industry standards and previous projects, negotiate with the consultant to optimize costs, and ensure transparency and accountability in the procurement process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why were the 12 weeks of additional procurement and tendering a problem?

A

The 12 weeks of additional procurement and tendering posed a problem due to the potential impact on project timelines and funding allocation. Delays in procurement could result in project delays, increased costs, and challenges in meeting critical deadlines, particularly given the urgency of the ECR relocation.

17
Q

Did you descope or value engineer?

A

Yes, I implemented value engineering initiatives to optimize project costs without compromising quality or functionality. This involved reviewing the scope of work and identifying opportunities to reduce costs through more efficient design solutions, alternative materials, or streamlined processes.

18
Q

Was the programme acceleration feasible in the first place?

A

While programme acceleration was considered, its feasibility depended on various factors such as the nature of critical path activities, availability of resources, and constraints faced by design consultants. Despite efforts to accelerate the programme, limitations in resource availability and external commitments impacted the feasibility of achieving significant acceleration.

19
Q

For advance payments how did you calculate value for money for this option?

A

To calculate value for money for advance payments, I assessed the potential benefits of early payments against the associated risks and costs. This involved analyzing the opportunity cost of tying up funds, evaluating the financial stability and track record of the consultant, and negotiating favorable terms and conditions to mitigate risks

20
Q

Did you account for advance payment bonds required and other contractual provisions to be added to the works contract?

A

Yes, I accounted for advance payment bonds and other contractual provisions as part of the procurement process. This involved reviewing contractual agreements, ensuring compliance with legal and regulatory requirements, and negotiating terms and conditions that safeguarded the client’s interests and mitigated risks associated with advance payments.

21
Q

What were the results of the value engineering efforts on the project’s budget and timeline, and how did this align with the client’s objectives for cost and quality?

A

The value engineering efforts resulted in a reduction in project costs while maintaining quality standards and aligning with the client’s objectives for cost efficiency. By optimizing design solutions, streamlining processes, and negotiating cost-effective solutions with consultants, the project was able to achieve significant cost savings and mitigate budget overruns, thereby enhancing the overall financial health of the project.

22
Q

Stages 0-1 are very vital in order to build up the inception stage for the design and understand the client brief. How would you advise on removing that from the fee/scope of works?

A
23
Q

You mentioned above that Network Rail did not have the place to store the early procured materials on site, how did you manage to store the early procured materials and insure them?

A

To address the challenge of storage for early procured materials, I explored alternative solutions such as leasing off-site storage facilities, utilizing existing storage space within Network Rail’s organization or subcontractors, or negotiating with suppliers for delayed delivery options aligned with project timelines. Additionally, appropriate insurance coverage was obtained to mitigate risks associated with storing the materials off-site or on-site.

24
Q

Can you elaborate on how your reforecasting efforts helped to reallocate the project funds more effectively? What impact did this have on the project’s overall financial health?

A

Reforecasting involved a meticulous review of project costs, identification of potential risks and opportunities, and adjustment of budget allocations to align with evolving project requirements. By regularly monitoring costs, reassessing priorities, and collaborating with stakeholders, I was able to reallocate project funds more effectively to areas of critical need. This proactive approach helped mitigate budget overruns, optimize resource utilization, and ensure that funds were allocated strategically to maximize project outcomes. The impact of these reforecasting efforts on the project’s overall financial health was significant, as it enabled better cost control, minimized variances, and enhanced transparency in budget management. Ultimately, it facilitated the achievement of project objectives within the allocated budget and timelines.

25
Q

Why would you use a percetage for contingency instead of calculating based on a series of likely events and their corresponding costs?

A

While calculating contingency based on likely events and their corresponding costs may provide a more tailored approach to risk management, using a percentage for contingency offers several advantages.

Firstly, it simplifies the budgeting process by providing a standardized method for allocating contingency across different projects. Secondly, it provides a cushion to account for unforeseen events or uncertainties that may not be explicitly identified during project planning. Additionally, using a percentage allows for flexibility in budgeting and can accommodate changes in project scope or requirements without the need for constant adjustments to the contingency amount. However, it’s essential to supplement percentage-based contingency with qualitative risk assessments and ongoing monitoring to ensure that it adequately addresses project risks and remains aligned with project objectives.

26
Q

Reflecting on the project, what would you have done differently in terms of procurement strategy to better manage time constraints and budget limitations?

A

Reflecting on the project, I recognize the need for a more proactive and strategic approach to procurement to better manage time constraints and budget limitations. One potential improvement would be to prioritize early engagement with suppliers and contractors to streamline procurement processes, negotiate favorable terms, and identify potential risks or constraints upfront. Additionally, leveraging competitive tendering more effectively, exploring alternative procurement routes, and implementing robust contract management practices could help mitigate delays and ensure cost-effective delivery of project requirements. By aligning procurement strategy more closely with project objectives and constraints, future projects can benefit from improved efficiency, reduced risk, and better overall outcomes.

27
Q

Given the ethical implications of project delays and budget mismanagement, how did you ensure transparency and maintain trust with your client throughout the project?

A

Transparency and trust are paramount in project management, especially when faced with challenges such as delays and budget constraints. Throughout the project, I maintained open and honest communication with the client, providing regular updates on project progress, budgetary issues, and any challenges encountered. By proactively addressing concerns, soliciting feedback, and offering solutions to mitigate risks, I fostered a collaborative relationship based on mutual trust and understanding. Additionally, I ensured that all decisions and actions were guided by ethical principles, with a focus on delivering value for the client while adhering to budgetary and timeline constraints. This commitment to transparency, integrity, and accountability helped maintain trust and confidence in my ability to effectively manage the project despite the challenges encountered.

28
Q

What type of vesting was used? What else could you have considered?

A
29
Q

You mentioned you implemented programme acceleration, under what form of contract was this and how did you ensure value for money?

A

Increasing levels of resource. Either on the same or additional work fronts.
Changing resources. These might only be available at greater expense.
Changing methods. Particularly sequencing, overlapping, hours of work, and procurement.
Changing work scope or specification

30
Q

You mentioned the client used traditional procurement. What else could you have used?

A
31
Q

Why were the cost forecasts initially not completed?

A
32
Q

Why did the client want to use negotiated tender? What would you have advised on?

A
33
Q

Was there a risk register formed?

A
34
Q
A