Budgets and Cost Control Flashcards
APM define budget as :
The estimation of costs, the setting of an agreed budget and managing of actual and forecast cost against the budget.
Cost planning is effectively about ?
Creating a justified and credible cost for the project and essentially a forecast of all the predicted costs of the project.
The there components of a budget ?
Base cost estimate , contingency and management reserve
Base cost estimate : This is the know cost of the project and will form the bulk of our budget as if we use to pay for such this as -
Human Resources
Accommodation
Consumables
Expenses
Capital items
It is what we believe we will need in order to implement our project management plan and execute all the project tasks, pay for all the resources and deliver output against the requirements
Contingency :
The contingency budget is a pot of money set aside and separate to the base cost edit image to pay for identified risks, or the ‘known unknowns’, effectively, it enables the project manager and their team to manage risk more effectively, as it provides them a sum of money that they can dip into to pay for any planned responses to risk .
Contingency: It does not typically require the project manger to ask for permission to use from the sponsor or steering group it is there to empower the project manager and allow them to make more?
effective decisions regarding risks without having to seek approval for additional funding to manage risk if they use the contingency budget
contingency - because we typically score risk and assign an owner based on this score we can also reflect this in our contingency using delegated authority this means ?
The project team won’t need to seek project manager approval to request access to funds to pay for risk responses , provided they remain within their delegated authority.
Management reserve: management reserve is money set aside for ‘unknowns unknowns’. Essentially…
we recognise that events may happen that couldn’t possibly have been predicted and having a funding pot of money set aside for just in case something happens will mean that we won’t need to draw money from other areas or ask for additional funding to deal with it.
Management reserve - it can be used to manage any sudden , unexpected changes in scope or direction, or any identified risk ghat have a very ?
Low likelihood of occurring but would have a manhole impact should them materialise.
Benefits of cost planning : Having a clear plan of what costs look like throughout a project will enable the project manager and their team to have more control over the project, since
the budget is one of key constraints that need to be managed
Benefits of cost planning - a well planned budget will provide a clear baseline for the project team to monitor progress against. If the tolerances are exceeded or even tending to be exceeded then the project manager and this team can ?
Take proactive action to intervene and keep the budget on track
Benefits of cost planning - A key document generated as part of scope is the Cost Breakdown Structure (CBS). If we have a defined and documented budget we can ?
Compare our actual cost against the estimated cost from the CBS, allowing us to assess our estimates and compile lessons learned for future decisions
Benefits of cost planning - A well defined budget can also help demonstrate the need for ?
Funding, helping to justify expenditure and can strengthen the business case .
Cost control terminology -
Committed - money that is
Legally agreed to be paid but has not yet been spent. Effectively we are contractually bound to pay someone,
So even if the project were to close early we will still need to pay
Cost terminology - Accrual
An accrued cost is money owed for work done but has not yet been invoiced. This means the money is spent , even it if remains in our account as we will need to pay for the work that has been done and are awaiting the invoice