10. Contract Practise Level 1 Flashcards
Why are contractual documents important?
What forms of contract are you aware of?
What are the conditions of a contract?
Can you tell me how you assess an AFP
What’s a payment certificate?
What are sectional and practical completions
What’s a defect liability period?
What’s LDs?
What is a final account and how would you prepare it?
Can you tell me what a collateral warranty is?
What are liquidated damages?
A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met
What are extensions of time?
Extensions of time adjust the completion date and relieves the contractor’s liability to pay liquidated damages
What must be in place before LDs can be deducted?
Employer must issue non completion certificate and a withholding notice
What if the employer suffered no loss or damage? (Liquidated damages)
It doesn’t matter the damages can still be deducted
How do you assess Cost when assessing a CE?
Actual Defined Cost
Work already done prior to the date the project manager instructed, or should have instructed, the contractor to submit a quotation.
• The contractor needs sufficient resources to maintain full and accurate cost records, which includes its own cost and/or subcontractor’s cost.
• It may require amending traditional application payment cycles while implementing an open book arrangement, so that at any point in time the contractor is able to identify the actual cost expended by subcontractors on works already carried out.
Forecasted Defined Cost
- Second is forecasting the defined cost of work not yet done.
- The assessment of these costs requires detailed knowledge of the progress of the individual work or trade packages and a realistic estimated final account for each subcontractor.
- As there is a limited period (the default being 3 weeks) for the contractor to submit its CE quotation, the Contractor has to have a means of forecasting the cost of the change inherent in the CE.
Adjustment of Fee
• The third matter is an adjustment of the fee which, as it is a percentage addition to the defined cost, is simply dependent on ensuring that the defined cost is correctly assessed
What are delay damages?
- A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met.
- X7 in NEC3 ECC. Amount defined in Part 1 of Contract Data
- If Contractor does not achieve completion date and X7 selected then delays damages are due from Contractor to Employer
What is a Bond?
- An arrangement where a contractual duty owed by one party to another is backed up by a third party
- It must be in writing, it is common for it to be a deed
- It will contain a duration and a financial limit
- Provided by bank for a fee
What are the types of Bond?
- Performance bond
- Retention bond
- Materials off site bond
- Advance payment bond
What is a performance Bond?
- “Contract of Guarantee” whereby one party (the Guarantor) undertakes to pay damages to a second party (the Employer) arising from breach of contract by a third party (the Contractor).
- Standard value is 10% of contract sum
- To call for payment Employer must prove that the contractor has defaulted in their obligations under the main contract and that loss has been suffered
Whats is a Parent Company Guarantee?
An arrangement where the contractual performance of one company in a corporate group is underwritten by the other members of that corporate group.
How are insurances dealt with under NEC3 ECC?
- Covered under section 8 - Risks and Insurance
• Contractor provides insurance stated in insurance table and any additional stated in Contract Data unless Employer stated to provide
• In joint names and covers Contractor’s risk events from starting date until defect cert or termination cert issued
• Before start date and on each policy renewal, Contractor submits insurance certificates to PM
• Any amount not received from insurer borne by risk owner (Contractor or Employer)
• Employer can insure a Contractor’s risk, cost borne by the Contractor and vice versa
• PM submits insurance policies and Certificates to be provided by Employer to Contractor for Acceptance.
How are advanced payments covered under NEC3 ECC?
X14 Advanced Payments
o It allows the contractor to receive lump sum payment in advance
o The payments, values and dates should be set out in the contract particulars
o They may be used where the contractor incurs high costs at the start of a project
o E.g. items with long lead times or the need to purchase specialist plant for manufacturing
What are the disadvantages of Advanced Payments?
o May reduce the incentive of the contractor
o Bad for the employer’s cashflow
o Concerns over why the contractor can’t fund the expenditure – insolvency worries