Case Study - Key issue 1 Flashcards
What happens at sectional completion in the NEC
It is agreed in option Optional clause X5 sectional completion
How are cashflows produced?
with the contractor and reviewed agaisnt programme
How do you check the robustness of a contractors QS
Check the programme against the cashflow and see how the activities align with the costs
How did you review the contractors application
Applicaiton is actual costs to date, so I reviewed the subcontractor applications to ensure they had only included for completed works.
what is included wihtin a contractors application
Timesheet, site cabins, Plant and Materials, Fee & insurances
What is the Change control process on the NEC
EWN, PMI, CEs
What the benefits of using option C for Glangwili
Target cost contract, Pain gain mechanism to encourage the contractor to reduce spend
What are the negatives of using option C for Glangwili
Do not have the cost certainty of a Option A/B
Why was option C selected?
Project was part of the Welsh Health Estates frameworks, and Opiton C was the chosen Contract as part of this framework
Would you have suggested a different NEC contract Option
Potentially option A - Price contract, however I as the project was not fully designed, option C encourages the contractor to look into options to reduce costs
What measures were undertaken to achieve expenditure
Monthly reproting and cost contact with the Client financial team to keep costs low
How long does an EWN last
8 weeks
What are X clause
Optional clause to include into the contract
What are Z clause?
Secondary option clauses, which can be specifically written into the contract
How does a Contractor produce a compensation event
The can issue a NCE if the issue has raised in the past 8 weeks, PM has 2 weeks to review and then the contractor has 3 weeks to issue a CEQ and the contractor has 2 weeks to reposd to the CE
How long was site closed for?
Initally the site was only closed for a few days
In the NEC what are the provisions for closing a site
Contractor issued a EWN explaining of the situation
How do you suspend works in the NEC
Clause 91 within the contract talks about terminitation table