BEC MCQ 6.2 Flashcards

1
Q

Comparing the project work completed to date to the baseline defined in the plan occurs

A

In the monitoring phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Baseline is developed during

A

Planning process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project work activities are completed during

A

Implementation process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Baseline includes

A

Project deliverables
Amount of time required to complete the project
Attributes to be excluded from the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Major process undertaken by a project manager

A

Project authorization including securing a project character and a statement of work is a major process undertaken by project manager
Project planning including development of the course of action is a significant process undertaken by the project manager
Closing or otherwise securing agreement that the project objectives have been met is major process undertaken by project manager
Project manager is responsible for project administration on a day to day basis including indentifying and managing internal and external stakeholder expectations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project members responsibility

A

carrying out the work and producing the deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project sponsor

A

Interfacing between the organization and project itself is the responsibility of project sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Approving project deliverables

A

is the responsibility of executive steering committee. He is the individual at the executive level of management who is responsible for funding and resource allocation to the project. The role of project sponsor includes responsibility of overall project delivery. He will not be reporting to board of directors but to the steering commitee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Stages in project management

A
Authorisation
Planning
Implementation
Monitoring
Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Planning

A

Planning involves all the activities necessary to determine the scope of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Implementation

A

Assure quality activities that are necessary to complete the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Risk

A

Trade off between risk and return

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Methods of estimating cots

A

Judgement- Manager consider a combination of historical information and cost of materials and labor
Parametric estimation- Statistical estimation between historical costs and other variables. Examples includes Regression analysis and learning curve model.
WBS- estimate- Bottom up analysis
Three point estimates- Range of cost estimates
Reserve analysis-Monetary padding for uncertain cost estimations
Project management software- Include a feature that can be estimated to project costs
Vendor bid analysis- Vendor will bid on the work and the contract will be awarded
Earned value management- Planned value, earned value, actual cost, Estimate at completion, Cost performance Index=EV/ AC IF CPI is less than one then the project is over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Deleverables

A
The product or service the project must deliver
S-Specific 
M-Measurable
A- Attainable
 R- Relevant
T- Time based
How well did you know this?
1
Not at all
2
3
4
5
Perfectly