AIA CONTRACTS Flashcards
A101
SFA/ OWNER - CONTRACTOR
STIPULATED SUM
Project price is based on a fixed price. Owner assignes risk to Contractor. Suitable when scope and schedule are clear.
for large or complex commercial construction projects.
A103
SFA/ OWNER - CONTRACTOR
COST OF WORK PLUS FEE w/o GMP
used on large projects when the basis of payment to the contractor is the cost of the work plus a fee, and the cost is not fully known at the commencement of construction
A141
SFA/ OWNER - DESIGN BUILDER
when the owner contracts with a single entity to provide both design and construction.
WORK BREAK DOWN STRUCTURE (WBS)
define the phases the project will go through; developing task lists for all of the effort required in each phase
The analysis considers all staff and the hours they will work on the project
A133
SFA/ OWNER - CMc
COST of WORK PLUS FEE w/ GMP
construction manager as constructor - assumes financial responsibility of the project
coord w/ A201 and B133
A195 (2008)
SFA/ OWNER - CONTRACTOR for
INTEGRATED PROJECT DELIVERY
for a large, transitional, and integrated project delivery, and provides business terms and conditions unique to the contract.
A201 (2017)
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
sets the rights, responsibilities, and relationships of the owner, contractor, and architect.
Various design-bid-build agreements incorporate and reference this “umbrella” document.
A295
GENERAL CONDITIONS of contract for
INTEGRATED PROJECT DELIVERY
sets duties of the owner, architect and contractor, and how they will work together through: conceptualization, criteria design, detailed design, implementation Document, construction, and closeout. Requires use of BIM.
general conditions for a transitional integrated project delivery.
A305
CONTRACTOR’S QUALIFICATION STATEMENT
This questionnaire is used to provide information about a contractor’s background.
A701
Instructions to Bidders
provides relevant information concerning the detailed req of the bidding process and includes:
- Definitions
- Bidding Documents
- Consideration of bids
- Owner/Contractor Agreement
- Supplementary Instructions
- Bidder’s representations
- Bidding procedures
- Post-bid Information
- Performance/labor and material payment bonds
B101
Standard Form of Agreement Between Owner and Architect
Contract typically used with large projects in conjunction with A201-2017.
Services listed are divided into basic, supplemental, and additional services.
may be used with a variety of compensation methods, including percentage of the budget for construction cost and stipulated sum.
B195
Standard Form of Agreement Between Owner and Architect for Integrated Project Delivery
between owner and architect is used with large, transitional integrated project delivery.
C401
Standard Form of Agreement Between Architect and Consultant
used when an architect obtains consulting services.
G701
Change Order
for implementing changes in the work agreed to by the owner, contractor, and architect.
G702
Application and Certificate for Payment
when a contractor applies for payment and the architect certifies the payment is due.
Shows the contract sum to date, including the total dollar amount of the work completed and stored to-date, the amount of retainage (if any), the total of previous payments, a summary of change orders, and the amount of current payment requested.
G703
CONTINUATION SHEET
used by the contractor when listing the portions of work and scheduled values. Breaks down contract sum into potions of the work.
It is suitable for any sized project.
G704
CERTIFICATE OF SUBSTANTIAL COMPLETION
standard form for recording the date of substantial completion of the work or a designated portion thereof.
C101
JOINT VENTURE AGREEMENT for
PROFESSIONAL SERVICES
2 or more parties to provide for their mutual rights and obligations in forming a joint venture.