B Flashcards
What is the first step in locating corner stakes for a building?
Establish a baseline
How do you use 3-4-5 rule to establish a 90-degree corner?
Measure out along the reference line four feet, measure the opposite line 3 feet, then measure between those two points. If the distance is 5 feet, you don’t have a 90 degree corner and you’ll have to adjust the angle between the lines accordingly.
Roughly how far from the building’s outside corners do you place the batter boards and why?
Minimum of 4 feet; so equipment operators and builders can do their work.
What’s the customary allowance for a working space for constructing forms?
2 feet
What do you use to clean rock or concrete surfaces before you place fresh concrete on them?
Stiff brooms and compressed air or water.
Why do you moisten a clay subgrade before you place fresh concrete on it?
To help subgrade from extracting moisture from the concrete.
Before you place concrete on a sand or gravel subgrade, what do you use to keep from extracting moisture from the mix and making the concrete set too fast?
Burlap, tarpaper, or polyethylene. Overlap the burlap and moisten it, lap the tarpaper at least an inch, and lap the polyethylene at least 12 inches.
What problems could a puncture in the vapor barrier cause?
Moisture could get trapped between the concrete and the barrier, resulting in shifting, cracking or splitting.