Q

During construction of a new building, or in spaces being added to an existing building, atleast ONE permanent stair shall be brought within how many FEET or how many FLOORS below the WORKING DECK?

A

40 feet or 4 floors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Whenever construction or demolition work reaches a height greater than ___ ft, atleast one elevator or a hoist shall be kept in readiness for FD use

A

75

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The maximum distance between the highest accessible floor from a temporary elevator or hoist & the working deck of the building under construction or demolition shall be no more than ___ ft or ___ floors

A

75/7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In concrete construction the working deck is the? In steel construction the working deck is?

A

Floor being formed

The floor where the metal decking and steel components are being placed before concrete is poured