API-578 Flashcards
API 578 provides guidelines for a material assurance system to verify:
All alloy materials. 1.0
The material verification program specified by API 578 covers:
Only pressure-containing components. 1.0
An alloy material is any metallic material that contains alloying elements that
are added:
To improve either mechanical properties or corrosion resistance. 3.1
An inspection lot includes:
all materials from a common source, of the same material type and same heat. 3.4
For construction and repair activities a written material verification program should be established by the:
Owner/User. 4.1
The material verification program should cover PMI testing of materials:
In existing piping systems and during construction, repairs and
alterations of piping systems. 4.1
During repairs, random PMI sampling of new components is most appropriate
for:
low-risk piping systems. 4.1
Who has the responsibility to determine the extent of PMI performed?
Owner/User 4.1
During construction the Owner should consider 100% PMI of new components on:
high-risk piping systems. 4.1
Usually substituting an alloy for carbon steel does not cause a problem. But hardenable alloys may cause failure in some carbon steel systems. Which of the following process services would substituting an alloy for carbon steelnot result in a potential problem.
Benzene 4.1.1
Who is responsible to assure that the material verification program meets the guidelines of API 578?
Owner/User 4.2.1
Who is responsibility to verify the adequacy of the material verification program that is performed by material suppliers?
Owner/User 4.2.2
Who has the responsibility to review and approve the adequacy of the PMI program used by fabricators?
Owner/User 4.2.2
A mill test report:
Is an important part of the material qualify assurance program. 4.2.4
During construction, which of the following alloy components does not need to be covered by a material verification program?
Bolts, expansion joints, gaskets, and pressure containing welds need to be checked. 4.2.5
During alloy welding:
One electrode from each lot or package should be identified. 4.2.6
If alloy element(s) are contained in the flux of a welding electrode, PMI testing:
Could be conducted on a “weld button” prior to production welds. 4.2.6
New longitudinal welded alloyed pipe should:
Receive random PMI testing of weld and base metal if there is a reason to suspect problems. 4.2.6.1
PMI of autogenous welds is:
Not required if the base metal was PMI tested. 4.2.6.2
Who has the responsibility to determine the extent of PMI testing required on existing piping systems?
Owner/User 4.3.2