Business Knowledge of IA: Business Acumen Flashcards
Fewer levels of authority, a shorter chain of command, and a wider span of control are characteristics of what type of organizational structure?
- Hierarchical
- Decentralized
- Centralized
- Hybrid
2- Decentralized
Rationale
A decentralized structure, also called a flat structure, is characterized by decision making dispersed in the lower levels of the organization, giving employees more freedom to take action and more autonomy. A centralized structure, also called a hierarchical, bureaucratic, or traditional structure, is one in which there are several levels of authority, a long chain of command, and a narrower span of control.
For organizational areas where processes/subprocesses potentially exist across functional lines, what is the benefit of using secondary links in a risk by process matrix?
- They link objectives to their relevant policies and procedures.
- They help show how processes are interrelated and impact each other.
- They help show the direct area impacted by failures in compliance and control.
- They furnish audit trails for use in audit programs that cross functional lines.
2- They help show how processes are interrelated and impact each other.
Rationale
Secondary links between processes and risks help show how processes are interrelated and affect one another. There could be any number of secondary links. The other three answer choices are not elements generally included or highlighted in detail in a risk by process matrix.
A small furniture-manufacturing firm with 100 employees is located in a two-story building and does not plan to expand. The furniture manufactured is make-to-stock rather than being special-ordered or custom-made. Considering these facts, the most common structure for this organization would be
- functional departmentalization.
- matrix organization.
- product departmentalization.
- divisional organization.
1- functional departmentalization.
Rationale
Organization by function is common to almost all firms at some level. It avoids duplication of effort and allows for specialization and supplied training.
Why are program evaluation review technique (PERT)/critical path management (CPM) charts useful for managing complex projects?
- Their simplicity allows for easy schedule modifications.
- They provide a basis for scheduling when tasks will be executed.
- They divide each project into sequential activities with estimated start and completion times.
- They identify and prioritize tasks that must be completed on time for the whole project to be completed on time.
4- They identify and prioritize tasks that must be completed on time for the whole project to be completed on time.
Rationale
PERT/CPM charts are used for large, complex projects that have a high degree of inter-task dependency. They graphically illustrate the critical path, which determines the total time required to complete the project and the critical activities on that path.
Projects can vary in duration and complexity, but most share similar characteristics. Which of the following is a characteristic of most projects?
- Doesn’t define a start date or target completion dates
- Includes a series of tasks and activities with a stated objective
- Has unlimited funding and resources
- Initiated at the request of regulators or as a result of new regulations
2- Includes a series of tasks and activities with a stated objective
Rationale
The majority of projects have clear start and end dates, a specific quantity of allocated resources, and a series of tasks and activities that allow it to reach its stated objective. Some projects (but not most) would be initiated as a result of new regulations or to meet compliance requirements.
A matrix organization would be most appropriate for
- a company operating a set of geographically dispersed telephone call centers that provide technical support.
- a company that starts several complex, multidisciplinary engineering and construction projects each year.
- a retail company that sells to customers through multiple stores located in shopping malls as well as through a website and mailed catalogs.
- a company that provides temporary staffing to a wide variety of commercial and governmental agencies.
2- a company that starts several complex, multidisciplinary engineering and construction projects each year.
Rationale
A matrix organization that would assign specialists as needed to various projects would be appropriate for such a company.
____________ is the process of planning, organizing, directing, and controlling an organization’s resources (people, equipment, time, money) to achieve objectives of a temporary endeavor.
- Project management
- Organizational design
- Engagement planning
- Strategic planning
1- Project management
Rationale
A project is a specific temporary endeavour undertaken to achieve a particular objective or objectives. Project management is the process put in place to achieve a project’s objectives.
What is usually considered the differentiating factor in determining core vs. non-core activities of an organization?
- Competitive advantage
- Extent of process documentation
- Key controls determination(s)
- Organizational chart inclusion
1- Competitive advantage
Rationale
Competitive advantage is usually the differentiating factor in designating core vs. non-core activities of an organization. Key controls determinations could have applicability to both core and non-core activities. Process documentation can vary greatly between activities and is not the determining factor in judging core vs. non-core activities. Both core and non-core activities can be included on a functional organization chart.
Once an adequate understanding of a business process (and related subprocesses) and objectives has been attained, the auditor’s next step typically involves
- prioritizing key controls for testing.
- determining the existence and extent of process audit trails.
- identifying and assessing risks to the achievement of objectives.
- developing or updating the audit program for testing purposes.
3- identifying and assessing risks to the achievement of objectives.
Rationale
Identifying and assessing risk would be the next major step for an auditor. Prioritizing key controls comes after (or as a result of) the risk assessment process. Audit trails may be considered in the upfront business process understanding and analysis phase and/or as part of control activity specifics identification. Audit programs are developed or updated after risk assessment, control activity specifics, and audit trail determinations are completed.
What is a major advantage of decentralized organizations?
- They have fewer managers than centralized organizations.
- They encourage increased initiative among employees.
- They streamline organizations and eliminate duplication of resources.
- They are easier to control.
2- They encourage increased initiative among employees.
Rationale
Increased initiative normally is associated with decentralized organizations.
A bank is designing an on-the-job training program for its branch managers. The bank would like to design the program so that participants can complete it as quickly as possible. The training program requires that certain activities be completed before others. For example, a participant cannot make credit loan decisions without first having obtained experience in the loan department. An appropriate scheduling technique for this training program is
- PERT (program evaluation review technique)/CPM (critical path method).
- queuing theory.
- sensitivity analysis.
- linear programming.
1- PERT (program evaluation review technique)/CPM (critical path method).
Rationale
PERT and CPM are techniques for scheduling interrelated time-series activities and identifying any critical paths in the series of activities.
What organizational structure groups organizational work into specialized units and jobs?
- Compartmentalization
- Decentralization
- Specialization
- Departmentalization
4- Departmentalization
Rationale
Both centralized and decentralized organizations use departmentalization but in different ways and to different degrees. Departmentalization may use grouping classifications such as product, geographic, process, or customer. In addition, functional, divisional, and matrix structures are all classification groupings that result from departmentalization.
What additional dimension of project management is depicted in Gantt charts as compared with flowcharts?
- Activity steps
- Time
- Resource allocation
- Cost
2- Time
Rationale
Gantt charts are a popular project management tool for planning and scheduling projects. They outline all of the tasks involved in a project and their order, shown against a time scale. Gantt charts show the time dimension of activities.
What is a major disadvantage of a matrix structure?
- Work conflicts due to dual reporting relationships
- Low employee participation
- Less efficient use of resources
- Loss of economies of scale
1- Work conflicts due to dual reporting relationships
Rationale
In a matrix structure, an employee may report to a functional head as well as a manager from another department on a special project/assignment. The matrix structure permits greater flexibility and use of resources. However, there can be accountability and work conflict issues because of the dual reporting relationship.
The following information applies to a project.
Immediate Activity Time (Days) Predecessor
A) 5 / None
B) 3 / None
C) 4 / A
D) 2 / B
E) 6 / C, D
Based on the information given, the earliest completion time for the project is
- 11 days.
- 14 days.
- 15 days.
- 20 days.
3- 15 days.
Rationale
There are two different activity paths listed: 5 + 4 + 6 = 15 days and 3 + 2 + 6 = 11 days. The longest path, which is called the critical path, determines the total time required to complete the project. Therefore, the earliest completion time for this project is 15 days.
A project manager is developing a schedule for a complex project that involves many different phases, tasks, and departments. Which of the following will be most helpful in this effort?
- Sensitivity analysis
- Process analysis
- Project charter
- Network analysis
4- Network analysis
Rationale
Network analysis is a graphical representation of a project’s tasks and schedule. It involves evaluating the network of tasks and functions that contribute to a project in order to determine the most efficient path for reaching the project goals.
The network below describes the interrelationships of several activities necessary to complete a project. The arrows represent the activities. The numbers between the arrows indicate the number of months to complete each activity. What is the shortest time to complete the project?
A-B: 2
B-D: 1
D-F: 2
A-C: 3
C-D: 3
C-E: 2
E-F: 1
- 8 months
- 6 months
- 5 months
- 14 months
1- 8 months
Rationale
The longest path from start to end is path A-C-D-F. Since all other paths are shorter in duration than path A-C-D-F, the activities along those paths can be completed before the activities along path A-C-D-F. Therefore, the amount of time to complete the activities along path A-C-D-F, which is 8 months, is the longest set of sequential durations and the shortest overall time in which the project can be completed (the critical path).
Which source of potential competitive advantage for an organization would most likely afford the greatest opportunity for an internal audit activity to add value through its assurance and/or consulting services?
- Suppliers and raw materials
- Customer base
- Process and methodology maturity
- Supply chain and transportation
3- Process and methodology maturity
Rationale
Internal auditors can play a vital consulting and/or assurance role in supporting and strengthening risk, control, quality, and other organization frameworks from a process and methodology maturity or enhancement perspective.
Which are the primary elements of risk considered and documented as part of an auditor’s risk/control matrix?
- Magnitude and materiality
- Frequency and occurrence
- Preventive and detective
- Probability and impact
4- Probability and impact
Rationale
Probability, also called likelihood, and (potential) impact are the two primary elements of risk considered and highlighted in an auditor’s risk (impact) and control matrix, along with other components (objective, key risk, activity, and controls). Preventive and detective relate to the nature of controls. Magnitude and materiality relate more to impact but do not formally or necessarily consider (or address) probability. Frequency and occurrence relate more to probability but do not address impact.
In the context of organizational structure, what does the term “span of control” refer to?
- Line of authority in the organization
- Number of employees in management or supervisory positions
- Number of employees who report to an individual in the chain of command
- Organization’s formal decision-making framework
3- Number of employees who report to an individual in the chain of command
Rationale
The chain of command refers to the line of authority in the organization (i.e., who reports to whom), while the span of control refers to the number of employees (subordinates) who report to a particular individual. Span of control is used to determine how many subordinates can be managed effectively and efficiently by a manager or supervisor.
What is one of the first things internal auditors should do when preparing for an audit of an outsourced business process?
- Assess why a business process has been outsourced in the first place.
- Understand whether the business process has been outsourced to a local or international party.
- Determine whether the organization has a defined third-party risk management program and governance structure.
- Compare outsourced costs to in-house cost alternatives.
3- Determine whether the organization has a defined third-party risk management program and governance structure.
Rationale
The third-party risk management program provides a starting point for identifying outsourcing risk appetite, policies, roles and responsibilities, and available tools to control third-party risks.
Which component of COSO’s Internal Control—Integrated Framework sets the foundation for the overall system of internal controls?
- Control activities
- Monitoring
- Control environment
- Risk assessment
3- Control environment
Rationale
The control environment includes the governance framework of an organization and is where the “tone at the top” (including commitment to internal control) is established. Objectives are set at and from the top (which falls within the context of an organization’s overall governance framework and entity-level controls in the control environment).
If an internal auditor discovers that a project manager has been “crashing” to affect a project’s critical path, the internal auditor should also examine
- the cost of project resources against the budgeted costs.
- the ethics guidelines to determine if a conflict of interest has occurred.
- the slack time of the project.
- the expense reports of the project manager to look for unusual travel or expenditures.
1- the cost of project resources against the budgeted costs.
Rationale
The process of adding resources to shorten the length of a task on the critical path is called “crashing.” If the project manager is using this technique, it is unlikely that the project has any slack time, but the auditor should examine the cost of the resources against the budgeted costs to determine the relative costs of shortening the project’s time line in this way. The auditor can also determine whether the technique produced the desired result, which would usually be to get the project back on schedule (or some variant of that).
The project management triangle consists of which of the following?
- Scope, cost, quality, time
- Plan, scope, approach, deliverables
- Plan, execute, complete
- Scope, approach, time, quality
1- Scope, cost, quality, time
Rationale
The project management triangle is the traditional approach to performing and delivering projects. It includes four elements: scope, cost, quality, and time. A change to one of these elements impacts the other elements. This means that the elements form project constraints that compete with each other. For example, a tight time frame may mean increased cost and reduced scope or a tight budget might mean increased time and reduced scope.