During construction of a new building, or in spaces being added to an existing building, atleast ONE permanent stair shall be brought within how many FEET or how many FLOORS below the WORKING DECK?
40 feet or 4 floors
Whenever construction or demolition work reaches a height greater than ___ ft, atleast one elevator or a hoist shall be kept in readiness for FD use
75
The maximum distance between the highest accessible floor from a temporary elevator or hoist & the working deck of the building under construction or demolition shall be no more than ___ ft or ___ floors
75/7
In concrete construction the working deck is the? In steel construction the working deck is?
Floor being formed