Building Contracts - Bespoke & JCT Flashcards

1
Q

What are the various forms of sub-contract commonly used?

A
  • JCT (Joint Contracts Tribunal)
  • NEC (New Engineering Contract)
  • FIDIC
  • Bespoke
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some considerations when selecting the most appropriate form of contract?

A

Nature of client
Cost, time, quality and risk allocation
Procurement choice
Value of work
Complexity of work
Size and location of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a bespoke contract?

A

They are tailor made to fit specific requirements of a project and often used when standard contracts are not suitable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the advantages of a bespoke contract?

A
  • Written by legal experts
  • Rights and obligations of each party clearly set out
  • Parties should be more-so familiar with the provisions of the form
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the dis-advantages of a bespoke contract?

A
  • Familiarity is decreased
  • Expensive to draft
  • Poorly drafted could lead to ambiguities
  • Clauses or provisions may be untested in court.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Have you amended a standard form of contract?

A

No. As consultants we do not have legal training and all amendments should be carried out by the legal team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does JCT stand for?

A

Joint Court Tribunal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What types of JCT are available to you?

A

o D&B
o SBC 2016
o Major Works Contract
o Minor Works Contract
o Intermediate Build Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What key project characteristics influence which JCT contract is used?

A
  1. Size, value and type
  2. Need for contractor design
  3. Certainty on final cost
  4. employer experience
  5. Programme requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When would you use a minor works contract?

A

For smaller, basic construction project procured via the traditional method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Tell me about the JCT minor works contract

A

For small basic projects, non complex
Employer responsible for design
Normally administered by architect or contract administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When would you use a JCT intermediate contract?

A

Designed for projects involving all recognised trades and skills where detailed contract provisions are needed for complex specialist work.
For contracts via the traditional method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When would you use the JCT SBC?

A

For large complex projects
Employer responsible for design
Works can be carried out in sections.
For contracts via the traditional method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When would you use a JCT major project contract?

A

Designed for large scale, major projects.
for contracts via the D&B method
Works are carried out by the contractors with experience and the ability to take greater risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When would you use a JCT D&B?

A

Designed for projects where contractor undertakes design and build. Where Contractor takes all the risk and quality only as good as the employers’ requirements. Is quick and cost certain, can be carried out in sections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When would you use a JCT Prime Cost?

A

Projects that require an early start on site
Design documents are not completed and wont be until work commenced.
suitable for projects using cost reimbursable or cost plus.

17
Q

When would you use a JCT Construction management contract?

A

Employer appoints separate trade contractors and a construction manager to oversee works for a fee.
Suitable for projects via the management method.

18
Q

What is a relevant event?

A
  • An event, on or off site which causes delay to the completion date.
    o These are variations or instructions
    o Strike
    o Terrorism
    o Suspension by contractor for non-payment
    o Force Majeure.
19
Q

What happens when a relevant event occurs?

A
  • As soon as the contractor notices a delay will occur, contractor must notify the Administrator in writing with clear substantiation with estimate of delay and why etc.
  • Contractor administrator must respond within 12 weeks.
  • If it has occurred, the contract administrator must assess the delay and issue a new completion date or EOT.
20
Q

What is force majeure?

A
  • Something which happens which is out of our control
    o War, riot, terrorism acts, contamination, civil war, bad weather etc.
21
Q

Under a relevant event, is the contractor entitled to loss and expense?

A
  • No, a claim to an extension of time only
  • Contractor will need to demonstrate loss and expense.
22
Q

What is a relevant matter?

A
  • A matter which the employer is responsible for.
  • Effects the progress of the works
  • May entitle the contractor to loss and expense.
23
Q

Example of relevant matter?

A
  • Failure to give the contractor possession of the site
  • Delays in receiving instructions
  • Disruption caused by work carried out by employer
24
Q

What is a loss and expense claim?

A

Associated with delays but can be for any event where contractor incurs a loss due to the failure of the employer (Relevant matter)

25
Q

What is key when assessing loss and expense claims?

A

It should be ACTUAL loss incurred by the contractor
Prices in the BOQ, SOR or prelims should not be used as actual costs will be more.

26
Q

Do you need an EOT for loss and expense?

A

No. loss and expense can be due without an EOT.

27
Q

What are common heads of claims with Loss & Expense?

A

Prolongation/prelims, thickening of preliminaries (extra site supervision), disruption, financial charges (interest).

28
Q

What are prolongation costs?

A

Site management, accommodation, plant etc.

29
Q

What is Partial possession?

A

Contract may allow an employer to take partial possession of part of the works before they have been completed.

30
Q

What are the key points of partial posession?

A

Not agreed in advance.
Contractor must give consent.

31
Q

Can the contractor refuse to give partial posession?

A

Yes. it can only be taken with the consent of the contractor. It may hinder the contractor’s ability to complete remaining areas.

32
Q

What are the implications of partial posession?

A

Half retention released
Contractor’s responsibility for insuring the works ends.
Employer becomes responsible for damages of the works
The defect period commences.

33
Q

What is Sectional completion under the JCT?

A

Refers to a provision within the building contract which allows different completion dates for different sections of work.

34
Q

What is the difference between sectional completion and partial posession?

A

Sectional completion - it is pre-planned and defined in the contract documents
Partial completion - Employer knows that it wants one part of the works finished in advance of the rest.

35
Q

What are the main options for insuring works under the JCT?

A

Option A - Contractor maintains and takes out joint names all risks insurance of the works out for new buildings

Option B - Employer takes out and maintains and takes out joint names all risks insurance of the works out for new buildings

Option C - Employer takes out and maintains joint names all risk insurance of the new works and existing structure and contents. Option C is for renovations.

36
Q

What are contractor’s all risks insurance?

A

Covers protection against the loss or damage of the works being undertaken.
Policy will pay for the repair or replacement of the insured works following damaged caused by an insured event.

37
Q

What are specified perils?

A

Fire, Explosion, Earthquake, Flooding etc.

38
Q

What is subrogation?

A

Allows an insurance company that has paid a loss to step into the shoes of its insured to then sue a party that may be responsible for causing the loss.

39
Q

What is a joint names policy?

A

A policy in two or more names (the contractor and the employer)