API 653: Tank Inspection, Repair, Alteration, and Reconstruction Flashcards

1
Q

What type of weld joint must be used when reconstructing a tank shell? (API 653-14, Section 8.2.2)

A

All new shell joints shall be butt-welded joints with complete penetration and complete fusion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should be the minimum dimension for a replacement shell plate? (API 653-14, Section 9.2.2.1)

A

The minimum dimension for a replacement shell plate is 12 in. or 12 times the thickness of the replacement plate, whichever is greater.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are acceptable shapes for replacement shell plates? (API 653-14, Section 9.2.2.1)

A

The replacement plate may be circular, oblong, square with rounded corners, or rectangular with rounded corners except when an entire shell plate is replaced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Prior to welding new vertical joints, what must be done to existing horizontal welds that contact the new vertical joint? (API 653-14, Section 9.2.2.2)

A

Prior to welding the new vertical joints, the existing horizontal welds shall be cut for a minimum distance of 12 in. beyond the new vertical joints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When installing a replacement shell plate, which joints (vertical or horizontal) should be welded first? (API 653-14, Section 9.2.2.2)

A

The vertical joints shall be welded prior to welding the horizontal joints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What type of joint should be used to install shell replacement plates? (API 653-14, Section 9.2.3.1)

A

Shell replacement plates shall be welded with butt joints with complete penetration and complete fusion, except as permitted for lapped patch shell repairs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How far from the edge of a weld joint in the annular plate ring or sketch plate must the edge of any vertical weld attaching a replacement plate be? (API 653-14, Section 9.2.3.3)

A

For shell plates of unknown toughness not meeting the exemption criteria of Figure 5.2, the edge of any vertical weld joint attaching a replacement plate shall be at 3 in. or 5t from the edge of a weld joint in the bottom annular ring or 18 weld joints in bottom plates under the tank shell.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What may be used for the closure of holes caused by the removal of existing shell openings or by the removal of severely corroded areas? (API 653-14, Section 9.3.2)

A

Lapped patch repair plates may be used for the closure of holes caused by the removal of existing shell openings or the removal of severely corroded or eroded areas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What two items must be entirely removed prior to installation of a repair plate? (API 653-14, Section 9.3.2.2)

A

Nozzle necks and reinforcing plates shall be entirely removed prior to installation of a repair plate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can lack of fusion in a weld be repaired? (API 653-14, Section 9.6.1)

A

Cracks, lack of fusion, and rejectable slag and porosity that need repair shall be removed completely by gouging and/or grinding and the resulting cavity properly prepared for welding and then welded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How should unacceptable surface defects, such as arc strikes, discovered in or adjacent to welded joints be repaired? (API 653-14, Section 9.6.5)

A

Unacceptable surface defects shall be repaired by grinding and/or welding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In a replacement shell penetration larger than NPS 4, what should be the diameter of the insert plate? (API 653-14, Section 9.8.6)

A

The minimum diameter shall be at least the greater of:

a) twice the diameter of the opening in the insert plate that accommodates the radial oriented nozzle, or
b) the diameter of the opening in the insert plates plus 12 in.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a new tank bottom is installed above an existing bottom, the spacing between existing welds around penetrations and the new bottom-to-shell weld may not meet API 650 requirements. What are three ways of altering the penetrations to meet API 650? (API 653-14, Sections 9.9.2 through 9.9.2.3)

A

1) The existing reinforcing plate may be trimmed to increase the spacing between the welds provided that the altered detail complies with the requirements of API 650, Section 5.7.
2) The existing reinforcing plate may be removed and a new reinforcing plate added except that reinforcing plate replacement is not permitted in existing stress relieved assemblies unless the requirements of 11.3 are met.
3) The existing penetration may be moved by cutting the section of the shell containing the fitting and reinforcing plate, and raising the entire assembly to the correct elevation (see Figure 9.9).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What areas constitute the “critical zone” for repairs to tank bottoms? (API 653-14, Section 3.10)

A

The portion of the tank bottom or annular plate within 3 in. of the inside edge of the shell, measured radially inward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What types of repairs are NOT allowed in the tank bottom critical zone? (API 653-14, Section 9.10.1.2)

A

No welding or weld overlays are permitted within the critical zone except for the welding of: widely scattered pits (see 4.3.2.2), pinholes, cracks in the bottom plates, the shell-to-bottom weld, welded-on patch plates, or where the bottom plate welded to the shell is being replaced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What types of repairs are allowed in the tank bottom critical zone? (API 653-14, Section 9.10.1.2)

A

Welded on patch plates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When replacing an entire tank bottom, what type of material should be used as a cushion between the old and new bottoms? (API 653-14, Section 9.10.2.1.1)

A

Suitable noncorrosive material cushion such as sand, gravel, or concrete shall be used between the old bottom and the new bottom.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When replacing an entire tank bottom, what procedures must be followed when installing and attaching the new bottom to the existing shell? (API 653-14, Section 9.10.2.1.2)

A

The shell shall be slotted with a uniform cut made parallel to the tank bottom. The cut edges in the slot shall be ground to remove all slag and burrs from cutting operations. The new bottom plate shall extend outside the shell as required by API 650, Section 5.4.2. All rules for weld spacing shall be followed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When replacing an entire tank bottom, what should be done with voids in the foundation below the old tank bottom? (API 653-14, Section 9.10.2.1.3)

A

Voids in the foundation below the old bottom shall be filled with sand, crushed limestone, grout, or concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What should be the minimum thickness of new roof plates for a supported cone roof? (API 653-14, Section 9.11.2.1)

A

The minimum thickness of new roof plates shall be 3/16 in. plus any corrosion allowance as specified in the repair specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What should be the nominal thickness of new roof plates for self-supporting roofs? (API 653-14, Section 9.11.3.1)

A

The nominal thickness of new roof plate shall be 3/16 in. or the required plate thickness given in API 650, Section 5.10.5 or Section 5.10.6, plus any specified corrosion allowance, whichever is greater.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What should be the minimum height of tank liquid above a hot tap location? (API 653-14, Section 9.14.1.2)

A

The minimum height of tank liquid above the hot tap location shall be at least 3 ft during the hot tapping operation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What type of electrode should be used for hot tap welding? (API 653-14, Section 9.14.1.3)

A

Welding shall be done with low hydrogen electrodes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What defects in shell plate preclude the installation of hot taps? (API 653-14, Section 9.14.1.5)

A

Hot taps shall not be installed on laminated or severely pitted shell plate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Hot taps are not permitted where the heat of welding may cause __________ (API 653-14, Section 9.14.1.6)

A

Environmental cracking (such as caustic or stress corrosion cracking)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

When preparing for a hot tap installation, how many shell thickness measurements shall be made? Where should they be made? (API 653-14, Section 9.14.3.2)

A

Shell plate thickness measurements shall be taken at a minimum of four places along the circumference of the proposed nozzle location.

27
Q

After completing the welding portion of the hot tap procedure, what pressure should be used to test the nozzle prior to mounting the hot tap machine? (API 653-14, Section 9.14.5.3)

A

After the valve has been installed on the flange, a pressure test at least 1.5 times the hydrostatic head shall be performed on the nozzle prior to mounting the hot tap machine, which shall be bolted to the valve.

28
Q

When bottom plates are to be reused, how should they be cut? (API 653-14, Section 10.3.2.1)

A

Bottom plates that will be reused shall be cut by deseaming of lap welds; or by cutting alongside of the remaining welds at a minimum of 2 in. away from existing welds, except where cuts cross existing weld seams.

29
Q

When roof plates are to be reused, how should they be cut? (API 653-14, Section 10.3.4)

A

Roof plates shall be cut by deseaming of lap welds, or by cutting alongside of the remaining welds at a minimum of 2 in. away from existing welds, except where cuts cross existing welds.

30
Q

If an entire tank bottom is to be reused in a reconstructed tank, how should the bottom be separated from the existing shell if there is no existing butt welded annular ring? (API 653-14, Section 10.3.2.2)

A

The bottom may be cut 12 inches from the shell, leaving the shell with part of the bottom (annular region) attached

31
Q

When shell plates are to be dismantled and reused, what are three ways in which they can be cut? (API 653-14, Section 10.3.3.1)

A

1) Any shell ring may be dismantled by cutting out existing weld seams and the heat affected zone (HAZ) of the weld. For the purpose of this method, the minimum HAZ to be removed will be 1/2 of the weld metal width or 1/4 in., whichever is less, on both sides of the weld seam.
2) Any shell ring 1/2-in. thick or thinner may be dismantled by cutting through the weld without removing the HAZ.
3) Shell rings may be dismantled by cutting vertical and/or horizontal cuts through the shell a minimum of 6 in. away from existing welds, except where cuts cross existing welds.

32
Q

If shell stiffening rings are removed, what must be done to the temporary attachment points? (API 653-14, Section 10.3.3.2)

A

The area where temporary attachments are removed shall be ground flush with the shell plate.

33
Q

If a tank shell is to be dismantled for reuse with a new bottom, where should the shell be cut from the existing bottom? (API 653-14, Section 10.3.3.3)

A

The shell shall be cut a minimum of 1/2” above the bottom plate.

34
Q

When can the existing shell-to-bottom weld connection be reused in a reconstructed tank? (API 653-14, Section 10.3.3.3)

A

The existing shell-to bottom weld connection shall not be reused unless the entire bottom is to be reused intact.

35
Q

What provisions should be made with regard to joint alignment during the reconstruction of a tank? (API 653-14, Section 10.4.2.1)

A

Provisions shall be made during the reconstruction of a tank to ensure that weld spacing requirements of Figure 9.1 are maintained. New vertical joints in adjacent shell courses, made in accordance with 10.3.3.1, shall not be aligned but shall be offset from each other a minimum distance of 5t, where t is the plate thickness of the thicker course at the point of the offset.

36
Q

What should be done with tack welds used in the assembly of vertical joints on the tank shell when the joints are welded manually? (API 653-14, Section 10.4.2.7)

A

Tack welds used in the assembly of vertical joints of tank shells shall be removed and shall not remain in the finished joint when the joints are welded manually.

37
Q

What should be done with primer coatings on surfaces to be welded? (API 653-14, Section 10.4.2.8)

A

If weldable primer coatings have been applied on surfaces to be welded, they shall be included in welding procedure qualification tests for the brand, formulation, and maximum thickness of primer applied. All other coatings shall be completely removed from the weld area prior to welding.

38
Q

Which should be welded first: bottom plate joints or shell-to-bottom joints? (API 653-14, Section 10.4.3.2)

A

The welding of the shell to the bottom (except for door sheets) shall be completed prior to the welding of bottom joints.

39
Q

What is the maximum allowable vertical butt joint misalignment when the plate thickness is 5/8 inch thick or less? (API 653-14, Section 10.4.4.1)

A

Misalignment in joints 5/8-in. thick or less shall not exceed 1/16 in.

40
Q

At what interval must the welder’s identification mark be stamped along completed weld joints? (API 653-14, Section 11.2.2)

A

The welder or welding operator’s identification mark shall be hand- or machine-stamped adjacent to and at intervals not exceeding 3 ft along the completed welds.

41
Q

What method of nondestructive examination should be used to detect shell plate laminations when adding a hot tap connection? (API 653-14, Section 12.1.2.1)

A

Ultrasonic examination

42
Q

What type of nondestructive examination should be used to examine completed welds attaching a nozzle neck to the tank shell? (API 653-14, Section 12.1.2.3)

A

Completed welds attaching nozzle neck to shell, and reinforcing plate to shell and to nozzle neck, shall be examined by the magnetic particle or liquid penetrant methods.

43
Q

What type of nondestructive examination should be used to examine completed repairs of butt welds? How much of the weld should be examined? (API 653-14, Section 12.1.3.2)

A

Completed weld repairs of butt welds shall be examined over their full length by radiographic or ultrasonic methods.

44
Q

How should the first pass of the shell-to-bottom weld be inspected? How long should this procedure take? (API 653-14, Section 12.1.6.1)

A

The first weld pass shall be examined by applying light diesel oil to the side opposite the first weld pass made. The oil shall be allowed to stand at least 4 hours (preferably overnight) and then the weld examined for wicking action.

45
Q

What should be the minimum diagnostic length of a radiograph of a weld? (API 653-14, Section 12.2.1.7)

A

The minimum diagnostic length of each radiograph shall be 6 in.

46
Q

What is the minimum duration of a hydrostatic test for a reconstructed tank? (API 653-14, Section 12.3.2)

A

That liquid level shall be held for a minimum of 24 hours.

47
Q

What is a requirement for new vertical and horizontal shell butt-welds? (API 653-14, Section 12.2.1.6)

A

New and replaced shell plate and door sheet welds shall be radiographed. All junctions between repair and existing welds shall be radiographed. If defects are found, 100 % radiography shall be performed on the repaired weld.

48
Q

Major repairs and major alterations to a tank may require a full hydrostatic test. What are six examples of the type of work that is considered a major repair or major alteration? (API 653-14, Section 3.21)

A

1) installing a shell penetration larger than NPS 12 beneath the design liquid level;
2) installing a bottom penetration within 12 in. of the shell;
3) removing and replacing or adding a shell plate beneath the design liquid level where the longest dimension of the replacement plate exceeds 12 in.;
4) removing or replacing annular plate ring material where the longest dimension of the replacement plate exceeds 12 in.;
5) complete or partial (more than one-half of the weld thickness) removal and replacement of more than 12 in. of vertical weld joining shell plates or radial weld joining the annular plate ring;
6) installing a new bottom;
7) removing and replacing part of the weld attaching the shell to the bottom, or to the annular plate ring, in excess of the amounts listed in 12.3.2.5.1 a);
8) jacking a tank shell.

49
Q

Where on the tank must an air leak test be conducted? (API 653-14, Section 12.4)

A

New or altered reinforcing plates of shell penetrations shall be given an air leak test in accordance with API 650, Section 7.3.5.

50
Q

When surveying for tank settlement during a hydrostatic test, what is the minimum number of measurement points? (API 653-14, Section 12.5.2)

A

The minimum required number of settlement measurement points is D/10, but no less than eight.

51
Q

How should roof supporting structures be dismantled? (API 653-14, Section 10.3.4)

A

Roof supporting structures shall be dismantled by removing bolts (if bolted) or deseaming the structural attachment welds.

52
Q

What should be done with tack welds when vertical joints on the tank shell are welded with a submerged-arc process? (API 653-14, Section 10.4.2.7)

A

When such joints are welded by the submerged-arc process, the tack welds shall be thoroughly cleaned of all welding slag but need not be removed provided that they are sound and are thoroughly fused into the subsequently applied weld beads.

53
Q

What is the minimum duration of a hydrostatic test for a tank that has undergone major repairs? (API 653-14, Section 12.3.2)

A

A full hydrostatic test of the tank is not required for major repairs and major alterations.

54
Q

To what types of tanks does this standard apply? (API 653-14, Section 1.1.1)

A

This standard covers steel storage tanks built to API 650 and its predecessor API 12C. It provides minimum requirements for maintaining the integrity of such tanks after they have been placed in service and addresses inspection, repair, alteration, relocation, and reconstruction.

55
Q

In case of apparent conflicts between the requirements of API 650 and API 653, which standard shall govern? (API 653-14, Section 1.1.2)

A

In the case of apparent conflicts between the requirements of this standard and API 650 or its predecessor API 12C, this standard shall govern for tanks that have been placed in service.

56
Q

Do temperature cracks in concrete seriously affect the strength of the concrete foundation? What can temperature cracks in concrete eventually result in? (API 653-14, Section 4.5.1.2)

A

Temperature cracks (hairline cracks of uniform width) do not seriously affect the strength of the concrete foundation structure; however, these cracks can be potential access points for moisture or water seepage that could eventually result in corrosion of the reinforcing steel.

57
Q

What are the 12 historical causes of tank bottom leakage listed in this document? (API 653-14, Section 4.4.2)

A

1) internal pitting and pitting rates in the anticipated service;
2) corrosion of weld joints (weld and heat affected zone);
3) weld joint cracking history;
4) stresses placed on the bottom plates by roof support loads and shell settlement;
5) underside corrosion (normally in the form of pitting);
6) inadequate drainage resulting in surface water flowing under the tank bottom;
7) the lack of an annular plate ring when required;
8) uneven settlement that results in high localized stresses in the bottom plates;
9) roof support columns or other supports welded to the tank bottom where adequate allowance for movement was not made;
10) rock or gravel foundation pads with inadequately filled-in surface voids;
11) nonhomogeneous fill under the tank bottom (e.g. a lump of clay in a sand foundation pad);
12) inadequately supported sumps.

58
Q

During hydrostatic testing, when should the final settlement measurement be taken? (API 653-14, Section 12.5.3)

A

When a settlement survey is required in accordance with 12.5.1, tank settlement shall be measured during filling and when the test water reaches 100 % of the test level.

59
Q

What are three approaches that can be used to correct tank shell and bottom settlement? (API 653-14, Section B.1.3)

A

1) localized repairs of the bottom plates,
2) partial re-leveling of the tank periphery, and
3) major re-leveling of the entire tank bottom.

60
Q

Internal measurements of tank bottom settlement can be made in an out-of-service tank by measuring along the tank diameter. What should be the maximum spacing of these measurements? (API 653-14, Figure B.2)

A

Maximum spacing of 10 ft across diameter.

61
Q

Uniform tank settlement does not induce stresses in the tank structure. However, where can problems arise when a tank undergoes uniform settlement? (API 653-14, Section B.2.2.1)

A

Uniform settlement of a tank does not induce stresses in the tank structure. However, piping, tank nozzles, and attachments must be given adequate consideration to prevent problems caused by such settlement.

62
Q

Which type of settlement poses the most severe threat to the structural integrity of a tank shell and bottom? (API 653-14, Section B.2.2.4)

A

Out-of-plane settlement is the important component to determine and evaluate in order to ensure the structural integrity of the shell and bottom.

63
Q

What is edge settlement? (API 653-14, Section B.2.3.1)

A

Edge settlement occurs when the tank shell settles sharply around the periphery, resulting in deformation of the bottom plate near the shell-to-bottom corner junction.