What are the different RIBA Design Stages?
Stage 0 - Strategic Definition (Site Appraisal)
Stage 1 - Preparation & Briefing (Project Brief)
Stage 2 - Concept Design (Architectural Concept & Cost plan - planning submission)
Stage 3 - Spatial Coordination (Architecture & Cost plan defined better)
Stage 4 - Technical Design (PCSA with contractors)
Stage 5 - Manufacturing & Construction (Build)
Stage 6 - Handover (Snagging)
Stage 7 - Use (post occupancy evaluation)
What is the current status of the change in regulation for Document B?
DLUHC on the 29th March 2024 released proposed amendments to Document B which propose that all new residential buildings over 18m will require a second staircase
These changes shall come into place on the 30 September 2026. Any new building that submits an initial notice ahead of this date is not subject to the amendments.
The second staircase does not need to include an evacuation lift, as following a cost benefit analysis which highlighted the net impact of including an evacuation lift would be c. £1.3bn, and unknown positive impact, there it is not required.
What is DLUHC’s Role?
Department for Levelling Up, Housing & Communities. Ministerial department for the government.
Responsible for housing, communities, and local government in England and the levelling up policy.
What is process for changing Building Regulations?
- Release consultation of proposed amendments
- Release a circular letter
- Highlight transitional period
- Highlight proposed amendments.
What are the building regulations?
Building Regulations 2010, build on the Building Act 1984. Set out required standards for building work.
What is approved document B?
Guidance on Fire Safety in buildings:
- Warnings & Escape
- Internal & External fire spread
- Access and facilities for the fire service
What is the difference between a project brief and a development brief
The purpose of development briefs is to stimulate interest in development sites whilst project briefs is to influence the form that a desired development will take
Who are Premier? and what is a Homeowner insurance provider?
Premier are an insurance provider that my client uses. They provide the insurance for the residential units.
What were some the development costs as part of the Development Appraisal for H11b?
Construction Costs = £114 (trying to get down to £112m).
Prof Fees = 9%
Sitewide Costs = £54m
Sales & Marketing = 5%
Contingency = 3% (construction risk taken into account within construction cost)
How was GDV calculated for H11b?
Sales value per sf was a blended £1,350 multiplied by the saleable area (NIA)
Why was H11b no longer viable?
Construction costs had increased, but GDV had decreased as NIA had reduced. NIA reduced by 3%.
What is GRC?
Glass Reinforced Concrete (fibre-reinforced concrete). Often used in exterior building façade panels and as architectural precast concrete
What was the building techniques for each block?
Tower = Unitised panels made of GRC & aluminium
Mansion = Hand laid brick (instead of precast)
What is a Section 96A? What is deemed “non-material?
Section 96A from the Town and Country Planning Act 1990.
Non-material is deemed by the council
What are some other ways to adjust a planning application?
Section 73 of the Town and Country Planning Act 1990. Can adjust conditions of approved applications