Building Contracts - NEC Flashcards
What does NEC stand for?
New Engineering Contract
What does (NEC) ECC stand for?
Engineering and Construction Contract (ECC)
Can you tell me about the NEC contract?
- Suitable contract between the contractor and employer
- Suitable for any sector or industry
- There are six main options to choose from.
What are the key points to note under the NEC?
- No reference to a Qs in the contract
- PM assumes fully authority
- PM controls time and cost
- Programme is a contract document
- Requirement for parties to give EWNs
What different NEC contracts are available to you? What are the options?
- Option A: Priced with Activity Schedule
- Option B: Priced with BoQ
- Option C: Target cost with Activity Schedule
- Option D: Target with BoQ
- Option E: Cost Plus
- Option F: Management Contract
- Option G: Term Contract
What are the advantages of the NEC?
- Based on mutual trust and co-operation
- Focuses on pro-active risk management
- Contract is written in plain english.
What are the key differences between the NEC 2 & 3?
- Termination was introduced
- Option F was introduced
- Dispute resolution was clearly introduced in NEC 3 (Options W1 & W2)
- No mention of the Housing Rights and Grants Act
What are the key differences between the NEC 3 & 4?
- NEC 4 now gender neutral
- Employer has become ‘Client’ and Works Information’ becomes ‘Scope’
- Risk Register is now Early Warning Register
- There is now an alliance contract.
Can you give an overview of the NEC Option A please?
- Priced with activity schedule
- Activity schedule simplifies the administration
- Payments made against the completion of an activity
- It’s a lump sum contract
- Project defined at tender
- Suitable for traditional or D&B
Can you give an overview of the NEC Option B please?
- Priced with BoQ
- risk of carrying out the work to agreed prices borne by Contractor.
- Contractor is entitled to be paid a percentage of each BoQ line item within payment schedule.
Can you give an overview of the NEC Option C please?
- Target cost with activity schedule
- Financial risks are shared between client and contractor in agreed proportion.
- Motivates the contractor to deliver the project in the most cost effective way.
- Target cost agreed between the parties and made up of contractor’s estimate of ‘defined costs’ to over costs, overhead and profit.
- Target cost set by activity schedule
- Target moves with CE’s
- Contract uses pain/gain mechanism
Can you give an overview of the NEC Option D please?
- Target cost with BoQ
- Financial risks are shared between client and contractor in agreed proportion
- Similar to C but BoQ used.
Can you give an overview of the NEC Option E please?
- Cost reimbursable/Cost plus
- Employer largely takes the financial risk
- Contractor reimbursed for all costs
- Used where the nature of the works or scope cannot be defined.
Can you give an overview of the NEC Option F please?
- cost reimbursable management contract
-Designed/constructed by multiple sub-contractors appointed by a management contractor. - financial risk largely taken by the client
Which Contract is most risky for the client?
Option E - because the contractor is being reimbursed for cost plus fee