API-578 Flashcards
API 578 provides guidelines for a material assurance system to verify:
All alloy materials. 1.0
The material verification program specified by API 578 covers:
Only pressure-containing components. 1.0
An alloy material is any metallic material that contains alloying elements that
are added:
To improve either mechanical properties or corrosion resistance. 3.1
An inspection lot includes:
all materials from a common source, of the same material type and same heat. 3.4
For construction and repair activities a written material verification program should be established by the:
Owner/User. 4.1
The material verification program should cover PMI testing of materials:
In existing piping systems and during construction, repairs and
alterations of piping systems. 4.1
During repairs, random PMI sampling of new components is most appropriate
for:
low-risk piping systems. 4.1
Who has the responsibility to determine the extent of PMI performed?
Owner/User 4.1
During construction the Owner should consider 100% PMI of new components on:
high-risk piping systems. 4.1
Usually substituting an alloy for carbon steel does not cause a problem. But hardenable alloys may cause failure in some carbon steel systems. Which of the following process services would substituting an alloy for carbon steelnot result in a potential problem.
Benzene 4.1.1
Who is responsible to assure that the material verification program meets the guidelines of API 578?
Owner/User 4.2.1
Who is responsibility to verify the adequacy of the material verification program that is performed by material suppliers?
Owner/User 4.2.2
Who has the responsibility to review and approve the adequacy of the PMI program used by fabricators?
Owner/User 4.2.2
A mill test report:
Is an important part of the material qualify assurance program. 4.2.4
During construction, which of the following alloy components does not need to be covered by a material verification program?
Bolts, expansion joints, gaskets, and pressure containing welds need to be checked. 4.2.5
During alloy welding:
One electrode from each lot or package should be identified. 4.2.6
If alloy element(s) are contained in the flux of a welding electrode, PMI testing:
Could be conducted on a “weld button” prior to production welds. 4.2.6
New longitudinal welded alloyed pipe should:
Receive random PMI testing of weld and base metal if there is a reason to suspect problems. 4.2.6.1
PMI of autogenous welds is:
Not required if the base metal was PMI tested. 4.2.6.2
Who has the responsibility to determine the extent of PMI testing required on existing piping systems?
Owner/User 4.3.2
When prioritizing the need for PMI on existing piping systems, which of the following is not a factor to consider?
Age of the facility. 4.3.3
Incorrect substitution of carbon steel is most likely to be found in:
Chrome systems. 4.3.3.1
Which residual element in a carbon steel system has not caused increased corrosion rates in HF acid piping system?
Fe 4.3.3.2
Low silicon carbon steel can corrode rapidly when exposed to:
Hydrogen-free sulfidation. 4.3.3.4
Carbon steel can corrode rapidly in hydrogen-free sulfidation when the silicon content in carbon steel is:
< 0.10%. 4.3.3.4
The owner decides to conduct PMI testing on some existing piping systems. Which of the following is a major factor in prioritizing the pipe?
The effectiveness of the construction & maintenance practices. 4.3.3.5
Which of the following piping components is most likely to have a substitution with the wrong material?
Bolting. 4.3.4
Which of the following piping components is most likely to have a substitution with the wrong material?
6 NPS Gate valve. 4.3.4
Who has the responsibility to determine the extent of PMI testing required during repairs and alterations of piping systems?
Owner/User. 4.4.1
Who has the responsibility to evaluate the effectiveness of a PMI program during repairs and alterations?
Owner/User. 4.4.1
During repairs and alterations the Owner should:
Have a written procedure describing their PMI program. 4.4.1
PMI testing at the warehouse is:
Not a substitute for PMI testing required during fabrication. 4.4.2
In the petrochemical industry, one common material mix-up problem occurs:
When temporarily removing spool pieces. 4.4.3
Identification of materials by visual stamps or markings:
Is not a substitute for PMI testing. 5.1
How do portable X-Ray Fluorescence PMI tools work?
Radiation waves excite the materials and the material emits a
different spectrum of radiation that can be analyzed. 5.2.2
PMI tools that use X-Ray fluorescence can not detect:
carbon. 5.2.2
How does Portable Optical Emission Spectrometry determine the elements in a material?
An electric arc causes a spectrum of light to be emitted from the tested material. The light is analyzed. 5.2.3
Chemical spot testing:
Removes a small amount of surface metal that is placed in a filter paper. Small droplets of reagents are used on the sample and different colors indicated different materials. 5.2.5.1
PMI tools that use Resistivity Testing are not always able to sort:
Low chromes and 300 series stainless steels. 5.2.5.2
PMI testing equipment should be:
Calibrated as specified by the manufacturer. 5.3
All personnel performing PMI tests should be:
Knowledgeable about the operation of the PMI test equipment. 5.5
Qualifications for personnel performing PMI testing should be submitted and reviewed by:
The Owner/User. 5,5
When PMI testing indicates that an alloy is outside the range allowed on the material spec, the component can:
Be used if accepted by the Owner/User following an assessment. 6.1c
An alloy weld overlay is applied to carbon steel base metal. What will occur?
Dilution. 6.2
An alloy weld overlay is applied to carbon steel base metal. Who has the responsibility to establish the minimum alloy requirements of the asdeposited weld metal?
Owner/User. 6.2
What is the appropriate action to take when an incorrect material is located during a PMI sampling of an inspection lot?
A more extensive inspection of the lot should be considered. 6.3
A color code system for pipe is specified by:
PFI ES22. 7.1.1
Identification of materials by color coding:
Is not a substitute for PMI testing. 7.1.1
Which of the following is not required when the owner’s PMI system requires physical marking of components?
The name of individual doing the marking. 7.1.1 / 7.1.2
Marking pens should not contain chlorides or:
Sulfur. 7.1.2b
When PMI testing is conducted on a new piping system, the documentation of the PMI results should be kept:
Until piping system is removed/scrapped. 7.4