21. Contract Admin Level 1 Flashcards
What are the main suites of construction contracts?
JCT
NEC 4
ECC
ICE
FIDIC
What does ‘JCT’ stand for?
Joint Contract Tribunal
What does NEC stand for?
New Engineering Contract
What does ECC stand for?
Engineering and Construction contract
What does FIDIC stand for?
Federation internationale des ingenieurs civils
What does ICE stand for?
Institution of Civil Engineers
What is a bespoke contract?
Contract conditions that are drafted specifically for a particular project.
What the advantages of standard forms over bespoke contracts?
- They are written by legal experts.
- Rights and obligations of each party are clearly set out to the required level of detail.
- The time and expense of preparing a fresh document for each occasion is avoided.
What the disadvantages of standard forms over bespoke contracts?
They may not be appropriate to the needs of a particular project or client.
Using an inappropriate standard form for the project will cancel out any advantages.
When would use a bespoke contract rather than a standard form?
When specialist advisors can undertake the amendments as this requires great skill and knowledge.
When pricing an EOT what would you include for and what rates?
When pricing an EOT I would include costs for prolongation of site cabins, site utilities, welfare
facilities, management staff, inefficient use of labour & plant resources, subcontractor mobilisation costs, head office, finance charges & loss of profit
Explain the relative advantages & disadvantages of the NEC and JCT?
Advantages of the JCT Suite of Contracts:-
o They are considered by many as the “industry standard,” therefore they offer familiarity.
o They cover most forms of procurement and building types through the various impressive ancillary documents to support the main forms.
o They are comprehensive in detail and considered by many to be fair and reasonable and not loaded in favour of either party.
Advantages of the NEC Contract
- They are applicable to a variety of procurement strategies,
- They offer clarity and simplicity by using:-
o Ordinary language (minimal legal jargon).
o They include flow charts to support their users.
- They act as a stimulus to good management through maintaining:-
o Up-to-date programmes which are required to be clear and precise.
o Provision of early warning procedures and risk registers.
o They Embody key features of project partnering.
o Assessment of Compensation events by applying a “rolling Final Account.”
Disadvantages of the JCT Suite of Contracts
**
- They are sometimes though to “compromise conditions,” in which they try to satisfy the interests of all parties.
- They can be considered as unnecessarily long and unnecessarily complex.**
Disadvantages of the NEC Contract
- They are often only considered to be used for civil engineering projects and partnerships.
- They have limited exposure to the market so they are therefore not fully tried and tested with supporting case law.**
What are the key differences between NEC and JCT?
- The NEC is concise and written in plain English
- There are a number of optional clauses reducing the need to amend contracts compared to the JCT
- Provision of early warning procedure and risk register encourage a proactive approach to the management of the project whereas JCT is more reactive.
- There is no QS or Employers Agent mentioned in NEC only a Project Manager who takes on both roles
- The Programme is a contract document under NEC with 25% of money being deducted on interim payments if the contractor does not submit an accepted programme at contract stage
What are the role of the parties in the NEC?
The Project Manager can be from the employer’s organisation or an external consultant.
The Project Manager represents the client and has full authority to make decisions, unless the employer has restricted his authority. The PM has the duty to be impartial and to apply the contract.
Designers prepare the work information and are not named in the NEC.
The supervisor is either from the employer’s organisation or an external consultant.
The supervisors role is to check that the works are carried out as described in the contract.
They have a similar role to the clerk of works with authority such as instructing searches or issuing
defect certificates
What is the role of the quantity surveyor under the NEC?
The role of the QS is not mentioned in the contract.
* The QS can adopt a supporting role to contractor and PM to agree cost of compensation events
despite not being formally referenced.
* Options B and D involve quantities and measurement.
* Target costs under options C and D require an audit role in open book accounting in target contracts
which the QS may be responsible for.