8. Contract Practise Level 3 Flashcards
On the CMP how did you go about uplifting rates?
What else could you have used other than CPIH?
Where can you get your data from for CPIH?
What is a completion date?
Why is programme so important under an NEC contract?
What is a risk of missing a completion date?
What is an extension of time?
What is your understanding of a Force Majeure Event?
Why did you advise liquidated damages?
What are LDs?
How would you calculate LDs?
What is a non completion certificate?
What is programme acceleration and which clause is listed under NEC?
Clause 36. The project manager request a quotation from the contractor to which the contractor has 3 weeks to provide a quote and then the PM has 2 weeks to respond
How are rates uplifted under NEC?
This would be administeted through secondary clause X1
What did you have to consider around programme acceleration