Case Study Flashcards

1
Q

Can you give me 3 amendments to the contract?

A

1) Amending final date for payment notice from 14 days to 28 days
2) Striking out of force majeur as a relevant event
3) The information release schedule amended to “Not Used”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the benefits of doing a Single Stage Competitive tender for this project?

A

1) Cost certainty
2) Control of design
3) Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Are there any existing building considerations when installing a new staircase?

A

1) Structure
2) Fire safety as the new opening
3) MEP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why did the Client initially set a budget before you did an estimate? How can this be avoided?

A

The Client had set a budget as they wanted this to be a target for us to achieve.

This can be avoided by having a more active involvement in the earlier stages of design and advising the Client on the appropriate budget through OCE’s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Please explain your advice to your Client regarding discounting of Tenderer’s 1 and 3?

A

I advised my Client that removing the tenderer posed a significant risk to the competitive nature of the tender. I informed them that they could be removing the lowest tenderer or highest quality tenderer from the process.

I acknowledged that they were late, and informed my Client we could keep them in the process to view what their bid would be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What risks does removing a tenderer present to your Client?

A

Removing the lowest tenderer.

Removing highest quality contractor.

Damaging relations with the Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Does removal of feature lighting not represent scope cut?

A

No, because the Client is still gaining a wall finish, just a different specification which has the same function, achieves the same performance, and has the same quality from the Client’s perspective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did the VE post-tender differ to the VE you did pre-tender?

A

My VE was sufficient pre-contract however the tenders came in overbudget and there was a need for further VE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you act ethically?

A

I acted with honesty and integrity, regularly communicated with my Client, followed QMS procedures and used standard / best practice templates to ensure quality in the document I produced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you briefly summarise the 3 key lessons you learnt from this project that you would take forward for future projects?

A

1) When undertaking a competitive tender, it’s essential the competitive nature is maintained.

2) Avoid overlapping design and cost planning.

3) Have a more active involvement in the earlier stages of design when advising on budgets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When were you engaged on the project, did you not have the opportunity to inform the feasibility stage to inform the budget rather then at Stage 1 or 2?

A

I was engaged from Stage 1. The Client had set the budget of £205ft2 as a target, I informed them in my OCE that this budget was not sufficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Regarding the time constraints due to lease expiry, Could alternative procurement strategies have been considered to mitigate this?

A

The mitigation methods were:

  • D&B Contract
  • Negotiated procurement

Although the Client wanted to retain control of the design, and wished to tender go to a competitive tender to get the best possible price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What VE was considered?

A

1) Adjusting the layout of glazed partitions
2) Half height tiling in lieu of full height tiling to W/C’s.
3) Vinyl flooring instead of timber to kitchens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why was the budget different from the market testing?

A

I implemented target rates for the design team to adjust their spec too.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What other strategies could you have implemented in lieu of the design teams target ceiling finishes?

A

Provisional sums

Prime costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Talk to me about the increase from Stage 2 Budget to Stage 3 as this increased further, ditto stage 4. Why was this not accounted for? What contingency is used to account for this?

A

Stage 2 to 3, the increase was largely due to the increase in professional fees and ceiling finishes. Design development risk covered the ceiling finishes, but not the increase in design fees.

17
Q

What was the difference between Tender 1 / 2 / 3? Why the £ spread…. Where they all complaint? Other than time.

A

The £ spread was due to them pricing the items differently. They were all compliant, other than tenderer 1 being late.